Request for Proposal _ CMS RENOVATION AND NEW.pdf

PDF 406 KB Posted

Attached to
Facility Renovations and New Construction at Cartersville Middle School
Solicitation number
PE-55463-NONST-2027-000000027
Issued by
Barrow County, Georgia

About this file

This is a Request for Proposal issued by Cartersville City Schools for Construction Management at Risk services to oversee facility renovations and new construction at Cartersville Middle School in Cartersville, Georgia. The project encompasses standing seam metal roof replacement (145,000 SF, $3.2M budget), interior restroom modernization ($570,000), flooring replacement in classrooms and corridors ($2.1M), minor modifications to existing structures ($50,000), construction of two new classroom additions totaling approximately 24,700 SF ($8.7M), and site upgrades with drainage remediation ($880,000). The total project budget is $15.5 million, with the existing building comprising approximately 172,700 SF. All renovation work will occur during nights, weekends, school holidays, and summer break. A mandatory pre-proposal conference is scheduled for September 15, 2026 at 10:00 AM EST at Cartersville City Schools, 15 Nelson Street, Cartersville, GA 30120. The deadline for submitting questions is September 22, 2026, with proposals due October 1, 2026 at 2:00 PM EST to Altman + Barrett Architects. Eight hard copies and one electronic copy (.pdf on thumb drive) must be submitted to Walter Altman at 117 West Main Street, P.O. Box 665, Hahira, GA 31632. The announcement of successful contractor or shortlist selection will occur October 9, 2026, with interviews conducted as deemed necessary. The final announcement of the successful contractor is scheduled for October 23, 2026. The anticipated preconstruction period extends from November 2026 through March 2027, with construction beginning May 2027 and completion scheduled for July 2028.

Proposals will be evaluated based on firm overview (5%), proposed management team (25%), K-12 construction experience (20%), approach to CM-at-Risk (5%), project schedule (5%), claims history (5%), financial information (10%), contractor fees (15%), and local participation (10%). The contractor fees component will serve as the basis for negotiation with the highest-ranked firm, with negotiations proceeding to the second-ranked firm if terms cannot be mutually agreed upon. The selected contractor must provide 100% performance and payment bonds, maintain specified insurance coverage including $1,000,000 general liability per occurrence and workers' compensation insurance, and comply with Immigration Reform and Control Act requirements and Georgia Security and Immigration Compliance Act provisions. The contractor shall obtain at least three qualified bids for each bid package and submit monthly payment applications using AIA G702 and G703 forms. Contractor fees are to be submitted on a lump-sum basis for preconstruction services, an itemized General Conditions Fixed Fee for each project with duration and unit rates, and a proposed percentage fee for overhead and profit. The contractor must demonstrate financial capability with a quick ratio of 1.0 or higher, an Experience Modification Rate of 1.1 or less over the past three years, current bonding capacity, and appropriate Georgia licensing. The project will be executed under an AIA A133-2019 Construction Manager as Constructor Agreement with a Guaranteed Maximum Price to be finalized upon contract execution.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cartersville City Schools

REQUEST FOR PROPOSAL

CONSTRUCTION PROFESSIONAL

For

Facility Renovations and New Construction at Cartersville Middle School for Cartersville City Schools Cartersville, Georgia

Cartersville City Schools (hereinafter referred to as CCS) is hereby seeking proposals from construction firms to provide services through the Construction Management at Risk delivery method for Facility Renovations and New Construction for Cartersville Middle School. The total budget for this project is $15,500,000. Request for Proposal (hereinafter referred to as RFP) package can be downloaded from:

www.altmanbarrettarchitects.com

Responses must be received by the Architect, Altman + Barrett Architects, before 2:00 PM on October 01, 2026, after which time and date they will no longer be accepted. Late responses will not be considered. To be accepted, all responses must be submitted in a sealed package marked "Proposal for Cartersville City Schools – Facility Renovations and New Construction – Construction Professional". Eight (8) hard copies and (1) electronic copy (.pdf format on a thumb drive) of each proposal must be addressed and delivered to:

Walter Altman Altman + Barrett Architects 117 West Main Street, P.O. Box 665 Hahira, GA 31632

Oral or telegraphic (including FAX and e-mail) responses are not acceptable.

The CCS will select the most qualified and responsive construction firm to enter a Construction Management at Risk contract for the construction of the above-mentioned projects. Award of the contract will be based on an evaluation of all required submittals noted in the RFP and, if needed, interviews.

It is the intent of the Owner to enter into a Construction Management at Risk agreement with one incorporated firm.

