1. THIS CONTRACT IS A RATED ORDER

RATING

PAGE OF

PAGES

UNDER DPAS (15 CFR 700)

2. CONTRACT NUMBER

3. SOLICITATION NUMBER

4. TYPE OF SOLICITATION

5. DATE ISSUED

6. REQUISITION/PURCHASE NUMBER

SEALED BID (IFB)

NEGOTIATED (RFP)

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

(If other than Item 7) NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

9. Sealed offers in original and _____four (4)________________________ copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in Until 3:00 p.m.

local time ___May 9, 2007____________________ (Hour) (Date) CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All Offers are subject to all terms and conditions contained in this solicitation.

A. NAME

B. TELEPHONE (NO COLLECT CALLS)

C. E-MAIL ADDRESS

AREA CODE

NUMBER

EXT.

(X)

SEC.

DESCRIPTION

PAGE(S)

(X)

SEC.

DESCRIPTION

PAGE(S)

PART I - THE SCHEDULE

PART II - CONTRACT CLAUSES

A

SOLICITATION/CONTRACT FORM

I

CONTRACT CLAUSES

B

SUPPLIES OR SERVICES AND PRICES/COSTS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

C

DESCRIPTION/SPECS./WORK STATEMENT

J

LIST OF ATTACHMENTS

D

PACKAGING AND MARKING

PART IV - REPRESENTATIONS AND INSTRUCTIONS

E

INSPECTION AND ACCEPTANCE

F

DELIVERIES OR PERFORMANCE

G

CONTRACT ADMINISTRATION DATA

L

INSTR., CONDS., AND NOTICES TO OFFERORS

H

SPECIAL CONTRACT REQUIREMENTS

M

EVALUATION FACTORS FOR AWARD

K

REPRESENTATIONS, CERTIFICATIONS AND OTHER

STATEMENTS OF OFFERORS

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

12. In compliance with the above, the undersigned agrees, if this offer is accepted within ________ calendar days (60 calendar days unless a different period is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

10 CALENDAR DAYS (%)

20 CALENDAR DAYS (%)

30 CALENDAR DAYS (%)

CALENDAR DAYS (%)

(See Section I, Clause No. 52-232-8)

14. ACKNOWLEDGEMENT OF AMENDMENTS

AMENDMENT NO.

DATE

AMENDMENT NO.

DATE

(The offeror acknowledges receipt of amendments to the SOLICITATION for offerors and related documents numbered and dated:

CODE

FACILITY

16. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

15A. NAME AND

ADDRESS

OF OFFEROR

(Type or print)

15B. TELEPHONE NUMBER

17. SIGNATURE

18. OFFER DATE

AREA CODE

NUMBER

EXT.

15C. CHECK IF REMITTANCE ADDRESS IS DIFFERENT FROM

ABOVE - ENTER SUCH ADDRESS IN SCHEDULE

19. ACCEPTED AS TO ITEMS NUMBERED

20. AMOUNT

21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

23. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

(4 copies unless otherwise specified) 10 U.S.C. 2304(a) ( ) 41 U.S.C. 253(c) ( )

24. ADMINISTERED BY (If other than Item 7)

25. PAYMENT WILL BE MADE BY

CODE

CODE

26. NAME OF CONTRACTING OFFICER (Type or print)

27. UNITED STATES OF AMERICA

28. AWARD DATE

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

(Signature of Contracting Officer)

(REV. 9-97)

10. FOR INFORMATION CALL:

11. TABLE OF CONTENTS

AUTHORIZED FOR LOCAL REPRODUCTION

STANDARD FORM 33

Previous edition is unusable Prescribed by GSA-FAR (48 CFR) 53.214(c)

SOLICITATION, OFFER AND AWARD

SOLICITATION

OFFER (Must be fully completed by offeror) AWARD (To be completed by Government) N/A 52

RES-07-047

X U.S. Nuclear Regulatory Commission Division of Contracts Mail Stop: T-7-I-2 Contract Management Branch 2 Washington DC 20555

NEHA DHIR

301-415-6594 nsd@nrc.gov See Attached Table of Contents X X X X X X X X X X X X X

