RFB 2024-015 Manitou Springs Midland Ave Arizona Rd Water and Sanitary Sewer Project 9.24.24.pdf

PDF 17 MB Posted

Attached to
Manitou Springs - Midland and Pawnee Design and Utility Engineering
Solicitation number
B 2024-015
Issued by
El Paso County, Manzanola Town, Colorado

About this file

The document is a Request for Bids (RFB No. 2024-015) issued by the City of Manitou Springs, Colorado, for the Midland Avenue and Arizona Road Sanitary Sewer and Water Main Replacement project. The project involves replacing water mains and sanitary sewer mains on Midland Avenue (west of Unita Road), with a pre-bid meeting scheduled for 10/4/24 at 1:00 PM at the Public Works Facility. Bid submissions are due by 10/25/24 at 2:00 PM via email, with a notice of award anticipated on 10/29/24. The project is expected to be completed within 40 working days from the Notice to Proceed, and the selected contractor will be responsible for providing project costs, mobilization time, materials, equipment, and installation.

The project is funded through state revolving funds and is subject to specific federal requirements, including Davis-Bacon wage rates and American Iron and Steel provisions. The contractor must obtain a performance bond covering 100% of the contract amount and a 50% payment bond, and must have an active Unique Entity Identifier (UEI) from SAM.gov. There is no Disadvantaged Business Enterprise (DBE) requirement for this project. The bid must include detailed information about crew and equipment costs, project timeline, and the contractor's approach to project management, including waste disposal, damage prevention, resident notification, traffic control, and compliance with local working hour restrictions.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

20200109 1 413-04-01

CITY OF MANITOU SPRINGS

Request for Bids

Midland Avenue and Arizona Road Sanitary Sewer and Water

Main Replacement

RFB NUMBER: 2024-015

Bid Submittal Deadline – 10/25/24, 2:00 PM City Contacts Andrew Morren, City Engineer, amorren@manitouspringsco.gov Alicia Stoke, Senior Administrative Assistant, astoke@manitouspringsco.gov

The City of Manitou Springs is accepting bids for replacement of the water mains and sanitary sewer mains on Midland Ave (west of Unita Rd). See attached plans and specifications.

• Publication Date: 9/24/24.

• Pre-bid meeting to be held on 10/4/24, 1:00 PM at the Public Works Facility, 101 Banks Place, Manitou Springs 80829.

• Deadline to present questions is 10/11/24, 2:00 PM o Questions are to be addressed to the identified City Contacts and will only be accepted via e- mail.

• Final Addendum posted on 10/18/24

• Bid shall be submitted to the City Contacts via e-mail to the identified City Contacts no later than the Submittal Deadline 10/25/24, 2:00 PM o There will not be a public bid opening.

• Notice of Award will be 10/29/24.

• The Selected Contractor will be required to obtain a performance bond to cover 100% of the project contract amount and 50% payment bond.

• Contractor must have an active UEI number from SAM.gov site.

• This project is subject to Davis-Bacon Wages, and American Iron and Steel requirements.

• There is no DBE requirement on this project The bid shall have an Anticipated Scope of Services that includes the following:

1. The Contractor will provide project costs for crews and equipment, anticipated mobilization time, and anticipated project completion time.

2. The Contractor is responsible to provide all materials and equipment necessary for fabrication, construction, and/or installation of this project.

3. All waste shall be disposed of by the Contractor.

4. The Contractor is responsible for damages, inside or outside the project area.

mailto:astoke@manitouspringsco.gov mailto:amorren@manitouspringsco.gov

20200109 2 413-04-01

5. The Contractor is responsible for their own confined space, roadway, and trenching safety procedures.

6. No work shall be done between the hours of 5:30 p.m. and 7:00 a.m., not at any time on Saturday, Sunday, or holidays except with the written permission of the city or in cast of an emergency.

7. The Contractor is responsible for providing written notices to all residents within project limits, a minimum of two weeks prior to construction.

8. If the project requires street closure – partial or otherwise, the Contractor shall provide all necessary traffic control. All traffic control personnel must at a minimum carry a current CDOT Flagger Certification. A Traffic Control Plan must be submitted to and approved by City staff at the pre-construction meeting. The pre-construction meeting is to be scheduled at time of accepting the contract.

9. Below is the Anticipated General Scope of Services for this project:

GENERAL SCOPE OF SERVICES

1. Midland Ave

a. Water – Abandon the existing 2” and 6” water mains and follow project special provisions for abandonment. See Bid Schedule for size and lineal feet of new service lines. Includes connecting all existing services to the new main, and replacing the services from the main to the curb stop.

b. Sanitary Sewer – Abandon the existing sanitary sewer main and follow project special provisions for abandonment. See Bid Schedule for size and lineal feet of new service lines. Includes connecting all existing services to the new main, and replacing the services from the main to the back of curb.

2. Arizona Rd

a. Water – Abandon the existing 2” water mains and follow project special provisions for abandonment. See Bid Schedule for size and lineal feet of new service lines. Includes connecting all existing services to the new main, and replacing the services from the main to the curb stop.

b. Sanitary Sewer – Abandon the existing sanitary sewer main and follow project special provisions for abandonment. See Bid Schedule for size and lineal feet of new service lines. Includes connecting all existing services to the new main, and replacing the services from the main to the back of curb.

3. Bypass Pumping or Acceptable Alternative– During the construction of the proposed sanitary sewer main, provide bypass pumping of the existing system per the construction phasing plan or acceptable alternative.

4. Disruption of services – Continuous water and sanitary sewer service shall be provided throughout the duration of the project, with the exception of during the period of time to connect the existing services to the new main.