Please direct all questions regarding this RFP to;

Walter Altman with Altman + Barrett Architects and Ken Paige with Cartersville City Schools., waltman@altmanbarrettarchitects.com and kpaige@cartersvilleschools.org.

ANY UNSOLICITED CONTACT OR COMMUNICATION REGARDING THIS PROJECT WITH ANY

CARTERSVILLE CITY SCHOOLS SYSTEM OFFICIAL, PERSONNEL OR BOARD MEMBERS BY ANYONE

FROM WITHIN OR ON BEHALF OF A PROPOSING FIRMS IS STRICTLY PROHIBITED AND WILL BE

GROUNDS FOR DISQUALIFICATION. THIS APPLIES FROM THE DATE OF THIS RFP AVAILABLE UNTIL

AFTER A CONTRACT HAS BEEN AWARDED TO THE CONSTRUCTION MANAGER.

http://www.altmanbarrettarchitects.com/ mailto:waltman@altmanbarrettarchitects.com mailto:kpaige@cartersvilleschools.org

GENERAL INFORMATION

Timeline:

Public Advertisement/RFP Available: September 01, 2026

Mandatory Pre-Proposal Conference: September 15, 2026 @ 10:00 am EST Cartersville City Schools 15 Nelson Street Cartersville, GA 30120

Deadline for Questions: September 22, 2026

Proposals Due: October 01, 2026 @ 2:00 pm EST

Announcement of Successful Contractor or Shortlist Selection Announcement: October 9, 2026

Interviews (if deemed necessary): TBD

Announcement of Successful Contractor October 23, 2026

Anticipated Preconstruction Period November 2026 to March 2027

Anticipated Construction Begin/End Date May 2027 (Begin Renovation, New Construction, Roof

Replacement) July 2028 (Completion)

Submission of proposals indicates Respondent’s acceptance of the evaluation technique and Respondent's recognition that some subjective judgments must be made by the CCS during the determination of ranking order and award.

The CCS reserves the right to select or reject any and all responses as a result of this Request for Proposal. The CCS is not liable for any costs incurred by any person or firm responding to this Request for Proposal.

The Submitter shall hold harmless and indemnify the Owner, the Architect, and other design consultants against all claims, suits, actions, costs, council fees, expenses, damages and/or judgements in decrees by reason of persons or property being damaged or injured by the Contractor or any of the Contractor’s employees/subcontractors in any capacity during the progress of the work, whether by negligence or otherwise.

Project Description:

This project will consist of site development, renovation / modifications and new construction for Cartersville Middle School, including the following scope of work:

1. Standing seam metal roof replacement – Roof area approx.. 145,000 SF. Budget is $3.2M.

2. Interior restroom modernization throughout building to include selective demolition and replacement of interior finishes along with various mechanical, plumbing, and electrical work.

Budget is $570,000.

3. Flooring replacement in classrooms and corridors. Budget is $2.1M.

4. Minor modifications in some areas of existing school to include new wall construction. Budget is $50,000.

5. Construction two new classroom additions. Budget is $8.7M.

6. Site upgrades and drainage remediations. Budget is $880,000.

Total new construction SF is approx. 24,700 SF. The existing CMS building is approx. 172,700 SF. Total budget is $15.5M. It is important to note that all renovation work will occur during nights, weekends, school holidays, and summer break. The project start time is variable during the overall schedule within the RFP.

GENERAL REQUIREMENTS

Contractor Responsibility

The selected Contractor will be required to assume total responsibility for all services offered in his/her proposal. The selected Contractor will be considered the prime contractor and the sole point of contact with regard to all contractual matters. The Contractor shall also be required to obtain at least three bids for each bid package (work category), exclusive of the Contractor’s guaranteed maximum price for the individual bid packages (work categories). If any bid packages receive less than three qualified bids, the Owner reserves the right to require rebidding these packages. The Contractor will not perform any portion of the project with its own forces except in an event or situation deemed necessary by both the Owner and Architect. Individual trade contracts will be between the Contractor and the Trade Contractors, and subject to the CCS approval.

Required Bonds and Insurance

The selected Contractor will be required to provide a 100% Payment Bond and 100% Performance Bond for the entire amount of the cost of construction. The Proposal shall include a letter from a bonding company indicating its willingness to issue said payment and performance bond for this project. Bonds for this project shall be issued by a bonding company listed in the current edition of the Federal Register as a surety, must be kept in force for the duration of the contract, executed by a resident agent of the State of Georgia and be in compliance with Georgia Revised Statutes.