See Section L.6, Timely Receipt of Proposals

Table of Contents

HYPERLINK \l "_Toc163973951" PART I - THE SCHEDULEA-1
HYPERLINK \l "_Toc163973952" SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTSB-1
HYPERLINK \l "_Toc163973953" B.1 PROJECT TITLEB-1
HYPERLINK \l "_Toc163973954" B.2 BRIEF DESCRIPTION OF WORK (MAR 1987)B-1
HYPERLINK \l "_Toc163973955" B.3 CONSIDERATION AND OBLIGATION--COST PLUS FIXED FEE (JUN 1988) ALTERNATE I (JUN 1991)B-1
HYPERLINK \l "_Toc163973956" SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORKC-1
HYPERLINK \l "_Toc163973957" SECTION D - PACKAGING AND MARKINGD-1
HYPERLINK \l "_Toc163973958" D.1 PACKAGING AND MARKING (MAR 1987)D-1
HYPERLINK \l "_Toc163973959" SECTION E - INSPECTION AND ACCEPTANCEE-1
HYPERLINK \l "_Toc163973960" E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCEE-1
HYPERLINK \l "_Toc163973961" E.2 PLACE OF INSPECTION AND ACCEPTANCE (MAR 1987)E-1
HYPERLINK \l "_Toc163973962" E.3 QUALITY ASSURANCEE-1
HYPERLINK \l "_Toc163973963" SECTION F - DELIVERIES OR PERFORMANCEF-1
HYPERLINK \l "_Toc163973964" F.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCEF-1
HYPERLINK \l "_Toc163973965" F.2 2052.211-70 PREPARATION OF TECHNICAL REPORTS (JAN 1993)F-1
HYPERLINK \l "_Toc163973966" F.3 2052.211-72 FINANCIAL STATUS REPORT (OCT 1999)F-1
HYPERLINK \l "_Toc163973967" F.4 PLACE OF DELIVERY--REPORTS (JUN 1988)F-2
HYPERLINK \l "_Toc163973968" F.5 DURATION OF CONTRACT PERIOD (MAR 1987)F-3
HYPERLINK \l "_Toc163973969" SECTION G - CONTRACT ADMINISTRATION DATAG-1
HYPERLINK \l "_Toc163973970" G.1 PROJECT OFFICER AUTHORITY (FEB 2004)G-1
HYPERLINK \l "_Toc163973971" G.2 2052.215-77 TRAVEL APPROVALS AND REIMBURSEMENT (OCT 1999)G-2
HYPERLINK \l "_Toc163973972" G.3 2052.216-71 INDIRECT COST RATES (JAN 1993)G-3
HYPERLINK \l "_Toc163973973" SECTION H - SPECIAL CONTRACT REQUIREMENTSH-1
HYPERLINK \l "_Toc163973974" H.1 2052.204.70 SECURITY (MAR 2004)H-1
HYPERLINK \l "_Toc163973975" H.2 2052.204-71 BADGE REQUIREMENTS FOR UNESCORTED BUILDING ACCESS TO NRC FACILITIES (MAR 2006)H-2
HYPERLINK \l "_Toc163973976" H.3 2052.209-72 CONTRACTOR ORGANIZATIONAL CONFLICTS OF INTEREST (JAN 1993)H-3
HYPERLINK \l "_Toc163973977" H.4 2052.215-70 KEY PERSONNEL (JAN 1993)H-5
HYPERLINK \l "_Toc163973978" H.5 2052.235-70 PUBLICATION OF RESEARCH RESULTS (OCT 1999)H-6
HYPERLINK \l "_Toc163973979" H.6 2052.242-70 RESOLVING NRC CONTRACTOR DIFFERING PROFESSIONAL VIEWS (DPVS) (OCT 1999)H-7
HYPERLINK \l "_Toc163973980" H.7 2052.242-71 PROCEDURES FOR RESOLVING NRC CONTRACTOR DIFFERING PROFESSIONAL VIEWS (DPVS) (OCT 1999)H-7
HYPERLINK \l "_Toc163973981" H.8 SECURITY REQUIREMENTS FOR INFORMATION TECHNOLOGY ACCESS APPROVAL (FEB 2004)H-8
HYPERLINK \l "_Toc163973982" H.9 GOVERNMENT FURNISHED EQUIPMENT/PROPERTY (JANUARY 2001)H-10
HYPERLINK \l "_Toc163973983" H.10 SEAT BELTSH-11
HYPERLINK \l "_Toc163973984" H.11 APPROPRIATE USE OF GOVERNMENT FURNISHED INFORMATION TECHNOLOGY (IT) EQUIPMENT AND/ OR IT SERVICES/ ACCESS (MARCH 2002)H-11
HYPERLINK \l "_Toc163973985" H.12 Compliance with U.S. Immigration Laws and RegulationsH-12
HYPERLINK \l "_Toc163973986" H.13 NRC INFORMATION TECHNOLOGY SECURITY TRAINING (AUG 2003)H-12
HYPERLINK \l "_Toc163973987" H.14 SECURITY REQUIREMENTS RELATING TO THE PRODUCTION OF REPORT(S) OR THE PUBLICATION OF RESULTS UNDER CONTRACTS, AGREEMENTS, AND GRANTS.H-13
HYPERLINK \l "_Toc163973988" PART II - CONTRACT CLAUSESI-1
HYPERLINK \l "_Toc163973989" SECTION I - CONTRACT CLAUSESI-1
HYPERLINK \l "_Toc163973990" I.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCEI-1
HYPERLINK \l "_Toc163973991" I.2 52.222-39 NOTIFICATION OF EMPLOYEE RIGHTS CONCERNING PAYMENT OF UNION DUES OR FEES (DEC 2004)I-3
HYPERLINK \l "_Toc163973992" I.3 52.232-25 PROMPT PAYMENT (OCT 2003)I-4
HYPERLINK \l "_Toc163973993" I.4 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)I-8
HYPERLINK \l "_Toc163973994" PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTSJ-1
HYPERLINK \l "_Toc163973995" SECTION J - LIST OF ATTACHMENTSJ-1
HYPERLINK \l "_Toc163973996" PART IV - REPRESENTATIONS AND INSTRUCTIONSK-1
HYPERLINK \l "_Toc163973997" SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORSK-1
HYPERLINK \l "_Toc163973998" K.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCEK-1
HYPERLINK \l "_Toc163973999" K.2 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2006)K-1
HYPERLINK \l "_Toc163974000" K.3 52.230-1 COST ACCOUNTING STANDARDS NOTICES AND CERTIFICATION (JUNE 2000)K-2
HYPERLINK \l "_Toc163974001" K.4 52.230-7 PROPOSAL DISCLOSURE--COST ACCOUNTING PRACTICE CHANGES (APR 2005)K-4
HYPERLINK \l "_Toc163974002" K.5 2052.209-70 CURRENT/FORMER AGENCY EMPLOYEE INVOLVEMENT (OCT 1999)K-4
HYPERLINK \l "_Toc163974003" K.6 2052.209-71 CONTRACTOR ORGANIZATIONAL CONFLICTS OF INTEREST (REPRESENTATION) (OCT 1999)K-5
HYPERLINK \l "_Toc163974004" SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORSL-1
HYPERLINK \l "_Toc163974005" L.1 NOTICE LISTING SOLICITATION PROVISIONS INCORPORATED BY REFERENCEL-1
HYPERLINK \l "_Toc163974006" L.2 52.215-20 REQUIREMENTS FOR COST OR PRICING DATA OR INFORMATION OTHER THAN COST OR PRICING DATA (OCT 1997)L-1
HYPERLINK \l "_Toc163974007" L.3 52.216-1 TYPE OF CONTRACT (APR 1984)L-2
HYPERLINK \l "_Toc163974008" L.4 52.233-2 SERVICE OF PROTEST (SEP 2006)L-2