20200109 3 413-04-01

INSTRUCTIONS TO BIDDERS

1. A "Bid" is a responsive, conforming, unconditional, complete, legible, and properly executed offer by a Bidder to provide the work specified in the Request for Bids for the compensation specified.

2. Bids shall be clearly marked with the project name, contact person, mailing address, and telephone number of the Bidder.

3. It shall be the responsibility of the Bidder to ensure that the Bid is in proper form and in the City's possession by or before the time and date designated in the Request for Bids. Bids will not be accepted after the designated time and date.

4. If a mistake is made or discovered during or after the Bid review, the City reserves the right to determine which party made the mistake and whether the mistake is material and, after these determinations, the City, in its sole reasonable discretion, shall decide whether to accept or reject the Bid. No advantage shall be taken by any party of manifest clerical errors or omissions in any Bid, and the contract and attached documents (the “Contract Documents”). Bidders shall notify the City immediately of any errors or omissions that are encountered.

5. 5. Any interlineation, alteration, or erasure shall be initialed by the Bidder. On the Bid, the price of each item shall be stated in numerals and words; in case of conflict, the words shall control. In the case of conflict between the indicated sum of any addition of figures and the correct sum, the correct sum shall control

6. The City shall not reimburse any Bidder for any cost incurred in preparing a Bid or attending equipment demonstrations, inspections, pre-bid conferences, or interviews.

7. Any amplification, clarification, explanation, interpretation, or correction of a Bid shall be made only by written addendum, and a copy of the addendum shall be mailed or delivered to each person receiving a Request for Bids. The City is not responsible for any amplification, clarification, explanation, or interpretation or correction of a Bid not contained in written addenda.

8. Bids by corporations shall be executed in the corporate name by the president or a vice-president (or a corporate officer accompanied by evidence of authority to sign), and the corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown. Bids submitted by partnerships shall be executed in the partnership name and signed by a partner, and the legal address of the partnership shall be shown. Bids submitted by limited liability companies shall be executed in the company's name and signed by a member, and the legal address of the company shall be shown. Names and titles shall be typed or printed below each signature.

20200109 4 413-04-01

9. The following information shall be submitted with the Bid, in the form of a cover letter:

a. The names and resumes of staff personnel who will be assigned to the work.

b. A complete proposed scope of work and schedule, including any alternatives that can be identified. The Bidder is expected to review the work site prior to submittal of the Bid.

c. The names and addresses of any subcontractors who will be retained for the work

d. A list of the Bidder's previous experience on similar projects.

10. The submission of a Bid shall be conclusive evidence and a legal admission that the Bidder: (1) has no questions, complaints, or objections in connection with the Contract Documents, subject to any requests made by the Bidder for amplification, clarification, explanation, interpretation, or correction; (2) has no questions, complaints, or objections as to the completeness, sufficiency, scope, or detail of the Bid; and (3) has full knowledge of the scope, nature, quality, and quantity of the equipment to be provided, the performance criteria, the requirements of the contract, the site and conditions of delivery, the Superior Municipal Code, and other applicable law.

11. The contract will be awarded to the lowest responsible and responsive Bidder complying with the terms and conditions, guidelines, and specifications presented in the Bid Request and these Instructions to Bidders. The City reserves the right to determine, in its sole reasonable discretion, whether any Bid meets the needs or purposes intended and is within the approved budget. The City does not base its award on prices alone. Also to be considered are: quality of product; past experience with the Bidder or any subcontractors, consultants, products or suppliers;

qualifications of the Bidder and/or subcontractors or suppliers; services offered;

warranties; maintenance considerations; long-range costs; delivery; and similar conditions.

12. The City reserves the right to conduct such investigations as it deems necessary to assist in the evaluation of any Bid to establish the experience, responsibility, reliability, references, reputation, qualifications, or financial ability of any Bidder, manufacturer or supplier. The purpose of such investigation is to satisfy the City that the Bidder has the experience, resources, and commercial reputation necessary to supply the specified equipment and to perform the necessary warranty and product support in accordance with the Contract Documents in the prescribed manner and time.

13. The City reserves the right, if it deems such action to be in its best interests, to reject any and all Bids or to waive any irregularities or informalities therein. Any incomplete, false, or misleading information provided by any Bidder shall be grounds for rejection of the Bid. If Bids are rejected, the City further reserves the right to investigate and accept the next best Bid in order of ranking, or to reject all Bids and re-solicit for additional Bids.

14. No Bid shall include federal excise taxes or state or local sales or use taxes.

20200109 5 413-04-01

15. In the event of any claim, suit, or demand which may result from any Bid, or the award of any contract as a result of submission of a Bid, Colorado law shall govern any such claim, suit, or demand and the rights and duties of the parties.

16. All parts not specifically mentioned which are necessary in order to provide a complete unit, shall be included in the Bid. Any item listed as "Standard" in the manufacturer's published specification, furnished by the Bidder, is assumed to be included in the Bid. Any variations shall be outlined in writing, noting cost factors where applicable

17. Bids shall be in accordance with the specifications contained in the Contract Documents. Should any requirement in the specifications not be included in manufacturer's specification sheets, the Bidder shall include with its Bid a statement of compliance. Failure to do so shall be grounds for disqualification of the Bid.

18. Each Bid shall include a statement of standard warranty of the manufacturer.

19. 19. Any Bid received as a result of this request is prepared at the Bidder’s expense and becomes City property and is therefore a public record upon opening by the City.

No Bid may be withdrawn for a period of sixty (60) days after the deadline for Bids.