To adequately protect the interests of the CCS, the successful respondent shall procure and maintain insurance during the life of the agreement. See Attachment "A" "Insurance Coverage" for required coverage.

Evidence of required bonds and insurance shall be presented prior to the execution of the Mandatory Amendment. Insurance policies to be carried under the agreement shall not be changed, canceled, or allowed to expire without thirty (30) days prior written notification to the CCS.

Immigration Reform Compliance Requirement

The successful Proposer will be required to certify compliance with the Immigration Reform and Control Act of 1986 (IRCA), D.L. 99-603 and the Georgia Security and Immigration Compliance Act OCGA 13-10-90 et.seq., by meeting or having complied with one of the (2) following provisions and by executing any affidavits required by the rules and regulations issued by the Georgia Department of Labor set forth at Rule 300-10-1-.01:

1) The Contractor warrants that Contractor has complied with the Immigration Reform and Control Act of 1986 and the Georgia Security and Immigration Compliance Act by registering at https://www.vis-dhs.com/EmployerRegistration and verifying information of all new employees;

2) The successful proposer shall comply with the stipulations cited in Security and Immigration Compliance Act OCGA 13-10-91. with respect to the proper federal authorizations regarding the right to work for subcontractors and contractors.

Background Check Affidavit

Successful Offeror will be required to execute a background check affidavit attesting to compliance with said affidavit (form to be provided by Owner). Such affidavit will require that ALL personnel of the CM who enter or occupy the Project site have passed a background check performed in accordance with GBO GAPS processing service.

Similarly, the CM shall require that every subcontractor, sub-subcontractor, laborer, and any other workers who perform any work on the Project site will be required to provide the same affidavit for all their respective personnel.

Taxes, Fees, Code Compliance and Licensing

The Contractor shall be responsible for compliance of all materials and construction with the requirements of all statutes, codes, and sanitary laws in effect in the City and/or County in which the Work is performed. The Contractor shall obtain and pay all necessary permits, inspections, tests and insurance required by law. In addition, if applicable to this project, Contractor shall pay for all utility connection fees, tap fees, impact fees, taxes, and any other fees associated with any work related to this project including utility connection/service to this project, as well as Land Disturbance/Notice of Intent/Notice of Termination fees. All installation and construction work shall be done by subcontractors licensed in the State of Georgia. The Contractor shall be responsible for compliance with all applicable codes and statutes.

Payment

Contractor shall submit monthly payment applications using AlA G702 and AlA G703 Continuation Sheets.

LIST OF REPRESENTATIVE SERVICES TO BE PROVIDED BY THE CONTRACTOR

Project Planning

1. Evaluate documents for constructability, value opportunities, and scheduling at each phase of design.

2. Participate and assist in planning meetings.

3. Conduct a Value Engineering review, including Life Cycle Cost, evaluations for alternate materials and systems prior to the beginning of the Construction Documents phase.

4. Prepare and submit cash flow analysis to Owner.

Cost Estimating and GMP Pricing

5. Due to the project schedule, a preliminary and schematic document estimate is not required.

6. Provide cost estimate for design development submittal. Provide separate estimates for each of the projects listed.

7. Provide guaranteed maximum price for construction.

Bidding and Awarding

8. Separate construction work into appropriate bid packages for each project (See Attachment "B").

Provide incentives for subcontractors in the event they are awarded bid packages for multiple projects.

9. Develop requirements to assure time, cost, and quality control during construction.

10. Submit bid packages to the Owner for review before issuing to bidders. Be advised that the

Owner reserves the right to modify bid requirements for subcontractors, including insurance, bonding, lien waivers, etc.

11. Provide an estimated construction schedule for issuance with the bid package for each project.

12. Identify bidders and generate bidder interest. Maintain a list of firms contacted and dates of contact for review by the Owner.

13. Schedule and conduct pre-bid conferences in conjunction with the architect and representatives from the CCS.

14. Advertise and distribute bid documents.

15. Assist in development of necessary addenda and distributing of these addenda to known bidders.

16. Obtain at least three bids on each bid package.

17. Monitor bidder activity.

18. Review and analyze bids and recommend awards.

19. Collect executed contracts, purchase orders, affidavits of assurance, insurance certificates, and performance and payment bonds and distribute copies to Owner, Architect and contractors.

20. Update schedule.

21. Conduct Pre-Construction meetings.

Construction Phase

22. Management staff for construction manager to include a Project Manager, on-site Superintendent for each project when simultaneous work is being performed. Superintendent shall have supervised past projects of similar size and scope and have excellent performance references from the Owners for a minimum of three (3) projects within a period of eight (8) years maximum.