HYPERLINK \l "_Toc163974009" L.5 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)L-3

HYPERLINK \l "_Toc163974010" L.6 2052.215-72 TIMELY RECEIPT OF PROPOSALS (OCT 1999)L-3
HYPERLINK \l "_Toc163974011" L.7 2052.215-73 AWARD NOTIFICATION AND COMMITMENT OF PUBLIC FUNDS (OCT 1999)L-3
HYPERLINK \l "_Toc163974012" L.8 2052.215-74 DISPOSITION OF PROPOSALS (JAN 1993)L-4
HYPERLINK \l "_Toc163974013" L.9 2052.215-75 PROPOSAL PRESENTATION AND FORMAT (OCT 1999)L-4
HYPERLINK \l "_Toc163974014" L.10 2052.216-70 LEVEL OF EFFORT (JAN 1993)L-8
HYPERLINK \l "_Toc163974015" L.11 2052.222-70 NONDISCRIMINATION BECAUSE OF AGE (JAN 1993)L-9
HYPERLINK \l "_Toc163974016" L.12 ESTIMATED DURATION (JUN 1988)L-9
HYPERLINK \l "_Toc163974017" L.13 USE OF AUTOMATED CLEARING HOUSE (ACH) ELECTRONIC PAYMENT/REMITTANCE ADDRESSL-9
HYPERLINK \l "_Toc163974018" L.14 SUBMISSION OF QUESTIONSL-10
HYPERLINK \l "_Toc163974019" SECTION M - EVALUATION FACTORS FOR AWARDM-1
HYPERLINK \l "_Toc163974020" M.1 2052.215-79 CONTRACT AWARD AND EVALUATION OF PROPOSALS (OCT 1999)M-1
HYPERLINK \l "_Toc163974021" M.2 EVALUATION FACTORSM-2
RES-07-047Section B
B-1

PART I - THE SCHEDULE

SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS

B.1 PROJECT TITLE

The title of this project is as follows:

Review and Analysis of Operational Events for Accident Sequence Precursors and Probabilistic Analysis of Other Issues

B.2 BRIEF DESCRIPTION OF WORK (MAR 1987)

The primary objective of this effort is to systematically evaluate U.S. nuclear plant operating experience to identify and document the operating events that were most likely to lead to inadequate core cooling and severe core damage (precursors), if additional failures occurred. Using standardized plant-specific models provided by the NRC, the contractor shall perform detailed risk analyses of events or conditions that have occurred during all phases of reactor operations.

B.3 CONSIDERATION AND OBLIGATION--COST PLUS FIXED FEE (JUN 1988) ALTERNATE I (JUN 1991)

(a) The total estimated cost to the Government for full performance of this contract is [_____________], of which the sum of [_____________] represents the estimated reimbursable costs, and of which [_____________] represents the fixed fee.

(b) There shall be no adjustment in the amount of the Contractor's fixed fee by reason of differences between any estimate of cost for performance of the work under this contract and the actual cost for performance of that work.

(c) The amount currently obligated by the Government with respect to this contract is [_____________], of which the sum of [_____________] represents the estimated reimbursable costs, and of which [_____________] represents the fixed fee.

(d) It is estimated that the amount currently allotted will cover performance through [______________].

RES-07-047Section C
C-1

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

See Section J, Attachment 1, Statement of Work RES-07-047Section D
D-1

SECTION D - PACKAGING AND MARKING

D.1 PACKAGING AND MARKING (MAR 1987)

The Contractor shall package material for shipment to the NRC in such a manner that will ensure acceptance by common carrier and safe delivery at destination. Containers and closures shall comply with the Interstate Commerce Commission Regulations, Uniform Freight Classification Rules, or regulations of other carriers as applicable to the mode of transportation. On the front of the package, the Contractor shall clearly identify the contract number under which the product is being provided.

RES-07-047Section E
E-1

SECTION E - INSPECTION AND ACCEPTANCE

E.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE

The following contract clauses pertinent to this section are hereby incorporated by reference (by Citation Number, Title, and Date) in accordance with the clause at FAR "52.252-2 CLAUSES INCORPORATED BY REFERENCE" in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.

NUMBERTITLEDATE
FEDERAL ACQUISITION REGULATION (48 CFR Chapter 1)
52.246-5INSPECTION OFAPR 1984
SERVICES--COST-REIMBURSEMENT

E.2 PLACE OF INSPECTION AND ACCEPTANCE (MAR 1987)

Inspection and acceptance of the deliverable items to be furnished hereunder shall be made by the Project Officer at the destination.

