Request for Information2.pdf
PDF 147 KB Posted
- Solicitation number
- DeCA04072026
- Issued by
-
Defense Commissary Agency
About this file
RFI Summary: CY 2026 Holiday Refrigerated Trailer Rentals
This is a Request for Information (RFI) issued by the Defense Commissary Agency (DeCA) for market research purposes regarding refrigerated trailer rentals to support 33 commissary locations across the Continental United States and Alaska during the 2026 holiday season. The requirement involves 33 trailers total—21 electric units and 12 diesel units—all 53-feet with roll-up doors. Delivery dates range from late September through early November 2026, with pickup dates spanning mid-December 2026 through mid-January 2027. Electric trailers require various specifications ranging from 208V to 480V with amperage between 40-100 AMP at 3-phase power; diesel trailers require full fuel tanks at delivery. All trailers must be FDA Food Safety Modernization Act (FSMA) and NSF-certified, sanitized to hygiene standards, and started upon delivery to verify operational status.
Contractor responsibilities include coordinating delivery and pickup at least 10 working days and 3 working days in advance respectively, obtaining all necessary installation passes and personnel security clearances, providing a 24-hour emergency point of contact with 2-hour emergency response time and 24-hour repair or substitute trailer provision, and liability for product loss due to equipment malfunction or negligence. The contractor must submit invoices through the Wide Area Work Flow (WAWF) system. Responses must include company information, business size and socio-economic status under NAICS code 532490, a capability narrative addressing simultaneous management of 33 trailers across geographic areas and emergency response capabilities, past performance on three relevant projects within the last 3-5 years, and optional feedback on requirement feasibility. Responses are due by 2:00 PM EDT on April 10, 2026, submitted via email to david.mootz@deca.mil. This RFI does not commit the government to contract and does not reimburse response costs.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01 - Statement of Work - Holiday Trailers.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information (RFI) for CY 2026 Holiday Refrigerated Trailer Rentals
Disclaimer: This is a Request for Information (RFI) ONLY. It is issued solely for informational and planning purposes and does not constitute a Request for Quote (RFQ) or a promise to issue an RFQ in the future. This RFI does not commit the U.S. Government to contract for any supply or service. Responders are advised that the Government will not pay for any information or administrative costs incurred in response to this RFI. All costs associated with responding are at the interested party’s sole expense. Not responding to this RFI does not preclude participation in any future solicitation, if one is issued.
1.0 Introduction and Purpose
The Defense Commissary Agency (DeCA) is conducting market research to identify potential sources capable of providing refrigerated trailer rentals to support 33 commissary locations in the Continental United States (CONUS) and Alaska during the 2026 holiday season. The objective of this RFI is to gain a comprehensive understanding of the marketplace, identify capable sources (including small businesses), and refine the agency's acquisition strategy.
2.0 Background
DeCA requires temporary, temperature-controlled storage capacity at various commissary locations to handle the increased inventory of frozen turkeys and other perishable holiday food items. The performance period is seasonal, with rentals typically starting in late September/early October 2026 and ending in mid-January 2027. This is a recurring requirement, and the proposed acquisition will be for a single contract to cover all 33 locations for the 2026 holiday season.
3.0 Summary of Requirements
The contractor shall provide all personnel, labor, supervision, equipment, and transportation necessary to deliver, set up, support, and retrieve 53-foot refrigerated trailers with roll-up doors at 33 specified locations.
Key Contractor Responsibilities:
• Coordination: Coordinate delivery and pick-up with the designated Commissary Officer at each location at least 10 working days prior to delivery and 3 working days prior to pickup.
• Site Access: Be responsible for obtaining all necessary installation passes, vehicle inspections, and personnel security clearances.
• Trailer Condition & Setup:
• All trailers must be cleaned, sanitized to meet hygiene standards, and cleared of debris before delivery.
• Trailers must comply with regulations such as the FDA's Food Safety
Modernization Act (FSMA) and be NSF-certified.
• Diesel trailers must be delivered with a full tank of fuel, with levels verified at delivery and pickup.
• Electric trailers must be delivered with all required electrical components and connected to the site's power supply to ensure operational start-up.
• All trailers must be started upon delivery to verify good working order, with the temperature set as required by the Commissary Officer.
• Emergency Service:
• Provide a 24-hour point of contact for emergency service.
• Provide an emergency response time of 2 hours after notification to begin restoration of service.
• On-site repair or a substitute trailer must be provided within 24 hours of the initial emergency call.
• Liability: The contractor will be held responsible for any costs incurred by the loss of product stored within a trailer that malfunctions due to faulty equipment or contractor negligence.
• Invoicing: All invoices must be submitted through the Wide Area Work Flow (WAWF) system.
Detailed Location and Trailer Specifications:
The requirement is for a total of 33 trailers across 33 locations, consisting of 21 Electric and 12 Diesel units. All trailers are 53-feet with roll-up doors.
Location Trailer Type
Specifications Delivery Date
Pickup Date
Additional Requirements
ABERDEEN PG -
HQCNEJ
Diesel N/A 10/01/2026 1/5/2027
ANDREWS AFB -
HQCNEK
Diesel N/A 10/2/2026 1/8/2027
BUCKLEY SFB -
HQCMCB
Electric 230V, 40 AMP, 3 Phase
10/6/2026 12/13/2026
CAMP PENDLETON
MCB - HQCKLM
Electric 210V, 60 AMP, 3 Phase
10/01/2026 1/8/2027 Requesting a Pigtail for plugging in.