Contractor shall submit his proposed project manager and superintendent and references for review by the Owner and Architect with this proposal. The Contractor is responsible for adequately staffing and maintaining the staff on this project at all times and if an Assistant Superintendent is deemed necessary, the proposer shall include such.

23. Mobilization of job site: Provide and maintain a fully equipped project office facility on a single site to perform all required Contractor duties and meetings and coordination of on-site activities for each project. Project sites without a job trailer may use a designated space within each building.

24. Assure timely procurement of all required permits.

25. Establish and maintain coordination procedures.

26. Develop and maintain a detailed schedule including delivery, approvals, inspection, testing, construction, and occupancy.

27. Conduct and record a minimum of monthly job progress meetings following a Contractor generated agenda with the Architect, Owner and all active trades, and follow-up with distribution of minutes to all parties.

28. Coordinate and log all request for information (RFI's).

29. Maintain a daily log of jobsite activities.

30. Prepare and submit change order documentation for review and approval by the architect and the

CCS. Review change order proposals to verify validity, purpose, and cost.

31. Maintain a system for review and approval of shop drawings.

32. Maintain written and photographic records and submit routine reports to the architect and CCS.

33. Maintain quality control and ensure conformity to contract documents.

34. Establish and maintain a jobsite safety program.

35. Provide cost control through progress payment review and verification according to the approved schedule and contract amounts.

36. Provide coordination of post completion activities, including the assembly of guarantees, manuals, and the owner’s final acceptance.

37. Coordinate and assure timely completion of final punch list.

38. Compile as-built drawings through-out construction.

39. Assemble close-out documents and forward to Architect for approval.

40. Coordinate any training specified for Owner's personnel.

41. Provide all services listed under "General Conditions" in Attachment "C" and further detailed in

Attachment “E”.

Post Occupancy

42. Implement and coordinate the one (1) year warranty and one (1) year warranty inspection.

43. Respond to request for corrections for work items found not to be installed correctly.

44. Respond to warranty related request.

45. Assist in post-construction review of the facility.

SELECTION PROCESS

The selection of the Contractor firm will be by an Evaluation Committee consisting of representatives of Cartersville City Schools. The Evaluation Committee will receive and review the proposals and conduct interviews as scheduled, if deemed necessary.

Phase I - Proposal Evaluation The Proposals will be evaluated against specified criteria and required submittals to determine the most responsible and responsive firm for this project. The specified criteria is listed as follows:

1. Firm Overview (5%)

2. Proposed Management Team (25%)

3. K-12 Construction Experience (20%)

4. Approach to CM-at-Risk (5%)

5. Project Schedule (5%)

6. Claims History (5%)

7. Financial Information (10%)

8. Contractor Fees (15%)

9. Local Participation (10%)

*Note: Item 8 will be used as a basis for negotiation with the highest ranked firm. In the event that these items cannot be negotiated to mutually acceptable amounts, the Owner will proceed to negotiations with the 2nd highest ranked firm.

Upon completion of the Phase I - Proposal Evaluation, CCS may conduct an additional evaluation of shortlisted Contractor firms via an interview if deemed necessary.

Phase II - Interviews Contractor firms chosen for interviews will be notified of the place and time that the interview will be conducted. The interview criteria will also be given to the shortlisted firms at that time.

Negotiation and Signing of Contract Upon completion of Phase I, and Phase II (if required), an AIA A133-2019 Cartersville City Schools/Construction Manager as Constructor Agreement – Cost of Work Plus Fee with GMP contract without Mandatory Amendment #1 will be executed between the selected Contractor and CCS. A Guaranteed Maximum Price (herein after referred to as GMP) will be prepared by the Contractor. The GMP shall be submitted to CCS and shall include a detailed project schedule, schedule of values that includes contractor contingency, a schedule of trade packages with subcontractors, clarifications and assumptions, and a monthly cash flow chart. Upon agreement by all parties on the GMP, the Mandatory Amendment #1 will be completed, signed and attached to the contract and shall constitute the full contract for the project. Once this is completed, a Notice to Proceed will be issued.

Upon the Owner receiving a fully executed contract, the Contractor may request payment for 100% of Pre-Construction Services.