E.3 QUALITY ASSURANCE

The quality of NRC research programs are assessed each year by the Advisory Committee on Reactor Safeguards. Within the context of their reviews of RES programs, the definition of quality research is based upon several major characteristics:

1.Results meet the objectives (75% of overall score)
Justification of major assumptions (12%)
Soundness of technical approach and results (52%)
Uncertainties and sensitivities addressed (11%)
2.Documentation of research results and methods is adequate (25% of overall score)
Clarity of presentation (16%)
Identification of major assumptions (9%)

Prior to submitting deliverables to the agency, the contractor shall incorporate sufficient review and quality checks to ensure that the deliverable is technically sound, the assumptions made in the analysis are appropriate and have been adequately justified, and that the text documenting the analysis is clear and easy to follow so that the Licensee’s staff will be able to complete their review in a timely manner, without the need to obtain clarifying information regarding the analysis.

RES-07-047Section F
F-3

SECTION F - DELIVERIES OR PERFORMANCE

F.1 NOTICE LISTING CONTRACT CLAUSES INCORPORATED BY REFERENCE

The following contract clauses pertinent to this section are hereby incorporated by reference (by Citation Number, Title, and Date) in accordance with the clause at FAR "52.252-2 CLAUSES INCORPORATED BY REFERENCE" in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to the full text of a clause.

NUMBERTITLEDATE
FEDERAL ACQUISITION REGULATION (48 CFR Chapter 1)
52.242-15STOP-WORK ORDERAUG 1989
ALTERNATE I (APR 1984)
52.247-34F.O.B. DESTINATIONNOV 1991

F.2 2052.211-70 PREPARATION OF TECHNICAL REPORTS (JAN 1993)

All technical reports required by Section C and all Technical Progress Reports required by Section F are to be prepared in accordance with Management Directive 3.7, "NUREG Series Publications" available at http://www.nrc.gov/reading-rm/doc-collections/management-directives/" http://www.nrc.gov/reading-rm/doc-collections/management-directives/. Management Directive 3.7 is not applicable to any Contractor Spending Plan (CSP) and any Financial Status Report that may be included in this contract.

F.3 2052.211-72 FINANCIAL STATUS REPORT (OCT 1999)

The contractor shall provide a monthly Financial Status Report (FSR) to the project officer and the contracting officer. The FSR shall include the acquisition of, or changes in the status of, contractor-held property acquired with government funds valued at the time of purchase at $50,000 or more. Whenever these types of property changes occur, the contractor shall send a copy of the report to the Chief, Property and Acquisition Oversight Branch, Office of Administration. The report is due within 15 calendar days after the end of the report period and must identify the title of the project, the contract number, the appropriate financial tracking code (e.g., Job Code Number or JCN) specified by the NRC Project Officer, project manager and/or principal investigator, the contract period of performance, and the period covered by the report. Each report must include the following for each discrete task:

(a) Total estimated contract amount.

(b) Total funds obligated to date.

(c) Total costs incurred this reporting period.

(d) Total costs incurred to date.

(e) Detail of all direct and indirect costs incurred during the reporting period for the entire contract or each task, if it is a task ordering contract.

(f) Balance of obligations remaining.

(g) Balance of funds required to complete contract/task order.

(h) Contractor Spending Plan (CSP) status: A revised CSP is required with the Financial Status Report whenever the contractor or the contracting officer has reason to believe that the total cost for performance of this contract will be either greater or substantially less than what had been previously estimated.

(1) Projected percentage of completion cumulative through the report period for the project/task order as reflected in the current CSP.

(2) Indicate significant changes in the original CSP projection in either dollars or percentage of completion. Identify the change, the reasons for the change, whether there is any projected overrun, and when additional funds would be required. If there have been no changes to the original NRC-approved CSP projections, a written statement to that effect is sufficient in lieu of submitting a detailed response to item "h".

(i) Property status:

(1) List property acquired for the project during the month with an acquisition cost between $500 and $49,999. Give the item number for the specific piece of equipment.

(2) Provide a separate list of property acquired for the project during the month with an acquisition cost of $50,000 or more. Provide the following information for each item of property: item description or nomenclature, manufacturer, model number, serial number, acquisition cost, and receipt date. If no property was acquired during the month, include a statement to that effect. The same information must be provided for any component or peripheral equipment which is part of a "system or system unit."

(3) For multi-year projects, in the September monthly financial status report provide a cumulative listing of property with an acquisition cost of $50,000 or more showing the information specified in paragraph (i)(2) of this clause.

(4) In the final financial status report provide a closeout property report containing the same elements as described above for the monthly financial status reports, for all property purchased with NRC funds regardless of value unless title has been vested in the contractor. If no property was acquired under the contract, provide a statement to that effect. The report should note any property requiring special handling for security, health, safety, or other reasons as part of the report.

(j) Travel status: List the starting and ending dates for each trip, the starting point and destination, and the traveler(s) for each trip.

(k) If the data in this report indicates a need for additional funding beyond that already obligated, this information may only be used as support to the official request for funding required in accordance with the Limitation of Cost (LOC) Clause (FAR 52.232-20) or the Limitation of Funds (LOF) Clause FAR 52.232-22.

F.4 PLACE OF DELIVERY--REPORTS (JUN 1988)

The items to be furnished hereunder shall be delivered, with all charges paid by the Contractor, to:

(a) Project Officer (1 copies)

[to be completed at time of award]

(b) Contracting Officer (1 copy)

F.5 DURATION OF CONTRACT PERIOD (MAR 1987)

This contract shall commence on the date specified in Block 5 of the SF 33 and will expire in four (4) years and three (3) months.

RES-07-047Section G
G-3

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 PROJECT OFFICER AUTHORITY (FEB 2004)

(a) The contracting officer's authorized representative hereinafter referred to as the project officer for this contract is:

Name: [to be completed at time of award]

Address: [to be completed at time of award]

Telephone Number: [to be completed at time of award]

(b) Performance of the work under this contract is subject to the technical direction of the NRC project officer. The term “technical direction” is defined to include the following:

(1) Technical direction to the contractor which shifts work emphasis between areas of work or tasks, authorizes travel which was unanticipated in the Schedule (i.e., travel not contemplated in the Statement of Work (SOW) or changes to specific travel identified in the SOW), fills in details, or otherwise serves to accomplish the contractual SOW.