CHARLESTON NWS
- HQCSKK
Electric See Notes 10/5/2026 1/12/2027
CHERRY POINT
MCAS - HQCCAZ
Electric 250V, 60 AMP, 10/6/2026 1/4/2027
CHINA LAKE -
HQCKM6
Electric 480V, 100 AMP, 10/01/2026 12/15/2026
FORT BELVOIR -
HQCNFF
Electric 220V, 60 AMP, 10/5/2026 1/8/2027
FORT BENNING -
HQCSJW
Electric 240V, 60 AMP, 3 Phase
10/1/2026 1/15/2027 Electrical cable for the trailer
FORT BLISS -
HQCMCW
Diesel N/A 11/1/2026 12/15/2026
FORT BRAGG
NORTH - HQCCAY
Electric 230V, 60 AMP, 10/01/2026 1/7/2027
FORT BRAGG
SOUTH - HQCCBT
Electric 230V, 60 AMP, 10/01/2026 1/9/2027
FORT CARSON -
HQCMCA
Electric 220V, 60 AMP, 10/20/2026 1/9/2027
FORT GORDON -
HQCSJZ
Electric 208V, 50 AMP, 10/01/2026 1/15/2027
FORT HOOD I -
HQCMC2
Electric 208V, 70 AMP, 10/01/2026 12/14/2026
FORT JACKSON -
HQCSKM
Diesel N/A 10/5/2026 1/12/2027
FORT LEE -
HQCCBC
Diesel N/A 10/5/2026 1/8/2027
FORT MEADE -
HQCNEN
Electric 230V, 60 AMP, FORT MYER -
HQCNFH
Electric 220V, 60 AMP, 3 Phase
06 October
1/8/2027
FORT STEWART -
HQCSJ2
Electric 240V, 60 AMP, GULFPORT -
HQCSKF
Electric 250V, 60 AMP, 10/5/2026 12/18/2026
HANSCOM AFB -
HQCNAA
Diesel N/A 11/1/2026 1/4/2027
HUNTER AAF -
HQCSJ3
Diesel N/A 10/01/2026 1/15/2027
LEMOORE NAS -
HQCKLV
Electric 480V, 50 AMP, 9/28/2026 1/9/2027
LEWIS MAIN -
HQCWGQ
Diesel N/A 10/01/2026 1/7/2027
MCCLELLAN PARK
- HQCKL1
Diesel N/A 10/5/2026 12/28/26
MINOT AFB -
HQCMCL
Diesel N/A 10/13/2026 1/12/2027
MIRAMAR MCAS -
HQCKMQ
Electric 208V, 60 AMP, 9/30/2026 1/2/2027
MOUNTAIN HOME
AFB - HQCWGH
Diesel N/A 11/1/2026 1/6/2027
NEW RIVER MCAS -
HQCCA3
Electric 230V, 60 AMP, 10/2/2026 1/11/2027
NORFOLK NAVSTA
- HQCCBH
Electric 220V, 60 AMP, 10/6/2026 1/9/2027
ROBINS AFB -
HQCSJ8
Diesel N/A 10/31/2026 1/15/2027
SAN DIEGO NB -
HQCKL8
Electric 240V, 40 AMP, 9/28/2026 1/8/2027
4.0 Information Requested from Industry
Interested parties are requested to submit a capability statement that addresses the following areas. Please limit your response to a maximum of 10 pages.
1. Company Information:
• Company Name
• Company Address
• Unique Entity ID (UEI) and CAGE Code
• Point of Contact (Name, Title, Email, Phone Number)
2. Business Size & Status:
• Identify your business size under NAICS code 532490 (Other Commercial and
Industrial Machinery and Equipment Rental and Leasing).
• Provide any applicable socio-economic status (e.g., Small Business, 8(a), HUBZone, Service-Disabled Veteran-Owned Small Business (SDVOSB), Woman-Owned Small Business (WOSB), etc.).
3. Capability Narrative: Provide a detailed narrative describing your company's ability to meet the requirements outlined in Section 3.0. Specifically address:
• Your approach to managing the simultaneous rental and support of 33 trailers across a wide geographical area.
• Your methodology for guaranteeing the 2-hour emergency response time and 24-hour repair/replacement window for all locations.
• Confirmation that your trailers and business practices meet the specified standards (53' with roll-up doors, FSMA/NSF certified, sanitation procedures, etc.).
• Your experience with government contracting, including WAWF invoicing and obtaining site/personnel access for military installations.
4. Past Performance:
• Provide a brief description of up to three (3) recent and relevant projects/contracts
(within the last 3-5 years) of similar scope and complexity. Include the customer name, contract value, and a brief summary of the work performed.
5. Feedback on Requirements (Optional):
• Provide any feedback on the clarity or feasibility of the requirements.
• Are there any industry best practices or alternative solutions DeCA should consider?
• Comment on the feasibility of the emergency response and replacement timelines across all specified locations.
5.0 Submission Instructions
Responses to this RFI are due by 2:00 PM EDST, April 10, 2026. Please submit your response via email to david.mootz@deca.mil (Contracting Specialist) with the subject line: "Response to RFI: CY 2026 Holiday Refrigerated Trailer Rentals".
mailto:david.mootz@deca.mil
| Request for Information (RFI) for CY 2026 Holiday Refrigerated Trailer Rentals |
| 1.0 Introduction and Purpose |
| 2.0 Background |
| 3.0 Summary of Requirements |
| 4.0 Information Requested from Industry |
| 5.0 Submission Instructions |
File details come from the government source that posted it. Updated .