RESPONSE FORMAT AND CONTENTS

General Information

Responses must be submitted in the format outlined in this section. Each response will be reviewed to determine if it is complete prior to actual evaluation. Failure to provide accurate, up-to-date responses to any and all portions of the RFP may result in disqualification without prejudice. The CCS reserves the right to eliminate from further consideration any responses that are deemed to be substantially or materially unresponsive to the requests for information contained in this section. The intent of the CCS is that all responses follow the same format in order to evaluate each response fairly. CCS may, during the course of the evaluation process, request additional information to supplement and/or clarify the information provided.

Proposals will be evaluated in light of the material and substantiating evidence presented in the proposal, and not on the basis of what is inferred.

Any exceptions taken to the terms and conditions of this RFP must be clearly identified. If no exceptions are listed, it will be concluded that the proposer will meet, in every detail, the conditions stipulated in this RFP. The RFP and the response will be incorporated into the contract.

Proposals may be modified or withdrawn by written notice received prior to deadline for receipt of proposals. A proposal also may be withdrawn in person by a proposer or his authorized representative, provided his identity is made known and he signs a receipt for the proposal, but only if the withdrawal is made prior to the deadline set for receipt of proposals.

Each respondent shall provide CCS with eight (8) copies of his/her response. Begin each section and subsection as described herein on a separate page. Number the pages in each section consecutively.

Each page shall have the name of the respondent indicated clearly across the bottom of each page.

Submission of a response authorizes the Owner to make inquiries concerning the respondent and its officers to any persons or firms deemed appropriate by CCS. Proposer consents to and authorizes the full investigation of the information given herein or in such other forms completed in connection with this proposal and consents to representatives of CCS contacting the named references, named financial institutions, and such other persons as may be needed to confirm such information, and waives any right proposer may have for such information or the intentional withholding of material facts (as determined by the Authority in its sole discretion), shall be a reason for rejection of the Proposal.

Questions that arise prior to the proposal submittal date shall be submitted by email to:

Walter Altman, Architect, waltman@altmanbarrettarchitects.com Ken Paige, Director of Maintenance & Facilities, kpaige@cartersvilleschools.org.

Phone calls will not receive a response.

Proposal Format mailto:waltman@altmanbarrettarchitects.com mailto:kpaige@cartersvilleschools.org

Cover Letter Each proposal shall include a one-page cover letter at the beginning of the proposal. The cover letter shall provide an overview, and summarize the key strengths of the submitting firm.

1. Firm Overview (5%): Briefly describe your firm, its officers, and executive management.

Explain your company philosophy as a Construction Manager, including any unique aspects of your firm that separate you from your competitors. Factors such as years-in-business and work experience will be considered.

2. Proposed Management Team (25%): Furnish an organizational chart for your firm specifically indicating those who will be involved in this project, the amount of time they will be assigned to the project and their specific assignments, resumes, and construction experience. Please include detailed resumes of the management team proposed (Project Manager, Superintendent, and Assistant Superintendent).

3. K-12 Construction Experience (20%): Specifically identify the top ten (10) most related projects your firm has completed, and include the following information:

Project name, location & description Original GMP or original bid compared to final cost Original schedule compared to actual completion time Reference for the project with name, address and phone number

4. Approach to CM-at-Risk (5%): Describe your general approach to the cost, schedule, quality control, and safety methods for this project as they relate to Construction Management-at- Risk. Describe your firm's project management systems and how your firm intends to provide preconstruction and construction management services. Submit your firm’s safety rating on the last 5 projects over $8 million and your firm’s overall safety rating.

5. Project Schedule (5%): Provide your firm' complete project schedule. Include all phases of the project, including submittals, equipment lead time, project phasing, project closeout, etc.

6. Claims History (5%): List all litigations, arbitrations, and mediations in which the firm has been involved in the past ten (10) years and indicate the disposition of each such claim, the name of the owner, and the nature of the claim.

7. Financial Information (10%): Provide one copy, in a separate sealed envelope marked “FINANCIAL INFORMATION”, of a reviewed and/or audited financial statement, balance sheet and income statement for the firm prepared by a certified public accountant. The financial statement must be within 6 months of year end, but in no case more than 18 months old.

Provide a compliance letter from your bonding company showing consent to provide 100% Performance and Payment Bonds for your services as a Contractor. Each respondent shall provide a certificate of insurance detailing their firm's present coverage and limits. Insurance agent shall certify that they are licensed to perform business in the State of Georgia. The certificate of insurance should be addressed to CCS and be dated within 30 days of the RFP due date.