The City of Manitou Springs is an Equal Opportunity Employer and no otherwise qualified individual shall be subject to discrimination on the basis of race, color, religion or religious affiliation, sex, familial status, age, genetics, disability, or national origin in any phase of employment for this position.

Midland Avenue Water and Sanitary Replacement Project No. 2024-015

BID SCHEDULE

09/24/2024

1 201-00000 Clearing and Grubbing LS 0.5 2 202-00000-SPC Flow Fill and Abandon Pipe [Sanitary] LF 15 3 202-00001-SPC1 Removal of Structure [Sanitary Cleanout] EA 1 4 202-00001-SPC2 Removal of Structure [Manhole] EA 1 5 202-00220 Removal of Asphalt Mat SY 25 6 202-00035-SPC1 Removal of Pipe [Sanitary] LF 377 7 203-00400 Rock Excavation CY 25 8 208-00000-SPC Erosion Control LS 0.5 9 403-33721-SPC Hot Mix Asphalt (Grading S) (75) (PG 64-22) TON 8

10 304-06007 Aggregate base course (Class 6) TON 12 11 603-50008-SPC1 8 Inch PVC (SDR26) (0' - 12' Depth) LF 521 12 604-39000-SPC1 Manhole Sanitary 4' Diameter (0'-12' Depth) EACH 3 13 604-39000-SPC2 Manhole Sanitary 4' Diameter (0'-12' Depth)(Drop) EACH 5 14 603-50008-SPC2 Connect to Existing Sanitary Sewer Service EACH 6 15 603-50008-SPC3 Connect to Existing Sanitary Sewer Main EACH 2 16 625-00000 Construction Surveying LS 0.5 17 626-00000 Mobilization LS 0.5 18 630-10005 Traffic Control LS 0.5

SANITARY SEWER TOTAL

19 201-00000 Clearing and Grubbing LS 0.5 20 202-00035-SPC2 Removal of Pipe [Water] LF 525 21 202-00220 Removal of Asphalt Mat SY 14 22 202-00032-SPC Removal of Valve [Water] EA 3 23 203-00400 Rock Excavation CY 25 24 203-01597 Potholing HR 16 25 208-00000-SPC Erosion Control LS 0.5 26 403-33721-SPC Hot Mix Asphalt (Grading S) (75) (PG 64-22) TON 5 27 304-06007 Aggregate base course (Class 6) TON 7 28 619-88886-SPC1 6 Inch Bend - 11.25 Degree [Vertical & Horizontal] EACH 7 29 619-88886-SPC2 6" x 6" Tee EACH 4 30 619-00002-SPC Connect Existing Water Service EACH 4 30 619-50480-SPC1 6 Inch PVC (C900)(DR14) LF 390 31 619-50480-SPC2 6 Inch PVC (C900)(DR14)(Insulated) LF 95 32 619-75048 6 Inch Gate Valve EACH 9 33 619-88886-SPC3 6 Inch Plug EACH 1 34 619-78048-SPC 6 Inch Fire Hydrant Assembly w/ 6" Gate Valve and PVC Lateral EACH 2 35 625-00000 Construction Surveying LS 0.5 36 626-00000 Mobilization LS 0.5 37 630-10005 Traffic Control LS 0.5

POTABLE WATER LINE TOTAL

PROJECT TOTAL

Total Bid in Numbers:

Total Bid in Words:

_________________________Dollars and _________________________ Cents.

Prepared By:

Company:

Address:

Phone:

Signed: ____________________________ Date:_______________________

Printed Name and Title

I acknowledge that this bid includes Addendum #____, #____, #____, and #____. (If none, so state.)

I hereby certify that I am authorized to submit this bid.

POTABLE WATER LINE

SANITARY SEWER

CITY ITEM

NO. CDOT ITEM NO. CONTRACT ITEM UNIT QUANTITY UNIT PRICE TOTAL COST

CITY

ITEM NO.

CDOT

ITEM NO. CONTRACT ITEM UNIT QUANTITY UNIT PRICE TOTAL COST

Midland Avenue Sanitary Sewer and Water Main Replacement Project Special Provisions Project No. 2024-015 09/24/2024

PSP-1

The 2023 CDOT Standard Specifications for Road and Bridge Construction controls construction of this project, unless otherwise noted. The following special provisions supplement or modify the Standard Specifications and take precedence over the Standard Specifications and plans. If City of Manitou Springs, City of Colorado Springs, or Colorado Springs Utilities’ specifications or standards are to be used for an aspect of work, it will be noted in these project special provisions.

PROJECT SPECIAL PROVISIONS

Page

Index Pages.........................................................................................................................................................PSP-1

Disadvantaged Business Enterprise (DBE) Contract Goal.................................................................................PSP-3

Commencement and Completion of Work.........................................................................................................PSP-4

Revision of Section 107 – Legal Relations and Responsibility to Public ..........................................................PSP-5

Revision of Section 201 – Clearing and Grubbing.............................................................................................PSP-6

Revision of Section 202 – Removal of Structures and Obstructions..................................................................PSP-7

Revision of Section 203 – Excavation and Embankment...................................................................................PSP-8

Revision of Section 208 – Erosion Control ........................................................................................................PSP-9

Revision of Section 304 – Aggregate Base Course..........................................................................................PSP-10

Revision of Section 403 – Hot Mix Asphalt............................................................................................... PSP-11-13

Revision of Section 603 – Culverts and Sewers...............................................................................................PSP-14

Revision of Section 604 – Manholes, Inlets, and Water Vaults .......................................................................PSP-15

Revision of Section 619 – Water Lines ............................................................................................................PSP-16