(2) Provide advice and guidance to the contractor in the preparation of drawings, specifications, or technical portions of the work description.

(3) Review and, where required by the contract, approval of technical reports, drawings, specifications, and technical information to be delivered by the contractor to the Government under the contract.

(c) Technical direction must be within the general statement of work stated in the contract. The project officer does not have the authority to and may not issue any technical direction which:

(1) Constitutes an assignment of work outside the general scope of the contract.

(2) Constitutes a change as defined in the "Changes" clause of this contract.

(3) In any way causes an increase or decrease in the total estimated contract cost, the fixed fee, if any, or the time required for contract performance.

(4) Changes any of the expressed terms, conditions, or specifications of the contract.

(5) Terminates the contract, settles any claim or dispute arising under the contract, or issues any unilateral directive whatever.

(d) All technical directions must be issued in writing by the project officer or must be confirmed by the project officer in writing within ten (10) working days after verbal issuance. A copy of the written direction must be furnished to the contracting officer. A copy of NRC Form 445, Request for Approval of Official Foreign Travel, which has received final approval from the NRC must be furnished to the contracting officer.

(e) The contractor shall proceed promptly with the performance of technical directions duly issued by the project officer in the manner prescribed by this clause and within the project officer's authority under the provisions of this clause.

(f) If, in the opinion of the contractor, any instruction or direction issued by the project officer is within one of the categories as defined in paragraph (c) of this section, the contractor may not proceed but shall notify the contracting officer in writing within five (5) working days after the receipt of any instruction or direction and shall request the contracting officer to modify the contract accordingly. Upon receiving the notification from the contractor, the contracting officer shall issue an appropriate contract modification or advise the contractor in writing that, in the contracting officer's opinion, the technical direction is within the scope of this article and does not constitute a change under the "Changes" clause.

(g) Any unauthorized commitment or direction issued by the project officer may result in an unnecessary delay in the contractor's performance and may even result in the contractor expending funds for unallowable costs under the contract.

(h) A failure of the parties to agree upon the nature of the instruction or direction or upon the contract action to be taken with respect thereto is subject to 52.233.1 . Disputes.

(i) In addition to providing technical direction as defined in paragraph (b) of the section, the project officer shall:

(1) Monitor the contractor's technical progress, including surveillance and assessment of performance, and recommend to the contracting officer changes in requirements.

(2) Assist the contractor in the resolution of technical problems encountered during performance.

(3) Review all costs requested for reimbursement by the contractor and submit to the contracting officer recommendations for approval, disapproval, or suspension of payment for supplies and services required under this contract.

(4) Assist the contractor in obtaining the badges for the contractor personnel.

(5) Immediately notify the Security Branch, Division of Facilities and Security (SB/DFS) (via e-mail) when a contractor employee no longer requires access authorization and return of any NRC issued badge to SB/DFS within three days after their termination.”

(6) Ensure that all contractor employees that require access to classified Restricted Data or National Security Information or matter, access to sensitive unclassified information (Safeguards, Official Use Only, and Proprietary information) access to sensitive IT systems or data, unescorted access to NRC controlled buildings/space, or unescorted access to protected and vital areas of nuclear power plants receive approval of SB/DFS prior to access in accordance with Management Directive and Handbook 12.3.

G.2 2052.215-77 TRAVEL APPROVALS AND REIMBURSEMENT (OCT 1999)

(a) All foreign travel must be approved in advance by the NRC on NRC Form 445, Request for Approval of Official Foreign Travel, and must be in compliance with FAR 52.247-63 Preference for U.S. Flag Air Carriers. The contractor shall submit NRC Form 445 to the NRC no later than 30 days before beginning travel.

(b) The contractor must receive written approval from the NRC Project Officer before taking travel that was unanticipated in the Schedule (i.e., travel not contemplated in the Statement of Work, or changes to specific travel identified in the Statement of Work).

(c) The contractor will be reimbursed only for those travel costs incurred that are directly related to this contract and are allowable subject to the limitations prescribed in FAR 31.205-46.

(d) It is the responsibility of the contractor to notify the contracting officer in accordance with the Limitations of Cost clause of this contract when, at any time, the contractor learns that travel expenses will cause the contractor to exceed the estimated costs specified in the Schedule.

(e) Reasonable travel costs for research and related activities performed at State and nonprofit institutions, in accordance with Section 12 of Pub. L. 100-679, shall be charged in accordance with the contractor's institutional policy to the degree that the limitations of Office of Management and Budget (OMB) guidance are not exceeded. Applicable guidance documents include OMB Circular A-87, Cost Principles for State and Local Governments; OMB Circular A-122, Cost Principles for Nonprofit Organizations; and OMB Circular A-21, Cost Principles for Educational Institutions.

G.3 2052.216-71 INDIRECT COST RATES (JAN 1993)

(a) Pending the establishment of final indirect rates which must be negotiated based on audit of actual costs, the contractor shall be reimbursed for allowable indirect costs as follows:

INDIRECT COST POOLRATEBASEPERIOD
[to be00
completed at00

time of award]

(b) The contracting officer may adjust these rates as appropriate during the term of the contract upon acceptance of any revisions proposed by the contractor. It is the contractor's responsibility to notify the contracting officer in accordance with FAR 52.232-20, Limitation of Cost, or FAR 52.232-22, Limitation of Funds, as applicable, if these changes affect performance of work within the established cost or funding limitations.