8. Fees (15%)

a. Pre-Construction Services Fee:

i. Provide a lump sum fee for preconstruction services listed in Attachment “C” and further detailed in Attachment “E”.

b. General Conditions Fixed Fee (Each Project):

i. Provide an itemized listing of General Condition with the associated cost for each item with duration and unit rate following the format indicated on Attachment "E". Basis for calculation should be a 14-month construction schedule with an overall construction phase budget of $15.5 million that includes Construction Contingency, General Conditions Fixed Fee, and Overhead and Profit. Grouping of costs is not allowed.

c. Proposed Percentage Fee for Overhead and Profit:

i. Contractor shall stipulate a percentage fee for Overhead and Profit on Attachment "D".

9. Local Participation (10%):

a. It is requested by Cartersville City Schools to encourage local participation of subcontractors and suppliers in this construction project. The Contractor shall demonstrate their process to provide the opportunity for local contractors and suppliers contractors and suppliers to compete for contracts to provide goods, services, and/or construction.”

*Note: Item 8 will be used as a basis for negotiation with the highest ranked firm. In the event that these items cannot be negotiated to mutually acceptable amounts, the Owner will proceed to negotiations with the 2nd highest ranked firm.

Firms must also provide supporting documentation as follows;

1) Proposer must provide a sworn statement attesting to compliance with the following minimum criteria.

2) The firm or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.

3) Firm must have sufficient bonding capacity for anticipated total cost of Work. Provide a letter from Surety Company, signed by an officer of the Surety Company listing State of Georgia license, A.M. Best A-/VII rating (or better), and US Treasury Circular 570 listing including underwriting limitation, and confirming surety company's willingness and ability to issue the required performance and payment bonds for this project to this Contractor.

4) Firm must have current Commercial General Liability Insurance policy, and must be able to provide all insurance coverages, limits, and endorsements as required by Attachment A - Insurance Requirements.

5) Firm must currently have and maintain Worker's Compensation insurance as required by the State of Georgia Workers Compensation statutes.

6) Firms must have all necessary, valid and current licenses to do business in the State of Georgia. Provide a copy of GC license, business license and Georgia Certificate of Existence.

7) Firm must demonstrate sufficient cash flow to undertake the project as evidenced by a quick ratio (current assets/current liabilities) of 1.0 or higher.

8) The firm must demonstrate a commitment to safety with regard to Worker's Compensation by having an Experience Modification Rate (EMR) over the past three years of 1.1 or less.

Provide documentation verifying this requirement.

9) The firm or its principals must not have not been terminated for cause or currently in default on any contract.

10) Proposer affirms that no person, by himself or herself, or anyone associated with Proposer in any way whatsoever, has prevented or endeavored to prevent competition in bidding or proposals by any means whatsoever. No person who desires to procure such work for himself or herself or for another shall prevent or endeavor to prevent anyone from making a bid or proposal therefore by any means whatsoever, nor shall such person so desiring the work cause or induce another to withdraw a bid or proposal for the work. Proposer further affirms and covenants that it will make an oath confirming the foregoing (as required by O.C.G.A. § 36-91-21(e)) prior to commencing any work, should it be awarded the contract which is the subject of this proposal.

Attachment A

INSURANCE REQUIREMENTS

Upon Notice of Award, Vendor may submit this form to their insurance agent as this form contains requirements that may be non-standard in the insurance industry.

Contractor shall furnish the Cartersville City Board of Education certificates of insurance as follows from company or companies acceptable to the Cartersville City Board of Education.

A. Required Certificates

1. Commercial General Liability Insurance Policy Vendor shall procure and maintain a Commercial General Liability Insurance Policy, including products and completed operations liability, and contractual liability coverage covering bodily injury, property damage liability and personal injury. The policy or policies must be on any "occurrence" basis. The policy shall include contractual liability coverage. The policy purchased by the Vendor must be issued by a company authorized to conduct business in the State of Georgia or by a company acceptable to the Cartersville City Schools Board of Education. The policy must include separate aggregate limits per project. Excess liability coverage may be used in combination with the base policy to obtain the limits listed below.

Limits $1,000,000 per Occurrence $300,000 Damage to Rented Premised each Occurrence $10,000 Medical Expense per person $1,000,000 Personal & Adv Injury $2,000,000 General Aggregate $2,000,000 Products – Comp / OP Aggregate

2. Business Automobile Liability Insurance Policy

The Contractor shall procure and maintain a Business Automobile Policy with liability limits of not less than $1,000,000 per person and $1,000,000 per occurrence or a policy with a combined single limit of not less than $1,000,000 covering any owned, non-owned, or hired autos. Excess liability coverage may be used in combination with the base policy to obtain these limits.