Revision of Section 625 – Construction Surveying..........................................................................................PSP-17

Revision of Section 626 – Mobilization ..........................................................................................................PSP-18

Revision of Section 630 – Construction Zone Traffic Control.........................................................................PSP-19

Traffic Control Plan – General .........................................................................................................................PSP-20

Utilities ....................................................................................................................................................... PSP-21-24

COLORADO STATE REVOLVING FUND REQUIRED SPECIFICATIONS

(SRF Non-Equivalency, BIL Funding)

Section 1 – Davis Bacon Prevailing Wage Requirements.......................................................................... PSP-25-33

Exhibit 1 - Minimum Wages, Colorado, U.S. Department of Labor............................................. PSP-50-56 General Decision Number CO20240002, Heavy Construction for Adams, Arapahoe, Boulder, Broomfield, Denver, Douglas, El Paso, Jefferson, Larimer, Mesa, Pueblo, and Weld Counties

Section 2 – American Iron and Steel .......................................................................................................... PSP-34-35

Section 3 – National Term on Suspension and Debarment ..............................................................................PSP-36

Section 4 – Equal Employment Opportunity.............................................................................................. PSP-37-42

PSP-2

Section 5 – Williams-Steiger Occupational Safety and Health Act of 1970 ....................................................PSP-43

Section 6 – Discovery of Archaeological and Other Historical Items..............................................................PSP-44

Section 7 – Not Applicable...............................................................................................................................PSP-45

Section 8 – Not Applicable...............................................................................................................................PSP-46

Section 9 – Signage Requirements ...................................................................................................................PSP-47

Section 10 – Not Applicable.............................................................................................................................PSP-48

Section 11 – SRF Required Forms by Section .................................................................................................PSP-49

PSP-3

Project No. 2024-015 09/24/2024

DISADVANTAGED BUSINESS ENTERPRISE (DBE) CONTRACT GOAL

This is a federally-assisted construction project. As described in the Colorado State Revolving Fund Required Specifications, the Bidder shall make good faith efforts to meet the following contract goal:

0.0 Percent DBE participation

PSP-4

Project No. 2024-015 09/24/2024

COMMENCEMENT AND COMPLETION OF WORK

(WORKING DAY)

The Contractor shall commence work under the Contract per the “Notice to Proceed” from the City of Manitou Springs. The Contractor shall complete all work within 40 working days in accordance with the "Notice to Proceed."

PSP-5

Project No. 2024-015 09/24/2024

REVISION OF SECTION 107

LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC

Section 107 of the Standard Specifications is hereby revised for this project as follows:

Subsection 107.01 shall include the following:

The Contractor shall construct the project during normal working hours, 8:00 am to 5:00 pm, Mondays through Fridays, exclusive of Holidays. Work outside of normal working hours requires the Engineer’s approval.

Subsection 107.07 shall include the following:

The Contractor shall provide written notification to all residents within the project limits a minimum of two weeks prior to start of construction. This initial notification shall include the following information:

1. Project scope and schedule

2. Anticipated impacts (general) to residents

3. Contractor and City contact information

Additionally, the Contractor shall seek out residents with special needs to take into consideration during construction.

PSP-6

Project No. 2024-015 09/24/2024

REVISION OF SECTION 201

CLEARING AND GRUBBING

Section 201 of the Standard Specifications is hereby revised for this project as follows:

Subsection 201.01 shall include the following:

This work consists of removal and disposal of trash and debris within the limits of the right-of-way, and other areas shown in the contract or required by the work. These items shall be removed and disposed of offsite by the Contractor during construction and prior to final acceptance of the project.

Subsection 201.02 shall include the following:

The Contractor shall remove and dispose of all visibly abandoned utility appurtenances that are located within the work area or right-of-way, and abandoned as a result of this project. These items shall not be disposed of within the project limits.

The Contractor shall not remove any shrubs or trees within the project limits without prior written approval from the Engineer. All trees and shrubs within or adjacent to the Project limits, unless otherwise noted, shall be protected.

Contractor shall mark all trees and shrubs that are required to be removed and shall obtain written approval from the Engineer prior to beginning the work.

Existing trees, shrubs, bushes, or grass, outside the designated work areas but inside the project limits that are damaged due to the Contractor’s operations shall be replaced in kind at the Contractor’s expense.

Section 201.04 shall be revised to include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 201-00000 Clearing and Grubbing LS

Although clearing and grubbing cannot be designated as being associated with the water or sanitary sewer installation individually, due to funding sources, the Clearing and Grubbing item shall be paid under the Water System and Sanitary Sewer System bid items, and shown in the bid schedules as 0.5 LS.

PSP-7

Project No. 2024-015 09/24/2024

REVISION OF SECTION 202

REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Section 202 of the Standard Specifications is hereby revised for this project as follows:

Subsection 202.01 shall include the following:

This work shall include the removal of existing fire hydrants, water main pipe, sanitary sewer pipe, sanitary sewer manholes, water main valves and fittings, sanitary sewer manholes, water and sanitary sewer services and appurtenances, pavement, the abandonment of existing pipes, and other material required to be removed.

Subsection 202.02 shall include the following:

The Contractor shall remove all existing water mains and sanitary sewer mains identified within the plans. All fire hydrants removed from the project will be replaced with new fire hydrants. All removed hydrants shall be salvaged, and shall be turned over to the City.

The Contractor shall abandon all existing sanitary sewer pipes as identified within the plans by draining the pipes, filling the pipes with suitable flow-fill material, and plugging of the ends in accordance with the Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 2.5.D.6).