RES-07-047Section H
H-14

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 2052.204.70 SECURITY (MAR 2004)

(a) Contract Security and/or Classification Requirements (NRC Form 187). The policies, procedures, and criteria of the NRC Security Program, NRC Management Directive (MD) 12 (including MD 12.1, "NRC Facility Security Program;" MD 12.2, "NRC Classified Information Security Program;" MD 12.3, "NRC Personnel Security Program;" MD 12.4, "NRC Telecommunications Systems Security Program;" MD 12.5, "NRC Automated Information Systems Security Program;" and MD 12.6, "NRC Sensitive Unclassified Information Security Program"), apply to performance of this contract, subcontract or other activity. This MD is incorporated into this contract by reference as though fully set forth herein. The attached NRC Form 187 (See List of Attachments) furnishes the basis for providing security and classification requirements to prime contractors, subcontractors, or others (e.g., bidders) who have or may have an NRC contractual relationship that requires access to classified Restricted Data or National Security Information or matter, access to sensitive unclassified information (e.g., Safeguards), access to sensitive Information Technology (IT) systems or data, unescorted access to NRC controlled buildings/space, or unescorted access to protected and vital areas of nuclear power plants.

(b) It is the contractor's duty to protect National Security Information, Restricted Data, and Formerly Restricted Data. The contractor shall, in accordance with the Commission's security regulations and requirements, be responsible for protecting National Security Information, Restricted Data, and Formerly Restricted Data, and for protecting against sabotage, espionage, loss, and theft, the classified documents and material in the contractor's possession in connection with the performance of work under this contract. Except as otherwise expressly provided in this contract, the contractor shall, upon completion or termination of this contract, transmit to the Commission any classified matter in the possession of the contractor or any person under the contractor's control in connection with performance of this contract. If retention by the contractor of any classified matter is required after the completion or termination of the contract and the retention is approved by the contracting officer, the contractor shall complete a certificate of possession to be furnished to the Commission specifying the classified matter to be retained. The certification must identify the items and types or categories of matter retained, the conditions governing the retention of the matter and their period of retention, if known. If the retention is approved by the contracting officer, the security provisions of the contract continue to be applicable to the matter retained.

(c) In connection with the performance of the work under this contract, the contractor may be furnished, or may develop or acquire, safeguards information, or confidential or privileged technical, business, or financial information, including Commission plans, policies, reports, financial plans, internal data protected by the Privacy Act of 1974 (Pub. L. 93.579), or other information which has not been released to the public or has been determined by the Commission to be otherwise exempt from disclosure to the public. The contractor shall ensure that information protected from public disclosure is maintained as required by NRC regulations and policies, as cited in this contract or as otherwise provided by the NRC. The contractor will not directly or indirectly duplicate, disseminate, or disclose the information in whole or in part to any other person or organization except as may be necessary to perform the work under this contract. The contractor agrees to return the information to the Commission or otherwise dispose of it at the direction of the contracting officer. Failure to comply with this clause is grounds for termination of this contract.

(d) Regulations. The contractor agrees to conform to all security regulations and requirements of the Commission which are subject to change as directed by the NRC Division of Facilities and Security (DFS) and the Contracting Officer. These changes will be under the authority of the FAR Changes clause referenced in this document.

The contractor agrees to comply with the security requirements set forth in NRC Management Directive 12.1, NRC Facility Security Program which is incorporated into this contract by reference as though fully set forth herein. Attention is directed specifically to the section titled "Infractions and Violations," including "Administrative Actions" and "Reporting Infractions."

(e) Definition of National Security Information. The term National Security Information, as used in this clause, means information that has been determined pursuant to Executive Order 12958 or any predecessor order to require protection against unauthorized disclosure and that is so designated.

(f) Definition of Restricted Data. The term Restricted Data, as used in this clause, means all data concerning design, manufacture, or utilization of atomic weapons; the production of special nuclear material; or the use of special nuclear material in the production of energy, but does not include data declassified or removed from the Restricted Data category pursuant to Section 142 of the Atomic Energy Act of 1954, as amended.

(g) Definition of Formerly Restricted Data. The term Formerly Restricted Data, as used in this clause, means all data removed from the Restricted Data category under Section 142-d of the Atomic Energy Act of 1954, as amended.

(h) Definition of Safeguards Information. Sensitive unclassified information that specifically identifies the detailed security measures of a licensee or an applicant for the physical protection of special nuclear material; or security measures for the physical protection and location of certain plant equipment vital to the safety of production of utilization facilities. Protection of this information is required pursuant to Section 147 of the Atomic Energy Act of 1954, as amended.

(i) Security Clearance. The contractor may not permit any individual to have access to Restricted Data, Formerly Restricted Data, or other classified information, except in accordance with the Atomic Energy Act of 1954, as amended, and the Commission's regulations or requirements applicable to the particular type or category of classified information to which access is required. The contractor shall also execute a Standard Form 312, Classified Information Nondisclosure Agreement, when access to classified information is required.

(j) Criminal Liabilities. It is understood that disclosure of National Security Information, Restricted Data, and Formerly Restricted Data relating to the work or services ordered hereunder to any person not entitled to receive it, or failure to safeguard any Restricted Data, Formerly Restricted Data, or any other classified matter that may come to the contractor or any person under the contractor's control in connection with work under this contract, may subject the contractor, its agents, employees, or subcontractors to criminal liability under the laws of the United States. (See the Atomic Energy Act of 1954, as amended, 42 U.S.C. 2011 et seq.; 18 U.S.C. 793 and 794; and Executive Order 12958.)