3. Workers' Compensation Insurance

Workers' Compensation Insurance in accordance with applicable state laws with the following limits:

Limits $1,000,000 each accident - Bodily Injury by Accident $1,000,000 each employee - Bodily Injury by Disease $1,000,000 policy limit - Bodily Injury by Disease

IF YOUR COMPANY IS EXEMPT FROM WORKERS' COMPENSATION INSURANCE IN ACCORDANCE WITH

GEORGIA LAW, PLEASE HAVE YOUR INSURANCE COMPANY SUBMIT A LETTER VERIFYING YOUR

EXEMPTION.

B. Certificates to contain policy number, policy limits and policy expiration date of all policies issued in accordance with this contract.

C. Certificates shall contain the location and operations to which the insurance applies.

D. Certificates shall contain Vendor's insurance coverage. If coverage is included in General Liability, please indicate this on the Certificate of Insurance.

E. Certificates are to be issued to:

Cartersville City Board of Education 15 Nelson Street Cartersville, GA 30120

F. The Contractor shall mail insurance document listed in this form to:

Cartersville City Board of Education 15 Nelson Street Cartersville, GA 30120

Attachment B

ESTIMATED MINIMUM BID PACKAGE LIST

Site Work Site Utilities Site Paving Site Concrete Termite Control Chain Link Fence Concrete Masonry Structural & Miscellaneous Steel Metal Stair & Railing Carpentry Building Insulation Doors, Frames & Hardware Windows, Storefront, Glass & Glazing Overhead Coiling Doors Framing, Drywall & Acoustical Epoxy Flooring or Ceramic Tile Resilient Flooring & Carpet Painting & Joint Sealant Specialties Signage Manufactured Canopy Covers Toilet and Bath Accessories Toilet Partitions Roofing and Roof Replacement Plumbing Fire Protection

HVAC

Electrical System (Including low voltage systems)

Attachment C

PRE-CONSTRUCTION FEE AND CONSTRUCTION PHASE GENERAL CONDITIONS FEE

1. Pre-Construction Phase Services

a. Estimating

b. Subcontractor solicitation

c. Scheduling

d. Value engineering & constructability reviews

e. Reproduction & distribution of bid documents

f. Postage

g. Advertising

h. Office supplies

i. Cost of personnel & associated costs (labor burden, cell phone, vehicle)

j. Payroll taxes

k. Bid packages

l. Office costs

m. Participation in design meetings

n. GMP preparation & delivery

2. Construction Phase Services (General Conditions)

a. Project Management (minimum 1 full-time project manager)

b. Field Supervision (min. 1 full-time on-site superintendent per site)

c. Assistant Superintendent

d. Project Clerical

e. Additional Project Personnel

f. Development of Reports (provide daily and monthly written reports including a daily log and pictorial records of the project progress.)

g. Safety and security measures to include all OSHA requirements.

h. Performance Bond & Payment Bond

i. Payroll Taxes

j. Labor Burden

k. Builder’s Risk Insurance (Provided by Owner)

l. Insurance for Construction Manager, personnel, equipment and building

m. Temporary office trailer(s) with fully functional lavatory & separate meeting room to accommodate 10 people. The office trailer shall be located at a single project site where all meetings will occur for each project.

n. Office equipment and furnishings, office supplies, telephone, fax, utilities, wireless internet access, drinking water & cups, meeting table and chairs, cleaning supplies, paper towels, toilet paper and any other items necessary to administer the project on-site.

o. Vehicles for Contractor’s staff.

p. Installation, maintenance and removal of Temporary Fencing.

q. Project construction signage.

r. Temporary sanitation facilities.

s. Jobsite security

t. Portable construction heat

u. Dumpsters, labor, tools, supplies, and disposal fees for daily and final project cleanup.

v. Building layout including engineers, instruments, and supplies.

w. All insurance listed in the "General Information" section.

x. All required permits, fees, and applicable state and local taxes.

y. Provide EPD storm water monitoring associated with construction activity.

z. Travel and living expenses for Contractor’s Staff.

aa. Temporary utilities required during the construction phase. Owner will pay use charges and CM is responsible for connections and maintenance of those connections.

bb. Temporary lighting.

cc. Temporary weather protection.

dd. Printing cost for submittals and close-out documents.

ee. Monthly progress photos.

ff. Equipment for site logistics and clean-up.

gg. Itemize any additional General Condition cost not specified above.

