Amendment 03.pdf

PDF 102 KB Posted

Attached to
NESDIS Architectural and Engineering IDIQ
Solicitation number
REQUIREMENTS-24-1827
Issued by

About this file

Amendment 03 is a questions and answers document for the NESDIS Architectural and Engineering IDIQ solicitation (REQUIREMENTS-24-1827), addressing 15 clarifying inquiries from potential offerors. Key clarifications include: confirmation that projects with completed design can be submitted, subconsultant projects are acceptable, the required number of projects is 3-5, and the standard page format is 8.5"x11". The government specified that blast resistance design is not a structural engineering requirement, no sample contract will be provided, and no further solicitation deadline extensions are anticipated beyond the May 05, 2025 10:00 am EDT submission deadline. Responses consistently direct offerors to follow the original pre-solicitation notice requirements, providing minimal additional guidance beyond direct questions about submission parameters.

View the file

Other files

File Type Posted
Request for SF-330 Updated.pdf PDF
Amendment 02.pdf PDF
Amendment 01.pdf PDF
SAES - NESDIS AE IDIQ Contract final.pdf PDF
Request for SF-330.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 03- Questions and Answers SAM.gov solicitation no.: REQUIREMEMTS-24-1827 Amendment Date: 05/02/2025

The following questions were received in response to the NESDIS SF-330 pre-solicitation notice.

Answers are provided below for informational purposes.

1. I wanted to reach you regarding the proposed NESDIS SSMC1 Building IDIQ project in Silver Spring, MD. Has a Geotechnical investigation already been performed at the site, or will you be accepting proposals for this in the coming weeks/months? Similarly, do you have a timeline for breaking ground and hiring Testing & Inspection services?

Answer: NESDIS is not looking for SSMC1 building Geotechincal services under this contract.

2. Can example projects be expanded to up to ten (10) example projects, to show breadth of relevant experience?

Answer: Please submit your offer as per listed requirement in the presolicitation notice.

3. Can the page count be expanded to one hundred (100) pages, to capture relevant experience and company standards and processes?

Answer: Please submit your offer as per listed requirement in the presolicitation notice.

4. Please verify what is not included in the current 80 page max page count (i.e. cover page, table of contents, letter of commitment from subs, SF330 Part II, divider pages, past performance questionnaires, letters of recommendation, etc…)

Answer: Please submit your offer as per listed requirement in the presolicitation notice. These are the total number of pages per offer.

5. Can the Org Chart be 11x17, and count as one (1) page?

Answer: Please submit your offer as per listed requirement in the presolicitation notice. Standard single page is 8.5"X11".

6. If we are using diagrams and graphics to convey relevant project information, can we use 11x17 page size, and have it count as one (1) page?

Answer: Please submit your offer as per listed requirement in the presolicitation notice. Standard single page is 8.5"X11".

7. Please confirm “work completed” is defined as design completed. Please confirm example projects may include projects where design is completed and construction is ongoing, and will count as a completed example project.

Answer: If the project planning and design is completed and accepted by the client, it is considered work complete for A/E firm.

8. In the Instructions to Offerors under 3. Past Performance (Page 5 of the ‘Request for SF-330 Updated’ document), it states the following: “Offerors shall submit past performance information for the same 3–5 projects submitted under Corporate Experience. Include customer references and building owner/representative contact details who can speak to the quality of services provided.” Please confirm if you are requiring Offerors to supply contact information only (name, phone, email, etc.) for the customer and building/owner references, or is there a Past Performance Review form that must be submitted?

Answer: Either or both information are acceptable.

9. Will projects with design completed be considered?

Answer: Yes.

10 Will significant subconsultant projects be considered? Or do all projects need to be from the prime?

Answer: Include projects and portions completed by prime and subcontractors.

11. Do you need SF-330 Part II from key subconsultants or just from the prime?

Answer: Prime and/or Subcontractors as it suitable for particular project.

12. Is a total of three (3) projects only required or do you require five (5) total?

Answer: Per instruction section of the SF330 a minimum of 3 and maximum of 5 relevant projects.

13. Our firm intends to submit on the above referenced opportunity. We would like to know if there is a sample contract that can be provided for review?

Answer: The Government does not have a sample contract.

14. Is blast resistance design capability for the structural engineer a requirement for this IDIQ?

Answer: Blast resistance design capability is not a structural engineering requirement.

15. We are working towards our submittal, but the response time is rather short and was curious if there was a reason why and if an extension is reasonable?

Answer: The Government has previously extended the requirement via amendment 02, at this time another extension is not anticipated.