RFB 14041 Summary.pdf

PDF 83 KB Posted

Attached to
West Gilman Street and University Avenue at North Park Street
Solicitation number
RFB 14041-0-2025-TJ
Issued by
Dane County, Madison City, Wisconsin

About this file

This document is a bid tabulation from the City of Madison for RFB 14041-0-2025-TJ, involving pavement marking work at West Gilman Street, University Avenue, and North Park Street. The project involves various pavement marking services including skid-resistant thermoplastic bike lane markings, epoxy line markings, crosswalk markings, stop lines, and symbol markings, along with corresponding pavement marking removal. The total quantities range from 1 to 650 units across different line items, with three bidders submitting proposals: Century Traffic LLC, Taza Construction, and Forward Traffic & Marking LLC.

Forward Traffic & Marking LLC was awarded the contract, submitting the lowest total bid for both project segments. For the Gilman Contra Flow Lane section, their total bid was $9,336.52, and for the University Avenue and North Park section, their total was $9,289.33, significantly undercutting the other bidders. The bid includes detailed unit pricing for various pavement marking types, with unit costs ranging from $0.49 to $270.84 depending on the specific marking type and size. No local vendor preference was noted, and all three bidders were classified as non-local vendors.

View the file

Other files

File Type Posted
Form D2 Cost Proposal.xlsx XLSX spreadsheet
RFB 14041.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Madison

RFB 14041-0-2025-TJ

West Gilman Street and University Avenue at North Park Street Awarded to: Forward Traffic & Marking LLC

City of Madison Standard Bid Item

Bid Item Description Total Quantity

Unit of Measurement Unit Cost Extended Price Unit Cost Extended Price Unit Cost Extended Price

60894 Skid/Slip Resistant Preformed Thermoplastic Pavement Marking, Bike Lane Green (SQFT) 350 Square Foot $32.50 $11,375.00 $19.00 $6,650.00 $12.57 $4,399.50

60840 Pavement Marking Epoxy, Line, 4-Inch 650 Linear Foot $3.75 $2,437.50 $4.00 $2,600.00 $0.49 $318.50 60841 Pavement Marking Epoxy, Double Line, 4-Inch 400 Linear Foot $7.50 $3,000.00 $8.00 $3,200.00 $0.97 $388.00

60856 Pavement Marking Epoxy, Continental Crosswalk, 18- Inch 84 Linear Foot $18.75 $1,575.00 $20.00 $1,680.00 $28.44 $2,388.96

60818 Pavement Marking Epoxy, Stop Line, 24-Inch 20 Linear Foot $22.50 $450.00 $21.00 $420.00 $18.41 $368.20

60831 Pavement Marking Epoxy, Symbol, Bike Straight Arrow 4 Each $250.00 $1,000.00 $370.00 $1,480.00 $270.84 $1,083.36

60883 Pavement Marking Removal, 12-Inch 50 Linear Foot $8.75 $437.50 $7.00 $350.00 $5.00 $250.00 60885 Pavement Marking Removal, 24-Inch 7 Linear Foot $17.50 $122.50 $12.00 $84.00 $20.00 $140.00

Total: $20,397.50 Total: 16,464.00 Total: 9,336.52 Local Vendor: N/A Local Vendor: N/A Local Vendor: N/A

City of Madison Standard Bid Item

Bid Item Description Total Quantity

Unit of Measurement

Unit Cost Extended Price Unit Cost Extended Price Unit Cost Extended Price

60894 Skid/Slip Resistant Preformed Thermoplastic Pavement Marking, Bike Lane Green (SQFT) 180 Square Foot $32.50 $5,850.00 $30.00 $5,400.00 $12.57 $2,262.60 Pavement Marking Removal, Remaining Exisiting Green Markings 575 Square Foot $2.50 $1,437.50 $3.25 $1,868.75 $3.00 $1,725.00

60803 Pavement Marking Epoxy, Line, 8-Inch 25 Linear Foot $5.00 $125.00 $4.50 $112.50 $1.23 $30.75 60814 Pavement Marking Epoxy, Crosswalk, 12-Inch 150 Linear Foot $11.25 $1,687.50 $12.00 $1,800.00 $17.18 $2,577.00 60818 Pavement Marking Epoxy, Stop Line, 24-Inch 30 Linear Foot $22.50 $675.00 $21.00 $630.00 $18.41 $552.30

60831 Pavement Marking Epoxy, Symbol, Bike Straight Arrow 2 Each $250.00 $500.00 $370.00 $740.00 $270.84 $541.68

60882 Pavement Marking Removal, 8-Inch 25 Linear Foot $1.25 $31.25 $3.75 $93.75 $4.00 $100.00 60883 Pavement Marking Removal, 12-Inch 150 Linear Foot $2.50 $375.00 $4.75 $712.50 $5.00 $750.00 60885 Pavement Marking Removal, 24-Inch 30 Linear Foot $5.00 $150.00 $6.00 $180.00 $20.00 $600.00

60889 Pavement Marking Removal, Symbol, Bike Lane 1 Each $62.50 $62.50 $90.00 $90.00 $75.00 $75.00

60891 Pavement Marking Removal, Symbol, Bike Arrow

1 Each $62.50 $62.50 $90.00 $90.00 $75.00 $75.00 Total: $10,956.25 Total: $11,717.50 Total: $9,289.33

Local Vendor: N/A Local Vendor: N/A Local Vendor: N/A

Forward Traffic & Marking LLC

Century Traffic LLC Forward Traffic & Marking LLC

Green Markings for Gilman Contra Flow Lane Taza Construction DBA of Tiles in Style LLC

Green Markings for University Avenue and North Park Taza Construction DBA of Tiles in Style LLC

Century Traffic LLC

Sheet1