Pre-Construction Phase Services Fee: $________________________

Construction Phase Services Fee (General Conditions): $_________________________

Attachment D

CONSTRUCTION MANAGEMENT SERVICES FEE

Overhead & Profit: _________________%

Attachment E (This form must be filled out in its entirety and every item have a value placed with it, even if

$0. A total amount will not suffice)

I. PRECONSTRUCTION COSTS AND EXPENSES BREAKDOWN

Description

Qty

Unit

Labor*

Mat'l**

Sub

Labor

Subtotal

Mat'l

Subtotal

Subtotal

Total

Notes

A. Preconstruction - Supervision & Management:

1 Senior Project Mgr. mos

2 Project Mgr. mos

3 Preconstruction Manager mos

4 Project Supt. mos

5 Cost Control mos

6 Scheduling mos

7 Secretary mos

8 Consultant mos

9 Other

10 Other

11 Office Supplies mos

12 Postage & Shipping mos

13 Blueprint/Photostat. ls

14 Phone Charges mos

15 Advertising mos

16 Courier Service mos

17 Travel Expenses mos

18 Other

19 Other

TOTAL ALL PRECONSTRUCTION COST AND EXPENSES

All items listed within “Other” must be identified within the “Notes” column. No items can be added at the time of GMP agreement. If there is not an item listed that will be included and needs to be accounted for, please list as other and provide clarification in the “Notes” column.

ATTACHMENT "E"

II. CONSTRUCTION PHASE GENERAL CONDITIONS FEE

Description

Qty

Unit

Labor*

Mat'l**

Labor

Subtotal

Mat'l

Subtotal

Total

Notes

Site Supervision & Management:

1 Senior Project Manager mos

2 Project Manager mos

3 Project Superintendent – Cartersville City Middle School Renovations + New Construction mos

4 General Superintendent mos

5 Secretary mos

6 Project Engineer mos

7 Office Engineer mos

8 Cost Control mos

9 Safety Engineer mos

10 Scheduling mos

11 Purchasing mos

12 Project Accountant mos

13 Other

14 Other

15 Other

Miscellaneous:

17 Development of Reports mos

18 Safety & Security Measures ls

19 Performance & Payment Bond ls

20 Builder Risk Insurance

21 Temporary Office – 1 required Mos

22 Office Equipment and Furnishing ls

23 Vehicles for Contractor’s Staff ls

24 Project Construction Signage Ls

25 Temporary Sanitary Facilities mos

26 Jobsite Security mos

27 Portable Construction Heat mos

28 Dumpsters and Disposal Fees ls

29 Building Layout ls

30 Insurance in General Information Section ls

31 Permits, Fees ls

32 EPD Storm Water Monitoring mos

33 Travel and Living Expenses ls

34 Printing Costs for Closeout Documents ls

35 Monthly Progress Photos mos

36 Equipment for Site Logistics mos

TOTAL ALL CONSTRUCTION OVERHEAD COSTS:

All items listed within “Other” must be identified within the “Notes” column. No items can be added at the time of GMP agreement. If there is not an item listed that will be included and needs to be accounted for, please list as other and provide clarification in the “Notes” column.

Alternates and Change Orders

1. Any Contractor fee for alternates accepted by the owner shall be paid using the percentage stipulated herein.

2. Change Orders will only be considered on Owner requested changes and unforeseeable conditions. For all executed change orders (changes in the work), the contract sum, and Contractor Fee shall be as specified in AIA A201 -2017 General Conditions, Article 7.

Delete from paragraph 7.3.4 the words "the Agreement, or if no such amount is set forth in the agreement, a reasonable amount" and insert the paragraph below:

A. In AIA A201-2017 General Conditions, paragraphs 7.3.3 and 7.3.4 the allowance for overhead and profit combined, included in the total cost to the owner shall be based on the following:

1) For the Construction Manager, for any work performed by his forces for changes in the work, ten percent (10%) of the costs.

2) For the Construction Manager, for any work performed by his subcontractors for changes in the work, five percent (5%) of the cost due to the subcontractor, or no more than as stated in the Contractor @ Risk proposal form, whichever is least.

3) For each subcontractor involved, for any work performed by his own forces for changes in the work, ten percent (10%) of the subcontractor's cost.

4) Overhead and profit is to be applied to only those costs identified in AIA A201- 2017 General Conditions, paragraph 7.3.4.

5) In order to facilitate checking and verification of change order proposals for both increases and decreases in the contract amount, all change order proposals shall be accompanied by a complete cost breakdown of the items in AlA A201-2017 General Conditions, paragraph 7.3.4 for both the Construction Manager and the subcontractors.

6) The only allowable mark-up for the cost of changes in the work shall be for overhead & profit as stated in subparagraphs above.

File details come from the government source that posted it. Updated .