The Contractor shall remove all water and sanitary sewer services from either 5’ behind the edge of roadway or at the property line (sanitary sewer) or the curb stop (water) to the new main.

The Contractor shall not remove any private property improvements (i.e. fence, mailboxes, etc.) without notification and approval from the Engineer.

Subsection 202.11 shall include the following:

Removal of pipe (water and sanitary sewer) shall include all pipe sizes and material encountered.

Subsection 202.12 shall include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 202-00000-SPC Flow Fill and Abandon Pipe [Sanitary] LF 202-00001-SPC1 Removal of Structure [Sanitary Cleanout] EA 202-00001-SPC2 Removal of Structure [Manhole] EA 202-00032-SPC Removal of Valve [Water] EA 202-00035-SPC1 Removal of Pipe [Sanitary] LF 202-00035-SPC2 Removal of Pipe [Water] LF 202-00220 Removal of Asphalt Mat SY

Removal of other material, including fittings, required to accomplish the work, shall not be paid for separately, but shall be included in in the work.

Sawcutting of asphalt or concrete shall not be measured and paid for separately, but shall be incidental to the project.

Removal of the existing water and sanitary sewer services shall not be measured and paid for separately, but shall be incidental to the cost of the project.

Separate payment for differing pipe sizes and materials will not be made.

PSP-8

Project No. 2024-015 09/24/2024

REVISION OF SECTION 203

EXCAVATION AND EMBANKMENT

Section 203 of the Standard Specifications is hereby revised for this project as follows:

Subsection 203.01 shall include the following:

Excavation and embankment shall follow the City of Colorado Springs Specifications – Section 200.

Subsection 203.05.(a) shall include the following:

Upon encountering rock, the Contractor shall immediately stop work, and notify the Engineer. Prior to commencing work, the Contractor and Engineer shall confirm and document the location and extents of rock.

Subsection 203.07 shall include the following:

Compaction shall follow the City of Colorado Springs Specifications – Section 206. For trenches greater than eight

(8) feet in depth, density tests shall be as follows: 1) 12 inches above the pipe, 2) one-third of the trench depth, 3) two-thirds of the trench depth, and 4) at the surface.

Subsection 203.11 shall include the following:

All rock excavation shall be measured by the volume encountered and removed, and confirmed with the Engineer.

Subsection 203.11.(e) shall be deleted, and replaced with the following:

Potholing will be measured by the total number of hours that excavation and backfilling equipment is actually used as directed. All other related work, including shoring, labor, and other equipment will not be measured and paid for separately, but shall be included in the work. Asphalt removal shall be paid for under the Removal of Asphalt Mat pay item.

Subsection 203.12 shall be deleted, and replaced with the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 203-00400 Rock Excavation CY 203-01597 Potholing HR

Payment for replacement of excavated rock material shall be included in the cost of Rock Excavation.

All other excavation and embankment required for the project shall not be measured and paid for separately, but shall be included in the work.

PSP-9

Project No. 2024-015 09/24/2024

REVISION OF SECTION 208

EROSION CONTROL

Section 208 of the Standard Specifications is hereby revised for this project as follows:

Entire Section 208 shall be deleted and revised to include the following:

Erosion control shall be in accordance with the City of Colorado Springs Drainage Criteria Manual, Volume II.

Installation of erosion control features, maintenance thereof, and their removal shall be paid for as lump sum as follows:

1. 50% - Upon installation of the erosion control features, and

2. 100% - Upon completion of the project.

Although erosion control cannot be designated as being associated with the water or sanitary sewer installation individually, due to funding sources, the Erosion Control item shall be paid under the Water System and Sanitary Sewer System bid items, and shown in the bid schedules as 0.5 LS.

PSP-10

Project No. 2024-015 09/24/2024

REVISION OF SECTION 304

AGGREGATE BASE COURSE

Section 304 of the Standard Specifications is hereby revised for this project as follows:

Entire Section 304 shall be deleted and revised to include the following:

All aggregate base course shall comply with City of Colorado Springs Specifications – Section 300.

Subsection 304.08 shall be deleted, and replaced with the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 304-06007 Aggregate Base Course (Class 6) TON

PSP-11

Project No. 2024-015 09/24/2024

REVISION OF SECTION 403

HOT MIX ASPHALT

Section 403 of the Standard Specifications is hereby revised for this project as follows:

Subsection 403.02 shall include the following:

The design mix for hot mix asphalt shall conform to the following:

Table 403-1

Property Test Method

Value For Grading

S (75)

Air Voids, percent at:

N (design) CPL 5115 3.5 – 4.5

Lab Compaction (Revolutions):

N (design) CPL 5115 100

Stability, minimum CPL 5106 30 Aggregate Retained on the 4.75 mm (No. 4) Sieve for S, SX and SG, and on the 2.36mm (No. 8) Sieve for ST and SF with at least 2 Mechanically Induced fractured faces, % minimum*

CP 45 60

Accelerated Moisture Susceptibility Tensile Strength Ratio (Lottman), minimum

CPL 5109

Method B 80

Minimum Dry Split Tensile Strength, kPa (psi)

CPL 5109

Method B 205 (30)

Grade of Asphalt Cement, Top Layer PG58-28

Grade of Asphalt Cement, Layers below Top PG58-28

Voids in the Mineral Aggregate (VMA) % minimum CP 48

See Table 403-2

Voids Filled with Asphalt (VFA), % AI MS-2 65-75 Dust to Asphalt Ratio

Fine Gradation Coarse Gradation

CP 50 0.6 – 1.2

0.8 – 1.6

Note: AI MS-2 = Asphalt Institute Manual Series 2 Note: Mixes with gradations having less than 40% passing the 4.75 mm (No. 4) sieve shall be approached with caution because of constructability problems.