(k) Subcontracts and Purchase Orders. Except as otherwise authorized in writing by the contracting officer, the contractor shall insert provisions similar to the foregoing in all subcontracts and purchase orders under this contract.

(l) In performing the contract work, the contractor shall classify all documents, material, and equipment originated or generated by the contractor in accordance with guidance issued by the Commission. Every subcontract and purchase order issued hereunder involving the origination or generation of classified documents, material, and equipment must provide that the subcontractor or supplier assign classification to all documents, material, and equipment in accordance with guidance furnished by the contractor.

H.2 2052.204-71 BADGE REQUIREMENTS FOR UNESCORTED BUILDING ACCESS TO NRC FACILITIES (MAR 2006)

During the life of this contract, the rights of ingress and egress for contractor personnel must be made available, as required, provided that the individual has been approved for unescorted access after a favorable adjudication from the Security Branch, Division of Facilities and Security (SB/DFS).

In this regard, all contractor personnel whose duties under this contract require their presence on site shall be clearly identifiable by a distinctive badge furnished by the NRC. The Project Officer shall assist the contractor in obtaining badges for the contractor personnel. All contractor personnel must present two forms of Identity Source Documents (I-9). One of the documents must be a valid picture ID issued by a state or by the Federal Government. Original I-9 documents must be presented in person for certification. A list of acceptable documents can be found at http://www.usdoj.gov/crt/recruit_employ/i9form.pdf. It is the sole responsibility of the contractor to ensure that each employee has a proper NRC-issued identification/badge at all times. All photo-identification badges must be immediately (no later than three days) delivered to SB/DFS for cancellation or disposition upon the termination of employment of any contractor personnel. Contractor personnel must display any NRC issued badge in clear view at all times during on site performance under this contract. It is the contractor's duty to assure that contractor personnel enter only those work areas necessary for performance of contract work, and to assure the protection of any Government records or data that contractor personnel may come into contact with.

H.3 2052.209-72 CONTRACTOR ORGANIZATIONAL CONFLICTS OF INTEREST (JAN 1993)

(a) Purpose. The primary purpose of this clause is to aid in ensuring that the contractor:

(1) Is not placed in a conflicting role because of current or planned interests (financial, contractual, organizational, or otherwise) which relate to the work under this contract; and

(2) Does not obtain an unfair competitive advantage over other parties by virtue of its performance of this contract.

(b) Scope. The restrictions described apply to performance or participation by the contractor, as defined in 48 CFR 2009.570-2 in the activities covered by this clause.

(c) Work for others.

(1) Notwithstanding any other provision of this contract, during the term of this contract, the contractor agrees to forego entering into consulting or other contractual arrangements with any firm or organization the result of which may give rise to a conflict of interest with respect to the work being performed under this contract. The contractor shall ensure that all employees under this contract abide by the provision of this clause. If the contractor has reason to believe, with respect to itself or any employee, that any proposed consultant or other contractual arrangement with any firm or organization may involve a potential conflict of interest, the contractor shall obtain the written approval of the contracting officer before the execution of such contractual arrangement.

(2) The contractor may not represent, assist, or otherwise support an NRC licensee or applicant undergoing an NRC audit, inspection, or review where the activities that are the subject of the audit, inspection, or review are the same as or substantially similar to the services within the scope of this contract (or task order as appropriate) except where the NRC licensee or applicant requires the contractor's support to explain or defend the contractor's prior work for the utility or other entity which NRC questions.

(3) When the contractor performs work for the NRC under this contract at any NRC licensee or applicant site, the contractor shall neither solicit nor perform work in the same or similar technical area for that licensee or applicant organization for a period commencing with the award of the task order or beginning of work on the site (if not a task order contract) and ending one year after completion of all work under the associated task order, or last time at the site (if not a task order contract).

(4) When the contractor performs work for the NRC under this contract at any NRC licensee or applicant site,

(i) The contractor may not solicit work at that site for that licensee or applicant during the period of performance of the task order or the contract, as appropriate.

(ii) The contractor may not perform work at that site for that licensee or applicant during the period of performance of the task order or the contract, as appropriate, and for one year thereafter.

(iii) Notwithstanding the foregoing, the contracting officer may authorize the contractor to solicit or perform this type of work (except work in the same or similar technical area) if the contracting officer determines that the situation will not pose a potential for technical bias or unfair competitive advantage.

(d) Disclosure after award.

(1) The contractor warrants that to the best of its knowledge and belief, and except as otherwise set forth in this contract, that it does not have any organizational conflicts of interest as defined in 48 CFR 2009.570-2.

(2) The contractor agrees that if, after award, it discovers organizational conflicts of interest with respect to this contract, it shall make an immediate and full disclosure in writing to the contracting officer. This statement must include a description of the action which the contractor has taken or proposes to take to avoid or mitigate such conflicts. The NRC may, however, terminate the contract if termination is in the best interest of the Government.

(3) It is recognized that the scope of work of a task-order-type contract necessarily encompasses a broad spectrum of activities. Consequently, if this is a task-order-type contract, the contractor agrees that it will disclose all proposed new work involving NRC licensees or applicants which comes within the scope of work of the underlying contract. Further, if this contract involves work at a licensee or applicant site, the contractor agrees to exercise diligence to discover and disclose any new work at that licensee or applicant site. This disclosure must be made before the submission of a bid or proposal to the utility or other regulated entity and must be received by the NRC at least 15 days before the proposed award date in any event, unless a written justification demonstrating urgency and due diligence to discover and disclose is provided by the contractor and approved by the contracting officer. The disclosure must include the statement of work, the dollar value of the proposed contract, and any other documents that are needed to fully describe the proposed work for the regulated utility or other regulated entity. NRC may deny approval of the disclosed work only when the NRC has issued a task order which includes the technical area and, if site-specific, the site, or has plans to issue a task order which includes the technical area and, if site-specific, the site, or when the work violates paragraphs (c)(2), (c)(3) or (c)(4) of this section.