Note: Gradations for mixes with a nominal maximum aggregate size of one-inch or larger are considered a coarse gradation if they pass below the maximum density line at the #4 screen.

Gradations for mixes with a nominal maximum aggregate size of 3/4” to 3/8” are considered a coarse gradation if they pass below the maximum density line at the #8 screen.

Gradations for mixes with a nominal maximum aggregate size of #4 or smaller are considered a coarse gradation if they pass below the maximum density line at the #16 screen.

*Fractured face requirements for SF may be waived by RME depending on project conditions.

PSP-12

Project No. 2024-015 09/24/2024

REVISION OF SECTION 403

HOT MIX ASPHALT

All mix designs shall be run with a gyratory compaction angle of 1.25 degrees and properties must satisfy Table 403-1. Form 43 will establish construction targets for Asphalt Cement and all mix properties at Air Voids up to 1.0 percent below the mix design optimum. CDOT will establish the production asphalt cement and volumetric targets based on the Contractor’s mix design and the relationships shown between the hot mix asphalt mixture volumetric properties and asphalt cement contents on the Form 429. CDOT may select a different AC content other than the one shown at optimum on the Contractor’s mix design in order to establish the production targets as contained on the Form 43. Historically, Air Voids adjustments typically result in asphalt cement increases from 0.1 to 0.5 percent.

Contractors bidding the project should anticipate this change and factor it into their unit price bid.

Table 403-2 Minimum Voids in the Mineral Aggregate (VMA)

Nominal Maximum Size*, mm (inches)

***Design Air Voids **

3.5% 4.0% 4.5% 5.0%

37.5 (1½) 11.6 11.7 11.8

N/A

25.0 (1) 12.6 12.7 12.8

19.0 (¾) 13.6 13.7 13.8

12.5 (½) 14.6 14.7 14.8

9.5 (⅜) 15.6 15.7 15.8

4.75 (No. 4) 16.6 16.7 16.8 16.9

* The Nominal Maximum Size is defined as one sieve larger than the first sieve to retain more than 10%.

** Interpolate specified VMA values for design air voids between those listed.

*** Extrapolate specified VMA values for production air voids beyond those listed.

The Contractor shall prepare a quality control plan outlining the steps taken to minimize segregation of HMA. This plan shall be submitted to the Engineer and approved prior to beginning the paving operations. When the Engineer determines that segregation is unacceptable, the paving shall stop and the cause of segregation shall be corrected before paving operations will be allowed to resume.

The hot mix asphalt shall not contain any reclaimed asphalt pavement.

Subsection 403.03 shall include the following:

Asphalt shall be placed with self-propelled, activated screed assembly pavers. The pavers shall have sufficient power to propel themselves and the hauling equipment without adversely affecting the finished pavement surface.

The paver hopper shall be equipped with a distribution system to place the mixture uniformly in front of the screed without segregation. The screed shall effectively produce a finished surface of the required thickness and texture without tearing, shoving, or gouging the mixture.

PSP-13

Project No. 2024-015 09/24/2024

REVISION OF SECTION 403

HOT MIX ASPHALT

Surface smoothness of the final surface is subject to testing by the 10-foot straightedge method. The Contractor shall furnish an approved 10-foot straightedge and depth gauge and provide an operator to aid the Engineer in testing the finished pavement surface. Areas to be tested shall be determined by the Engineer. The variation between any two contacts with the surface shall not exceed 3/16-inch in 10 feet. Areas showing deviation of more than 3/16-inch shall be marked and corrected at the Contractor’s expense.

Subsection 403.04 shall be deleted, and replaced with the following:

Placement of asphalt shall be measured by area installed at the surface. Areas with exclusive water or sanitary sewer installations shall be measured and paid for under the bid schedule of the water or sanitary sewer. Areas with both water and sanitary sewer installation shall have the area divided by two (2), and the respective amounts paid under each bid schedule.

Subsection 403.05 shall be deleted, and replaced with the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 403-33721-SPC Hot Mix Asphalt (Grading S) (75) (PG 58-28) TON

Aggregate, asphalt cement, asphalt recycling agent, additives, hydrated lime, and all other work necessary to complete the hot mix asphalt item will not be paid for separately, but shall be included in the unit price.

Excavation, preparation, and tack coat of areas to be paved will not be measured and paid for separately, but shall be included in the work.

PSP-14

Project No. 2024-015 09/24/2024

REVISION OF SECTION 603

CULVERTS AND SEWERS

Section 603 of the Standard Specifications is hereby revised for this project as follows:

Subsection 603.01 shall include the following:

This work shall include the construction of sanitary sewer systems in accordance with the Colorado Springs Utilities Waste Water Line Extension and Service Standards.

Subsection 603.02 shall include the following:

All waste water materials shall meet the requirements shown in the Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 4).

Subsection 603.03 shall include the following:

Construction of sanitary sewer mains, manholes, and service connections shall be constructed in accordance with Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 5).

Tracer wire shall be installed along all new sanitary sewer mains, sanitary sewer services, and at manholes in accordance with Colorado Springs Utilities Waste Water Line Extension and Service Standards, Sections 5.15 and 5.22.D.1.a.

Subsection 603.06 shall include the following:

Bypass pumping of the existing sanitary sewer system may be required, and shall follow the Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 5.7). The Contractor shall submit a Bypass System Plan to the City of Manitou Springs and the Engineer for review and approval a minimum of 2 weeks prior to construction.

Subsection 603.13 shall include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 603-50008-SPC1 8 Inch PVC (SDR26) (0’ - 12’ Depth) LF 603-50008-SPC2 Connect to Existing Sanitary Sewer Service EA 603-50008-SPC3 Connect to Existing Sanitary Sewer Main EA

Payment for Connecting to Existing Sanitary Sewer Service shall include connection to the new main, and installing a new service from the main to the property line or 5’ behind the edge of roadway, including tracer wire. Installation shall also include the installation of a clean out at the connection point.

The placement and testing of tracer wire shall not be measured and paid for separately, but shall be included in the cost of the project.

Payment for Connect to Existing Sanitary Sewer Main shall include the appropriate sized coupling, or connection into an existing manhole.

Bypass pumping will not be measured and paid for separately, but shall be included in the cost of the project.

Placement of flow fill between sanitary sewer main and other utilities shall not be paid for separately, but shall be included in the cost of the project.

PSP-15

Project No. 2024-015 09/24/2024

REVISION OF SECTION 604

MANHOLES, INLETS, AND WATER VAULTS

Section 604 of the Standard Specifications is hereby revised for this project as follows:

Subsection 604.01 shall include the following:

This work shall include the construction of sanitary sewer manholes in accordance with the Colorado Springs Utilities Waste Water Line Extension and Service Standards.

Subsection 604.02 shall include the following:

All sanitary sewer manhole materials shall meet the requirements shown in the Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 4).

Subsection 604.04(b) shall include the following:

Construction of sanitary sewer manholes shall comply with the Colorado Springs Utilities Waste Water Line Extension and Service Standards (Section 5.)

Subsection 604.07 shall include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 604-39000-SPC1 Manhole (Sanitary)(4’ Diameter)(0’ - 12’ Depth) EA 604-39000-SPC2 Manhole (Sanitary)(4’ Diameter)(0’ - 12’ Depth)(Drop) EA

PSP-16

Project No. 2024-015 09/24/2024

REVISION OF SECTION 619

WATER LINES

Section 619 of the Standard Specifications is hereby revised for this project as follows:

Subsection 619.01 shall include the following:

This work shall include the construction of water systems in accordance with the Colorado Springs Utilities Water Line Extension and Service Standards.

Subsection 619.02 shall include the following:

All water system materials shall meet the requirements shown in the Colorado Springs Utilities Water Line Extension and Service Standards (Section 4).

Subsection 619.03 shall include the following:

Construction of water mains, fittings, fire hydrants, service taps, and services shall be constructed in accordance with Colorado Springs Utilities Water Line Extension and Service Standards (Section 5).

Tracer wire shall be installed along all new water mains, water services, and fire hydrants in accordance with Colorado Springs Utilities Water Line Extension and Service Standards, Sections 5.16 and 5.21.M.

Subsection 619.05 shall include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 619-00002-SPC Connect Existing Water Service EA 619-50480-SPC1 6 Inch PVC (C900)(DR14) LF 619-50480-SPC2 6 Inch PVC (C900)(DR14)(Insulated) LF 619-75048 6 Inch Gate Valve EA 619-78048-SPC 6 Inch Fire Hydrant Assembly w/ 6” Gate Valve and PVC Lateral EA 619-88886-SPC1 6 Inch Bend – 11.25 Degree [Vertical & Horizontal] EA 619-88886-SPC2 6” x 6” Tee EA 619-88886-SPC3 6 Inch Plug EA

Payment for Connect Existing Water Service shall include tapping into the new main, installing continuous pipe from the corp stop to the curb stop, including tracer wire, of each resident.

Construction of all concrete thrust blocks shall not be measured separately, but shall be included in the cost of the fitting.

Installation of all anodes shall not be measured separately, but shall be included in the cost of the fitting.

The placement and testing of tracer wire shall not be measured and paid for separately, but shall be included in the cost of the project.

Placement of flow fill between water main and other utilities shall not be paid for separately, but shall be included in the cost of the project.

PSP-17

Project No. 2024-015 09/24/2024

REVISION OF SECTION 625

CONSTRUCTION SURVEYING

Section 625 of the Standard Specifications is hereby revised for this project as follows:

Section 625.13 shall be revised to include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 625-00000 Construction Surveying LS

Although construction surveying can be designated as being associated with the water or sanitary sewer installation individually, due to funding sources, the Construction Surveying item shall be paid under the Water System and Sanitary Sewer System bid items, and shown in the bid schedules as 0.5 LS.

PSP-18

Project No. 2024-015 09/24/2024

REVISION OF SECTION 626

MOBILIZATION

Section 626 of the Standard Specifications is hereby revised for this project as follows:

Section 626.02 shall be revised to include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 626-00000 Mobilization LS

Although mobilization cannot be designated as being associated with the water or sanitary sewer installation individually, due to funding sources, the Mobilization item shall be paid under the Water System and Sanitary

PSP-19

Project No. 2024-015 09/24/2024

REVISION OF SECTION 630

CONSTRUCTION ZONE TRAFFIC CONTROL

Section 630 of the Standard Specifications is hereby revised for this project as follows:

Section 630.18 shall be revised to include the following:

Payment will be made under the following item(s):

Item No. Pay Item Pay Unit 630-10005 Traffic Control LS

Although traffic control cannot be designated as being associated with the water or sanitary sewer installation individually, due to funding sources, the Traffic Control item shall be paid under the Water System and Sanitary

PSP-20

Project No. 2024-015 09/24/2024

TRAFFIC CONTROL PLAN - GENERAL

The key elements of the Contractor’s method of handling traffic (MHT) are outlined in Subsection 630.10(a).

The components of the TCP for this project are included in the following:

(1) Section 104.04 and Section 630 of the specifications

(2) CDOT Standard Plans

(3) Schedule of Construction Traffic Control Signs

(4) Construction Phasing Plans

(5) City of Colorado Springs Manual on Uniform Traffic Control Devices – Supplement for the City of

Colorado Springs.

Unless otherwise approved by the Engineer, the Contractor’s equipment shall follow normal and legal traffic movements. The Contractor’s ingress and egress of the work area shall be accomplished with as little disruption to interstate highway, state highway, and local road traffic as possible.

Traffic control devices shall be removed by picking up the devices in a reverse sequence to that used for installation.

This may require moving backwards through the work zone. When located behind barrier or at other locations shown on approved traffic control plans, equipment may operate in a direction opposite to adjacent traffic.

The City may have entered into operating agreements with one or more law enforcement organizations for cooperative activities. Under such agreements, at the sole discretion of the City, law enforcement personnel may enter the work zone for enforcement purposes and may participate in the Contractor’s traffic control activities. The responsibility under the Contract for all traffic control resides with the Contractor and any such participation by law enforcement personnel in Contractor traffic control activities will be referenced in either the Special Provisions or General Notes of the plans depending on whether the Contractor is to hire local law enforcement or if the City is contracting with Colorado State Patrol for uniformed traffic control. Nothing in this Contract is intended to create an entitlement, on the part of the Contractor, to the services or participation of the law enforcement organization.

Special Traffic Control plan requirements for this project are as follows:

During the construction of this project, traffic shall use the present traveled roadway unless identified on the plans or approved by the Engineer.

The Contractor shall not have construction equipment or materials in the lanes open to traffic at any time, unless approved by the Engineer.

Throughout the duration of the project, reasonable access shall be provided to residents within the work zone. Prior to the pre-construction meeting, the Contractor shall provide a written accessibility plan for each Phase to the City, outlining the Contractor’s plan to provide access to residents throughout the duration of the project. Due to limited parking accommodations within the existing right-of-way, the Contractor shall provide a safe pedestrian accessible route to residents within the work zone in such a manner that residents shall not be required to walk more than 100’ from their residence to the beginning of the work zone. At the end of each work day, the Contractor shall place steel plates, and provide other forms of protection within the construction area to allow safe passage of vehicles for residents.

The Contractor shall assist residents to ensure that trash pickup and mail collection is not interrupted.

At least one week prior to starting construction, the Contractor shall notify the City of Manitou Springs’ City Engineer of the date the Contractor intends to start construction.

All costs incidental to the foregoing requirements shall be included in the original contract prices for the project.

PSP-21

Project No. 2024-015 09/24/2024

UTILITIES

Known utilities within the limits of this project are:

UTILITY COMPANY CONTACT

EMAIL

TELEPHONE

Lumen/CenturyLink Ken Davis ken.davis2@lumen.com

719-636-4006

Colorado Springs Utilities (Elecric) Kyle Leibhart kleibhart@csu.org

719-668-7455

Colorado Springs Utilities (Gas) Tim Benedict tbenedict@csu.org

719-668-3574

City of Manitou Springs Utilities (Water/Waste Water) Dan Olson dolson@manitouspringsco.gov

719-492-2335

Comcast Tod Bell tod_bell@cable.comcast.com

719-442-4733

The work described in these plans and specifications requires coordination between the Contractor and the utility companies in accordance with Subsection 105.11 in conducting their respective operations as necessary to complete the utility work with minimum delay to the project.

All new underground facilities, including laterals up to the structure or building being served, installed as part of this project must be electronically locatable when installed, in compliance with Colorado Revised Statutes, Title 9, Article 1.5.

PART 1 - CONTRACTOR SHALL PERFORM THE WORK LISTED BELOW:

Coordinate project construction with performance by the utility owner of each utility work element listed in Part 2 below. Perform preparatory work specified in Part 2 for each utility work element. Provide an accurate construction schedule that includes all utility work elements to the owner of each impacted utility. Provide each utility owner with periodic updates to the schedule. Conduct necessary utility coordination meetings, and provide other necessary accommodations as directed by the Engineer. Notify each utility owner in writing, with a copy to the Engineer, prior to the time each utility work element is to be performed by the utility owner. Provide notice, as specified in Part 2, immediately prior to the time the utility work must begin to meet the project schedule.

Provide traffic control, as directed by the Engineer, for any utility work performed by the utility owner within the project limits expected to be coordinated with construction. However, traffic control for utility work outside of typical project work hours shall be the responsibility of the utility owner.

Perform each utility work element for every utility owner listed in Part 1. Notify each utility owner in advance of any work being done by the Contractor to its facility, so that the utility owner can coordinate its inspections for final acceptance of the work with the Engineer. Obtain written acceptance from the utility owner for work performed by Contractor.

Request and receive utility locates prior to commencing any type of excavation. Based upon these locates, guardrail and other improvements may need to be adjusted as directed by the Engineer to avoid a utility. Hand digging, non-

PSP-22

Project No. 2024-015 09/24/2024 invasive installations, along with test holing, may be required if a utility is within 5 feet of a proposed guardrail post location.

All Utility Companies

The Contractor will contact each utility company a minimum of 2 business days, unless otherwise noted, prior to working in the utility company’s area so that the utility company can provide an inspector and/or complete any necessary adjustments or relocations.

If a need for utility work by either the Contractor or a utility company arises, the following shall apply: The Contractor shall be responsible for coordinating the adjustment of utilities on this…

This is the start of the file's text. The full file is on GovTribe.