(e) Access to and use of information.

(1) If in the performance of this contract, the contractor obtains access to information, such as NRC plans, policies, reports, studies, financial plans, internal data protected by the Privacy Act of 1974 (5 U.S.C. Section 552a (1988)), or the Freedom of Information Act (5 U.S.C. Section 552 (1986)), the contractor agrees not to:

(i) Use this information for any private purpose until the information has been released to the public;

(ii) Compete for work for the Commission based on the information for a period of six months after either the completion of this contract or the release of the information to the public, whichever is first;

(iii) Submit an unsolicited proposal to the Government based on the information until one year after the release of the information to the public; or

(iv) Release the information without prior written approval by the contracting officer unless the information has previously been released to the public by the NRC.

(2) In addition, the contractor agrees that, to the extent it receives or is given access to proprietary data, data protected by the Privacy Act of 1974 (5 U.S.C. Section 552a (1988)), or the Freedom of Information Act (5 U.S.C. Section 552 (1986)), or other confidential or privileged technical, business, or financial information under this contract, the contractor shall treat the information in accordance with restrictions placed on use of the information.

(3) Subject to patent and security provisions of this contract, the contractor shall have the right to use technical data it produces under this contract for private purposes provided that all requirements of this contract have been met.

(f) Subcontracts. Except as provided in 48 CFR 2009.570-2, the contractor shall include this clause, including this paragraph, in subcontracts of any tier. The terms contract, contractor, and contracting officer, must be appropriately modified to preserve the Government's rights.

(g) Remedies. For breach of any of the above restrictions, or for intentional nondisclosure or misrepresentation of any relevant interest required to be disclosed concerning this contract or for such erroneous representations that necessarily imply bad faith, the Government may terminate the contract for default, disqualify the contractor from subsequent contractual efforts, and pursue other remedies permitted by law or this contract.

(h) Waiver. A request for waiver under this clause must be directed in writing to the contracting officer in accordance with the procedures outlined in 48 CFR 2009.570-9.

(i) Follow-on effort. The contractor shall be ineligible to participate in NRC contracts, subcontracts, or proposals therefor (solicited or unsolicited), which stem directly from the contractor's performance of work under this contract. Furthermore, unless so directed in writing by the contracting officer, the contractor may not perform any technical consulting or management support services work or evaluation activities under this contract on any of its products or services or the products or services of another firm if the contractor has been substantially involved in the development or marketing of the products or services.

(1) If the contractor, under this contract, prepares a complete or essentially complete statement of work or specifications, the contractor is not eligible to perform or participate in the initial contractual effort which is based on the statement of work or specifications. The contractor may not incorporate its products or services in the statement of work or specifications unless so directed in writing by the contracting officer, in which case the restrictions in this paragraph do not apply.

(2) Nothing in this paragraph precludes the contractor from offering or selling its standard commercial items to the Government.

H.4 2052.215-70 KEY PERSONNEL (JAN 1993)

(a) The following individuals are considered to be essential to the successful performance of the work hereunder:

[to be completed at time of award]

The contractor agrees that personnel may not be removed from the contract work or replaced without compliance with paragraphs (b) and (c) of this section.

(b) If one or more of the key personnel, for whatever reason, becomes, or is expected to become, unavailable for work under this contract for a continuous period exceeding 30 work days, or is expected to devote substantially less effort to the work than indicated in the proposal or initially anticipated, the contractor shall immediately notify the contracting officer and shall, subject to the con-currence of the contracting officer, promptly replace the personnel with personnel of at least substantially equal ability and qualifications.

(c) Each request for approval of substitutions must be in writing and contain a detailed explanation of the circumstances necessitating the proposed substitutions. The request must also contain a complete resume for the proposed substitute and other information requested or needed by the contracting officer to evaluate the proposed substitution. The contracting officer and the project officer shall evaluate the contractor's request and the contracting officer shall promptly notify the contractor of his or her decision in writing.

(d) If the contracting officer determines that suitable and timely replacement of key personnel who have been reassigned, terminated, or have otherwise become unavailable for the contract work is not reasonably forthcoming, or that the resultant reduction of productive effort would be so substantial as to impair the successful completion of the contract or the service order, the contract may be terminated by the contracting officer for default or for the convenience of the Government, as appropriate. If the contracting officer finds the contractor at fault for the condition, the contract price or fixed fee may be equitably adjusted downward to compensate the Government for any resultant delay, loss, or damage.

H.5 2052.235-70 PUBLICATION OF RESEARCH RESULTS (OCT 1999)

(a) The principal investigator(s)/contractor shall comply with the provisions of NRC Management Directive 3.8 (Vol. 3, Part 1) and NRC Handbook 3.8 (Parts I-IV) regarding publication in refereed scientific and engineering journals or dissemination to the public of any information, oral or written, concerning the work performed under this contract. Failure to comply with this clause shall be grounds for termination of this contract.

(b) The principal investigator(s)/contractor may publish the results of this work in refereed scientific and engineering journals or in open literature and present papers at public or association meetings at interim stages of work, in addition to submitting to NRC the final reports and other deliverables required under this…

This is the start of the file's text. The full file is on GovTribe.

Other files

File Type Posted
Amendment2.doc DOC document
2_Attachment6 OCOI.doc DOC document
Attachment3.DOC DOC document
Attachment5.DOC DOC document
Attachment4.DOC DOC document
Attachment1.pdf PDF
RFP.doc DOC document
Attachment2.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .