Replacement Deck for the Lodge at Quail Ridge Park.pdf
PDF 2 MB Posted
- Solicitation number
- 26-91
- Issued by
- St. Charles County, Missouri
About this file
Summary: IFB 26-91 Replacement Deck for the Lodge at Quail Ridge Park
This is an Invitation for Formal Bid (IFB) issued by St. Charles County Government, Missouri, for the complete replacement of a deck at the Lodge located at Quail Ridge Park in Wentzville, Missouri. The scope of work includes removal and disposal of the existing deck platform, substructure, concrete piers and footings, stairs, and railings, followed by construction of a new deck utilizing Veka Deck Pro materials with specifications including #1 pressure-treated lumber 6"x6" posts on galvanized post stands bolted to 12" diameter bell bottom piers at 30" minimum depth, vinyl railing system with aluminum balusters, enclosed Veka stairs with 4.5' width, and a 9'3" concrete landing pad. All work must be completed during February 2027 when the lodge is closed for annual cleaning, with no concurrent reservations. The bid opening is scheduled for July 31, 2026, at 10:30 a.m. in Room 116 of the St. Charles County Administration Building at 201 North Second Street, St. Charles, Missouri 63301. Site visits are recommended and can be scheduled by contacting Park Supervisor Mike King at 636-949-7535, extension 3372. All questions must be submitted in writing by 3:00 p.m. on July 24, 2026. Sealed bids must be received at the St. Charles County Finance Department, Room 541, prior to bid opening, with one original and one copy required. The contract term is approximately twelve months from the date of notice of award, with project completion required within 120 calendar days of the Notice to Proceed.
All bid prices must be guaranteed for ninety days and submitted on an F.O.B. destination basis with all delivery costs included. Sales tax and federal taxes are not applicable and must be excluded from bids. A 5% bid bond, performance bond equal to 100% of the bid total, and payment and materials bond equal to 100% of the bid total are required. The contractor must maintain worker's compensation insurance with statutory limits, general liability and automobile insurance of $1,000,000 per person and $3,000,000 per occurrence (or $3,000,000 combined single limit), and property damage coverage of at least $1,000,000. The contractor must be enrolled in the E-Verify federal work authorization program and provide a notarized affidavit confirming compliance. For projects exceeding $75,000, prevailing wage requirements apply pursuant to Missouri Revised Statutes Sections 290.210 to 290.340, with Annual Wage Order #33 as amended May 28, 2026, in effect; contractors face $100 per day penalties for each worker paid below prevailing wage rates. The prime contractor must perform at least 40% of the contract work with its own organization. St. Charles County reserves the right to reject any or all bids and award to the low responsive, responsible bidder or the offeror whose proposal is most advantageous to the County, considering price and other factors including geographic location. All products must be manufactured or produced in the United States in compliance with Missouri's Domestic Products Procurement Act for contracts valued at $25,000 or more.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LEGAL NOTICE
INVITATION FOR FORMAL BID
IFB 26-91
For
Replacement Deck for the Lodge at Quail Ridge Park
St. Charles County Government St. Charles, MO
St. Charles County is seeking bids for a Replacement Deck for the Lodge at Quail Ridge Park.
The county reserves the right to terminate the contract for any violation, by the successful bidder, of any term or condition of the contract by giving thirty (30) days written notice stating the reasons therefore and giving the party time to remedy any deficiencies. All bid prices submitted must be guaranteed for ninety (90) days.
26-091 Replacement Deck for the Lodge at Quail Ridge Park
Parks Department
Proposal Response from (please complete)
Name of Company or individual
BID INSTRUCTIONS
One [1] signed original and one [1] signed copy of the bid must be received in a sealed envelope plainly marked “26-091 Replacement Deck for the Lodge at Quail Ridge Park” with the date and time of the bid opening in the lower left corner of the envelope.
An authorized representative of the company/person submitting the bid must sign the bid, in blue ink.
Bids must be submitted to the St. Charles County Finance Department, 201 North Second Street Room 541 St. Charles MO 63301 prior to the bid opening.
Bid opening will be on 07/31/2026 at 10:30 AM , in Room 116 of the St. Charles County Administration Building, 201 North Second Street, St. Charles, MO 63301.
St. Charles County reserves the right to accept and/or reject any and all bids.
Bid results may be obtained by going to our St Charles County Government website at http://www.sccmo.org/Bids.aspx click on “show Closed/Awarded/Cancelled bids”, select bid and click on “related documents”. No phone calls please. The time it takes for final bid results to be made public depends on the complexity of the project and the cost of the project.
BID INQUIRIES
Any questions or clarifications concerning this Request for Bid must be submitted in writing via E- mail (preferred), mail or fax to:
Lenore Moore St. Charles County Government Finance Department 201 North Second St St. Charles, Missouri 63301 lmoore@sccmo.org
For questions or inquiries concerning the specifications please contact:
Kevin Eastman Asst. Superintendent of Parks St. Charles County Government
201 N. Second Street St. Charles, Missouri 63301 Phone: (636) 949-7535 ext.7633 keastman@sccmo.org
Parks Department
Site visits are recommended. Please contact Park Supervisor Mike King to schedule an appointment. 636-949-7535 ext 3372
Quail Ridge Park Maintenance Building 560 Interstate Dr
Wentzville, Mo 63385
Klondike Shower House is located at: Klondike Park 4600 Hwy. 94 South Augusta, MO. 63332
The bid number and title shall be referenced on all correspondence.
All questions must be received no later than 03:00 PM on 07/24/2026. Any question received after this deadline may not be answered.
Responses to questions/clarifications will be placed on the County’s website http://www.sccmo.org/Bids.aspx . Check this website frequently for updates and any addendum that are issued.
Parks Department
Prohibited Communication
Contact with any representative, other than through the procedure outlined in the section titled “Bid Inquiries”, concerning this request is prohibited PRIOR TO BID OPENING.
Representative shall include, but not be limited to, all elected and appointed officials, and employees of St. Charles County and their Agents within St. Charles County.
Any Offeror engaging in such prohibited communications prior to Bid Opening may be disqualified at the sole discretion of St. Charles County.
TERMS AND CONDITIONS
St. Charles County reserves the right to reject any and all bids or parts of a bid and waive technicalities, and to adjust quantities.
All bids will be considered final. No additions, deletions, corrections, or adjustments will be accepted after the time of bid opening.
All delivery costs or charges must be included in the F.O.B. destination bid price.
City, County and State of Missouri Sales Tax and Federal Taxes are not applicable to sales made to St. Charles County and must be excluded.
The contract shall be effective for the approximate twelve (12) month period from the date of the notice of award.
The electronic version of this bid/RFP is available upon request. The document was entered into WORD for Microsoft Windows. The Purchasing Office does not guarantee the completeness and accuracy of any information provided on the electronic version. Therefore, respondents are cautioned that the hard copy of this bid/RFP on file in the Purchasing Office governs in the event of a discrepancy between the information contained in or on the electronic version and that which is on the hard copy.
Vendors are required to clearly identify any deviations from the specifications in this document.
An authorized officer of the company submitting the bid must sign all bids, in blue ink.
Vendors must submit two [2] signed copies of their bid; one is to be an original and so marked.
All prices and notations must be in blue ink or typewritten on the attached form. Mistakes must be crossed out, corrections typed adjacent and must be initialed in blue ink by the person signing the bid.
St. Charles County will not award any bid to an individual or business having any outstanding amounts due from a prior Contract or business relationship with the County or who owes any amount(s) for delinquent Federal, State or Local taxes, fees and licenses.
Parks Department
Sealed proposals received after the designated time of the receipt of the sealed proposals will be considered as “No Bid” and “Void” and will not be opened.
The successful bidder is specifically denied the right of using, in any form or medium, the names of St. Charles County or any other public agency of St. Charles County Government for public advertising unless express written permission is granted.
All bidders must possess the necessary and appropriate business and/or professional licenses in their field.
Award will be made to the low responsive, responsible bidder, or to the offeror whose proposal is most advantageous to the County, price and other factors considered including geographic location. When payments are to be made to the County, award will be made to the most advantageous offer.
County reserves the right to accept any item or group of items offered, unless the bidder qualifies his bid by specific limitations. The bid can be on an "all or none" basis if wording in the bid so states and if all items solicited are included in the bid.
When applicable, provide unit prices and extension prices. Where there is disagreement in the unit and extension prices, the unit price shall govern.
Prevailing Wage
The proposal for this Contract shall be based upon the required payment by the Bidder for wages for each craft or type of workmen required to execute the Contract as determined by the Department of Labor and Industrial Relations of Missouri, pursuant to Sections 290.210 to 290.340, RSMo. For those projects with a total cost greater than $75,000.00, a schedule of such prevailing hourly rate of wages as determined by the Department of Labor and Industrial Relations of Missouri, pursuant to said statutory provisions and made a part of this Contract.
Annual Wage Order #33 as amended 05/28/2026 shall be in effect for this project the provisions of sections 290.210 to 290.340 shall not apply to the construction of public works for which either the engineer’s estimate or the bid accepted by the County for the total project is in the amount of $75,000.00 or less. For any awarded bid in the amount of $75,000.00 or less that becomes subject to a contract amendment that increases the total project cost in excess of $75,000.00, the provisions of 290.210 to 290.340 shall apply only to that portion of the project that is in excess of $75,000.00.
The Contractor must comply with all provisions of the Prevailing Wage Law under Annual Wage Order #33 as amended 05/28/2026 for this project. The contractor will forfeit a penalty to the County of $100 per day (or portion of a day) if a worker is paid less than the prevailing rate for any work done under the contract by the contractor or by any subcontractor (see section290.250, RSMo). Certified payroll shall be submitted with request for payment.
Parks Department
BONDS: The following Bond types are required:
Performance Bond- A 100% Performance and Payment Bond in favor of the Owner. The Security Co. representing Contractor must be authorized to do business in the State of Missouri and be approved by Owner.
Bid Bond- A 5% deposit of the bid total, presented in the form of a cashier’s check, Certified check, or bid bond, made payable to St. Charles County.
INSURANCE
The Contractor shall maintain the following minimum amounts of insurance coverage during the life of the contract:
Worker's Compensation and Employer's Liability: Statutory WC limits as required by the Statutes of the State of Missouri (or a qualified self-insurer) and Employers Liability in an amount of no less than $1.0 million.
Automobile, General Liability and Property Damage: The Contractor shall maintain the following minimum amounts of automobile, general liability, and property damage insurance coverage during the life of the contract:
$1,000,000 for bodily injury or death to any one person and $3,000,000 per occurrence for automobile and general liability coverage; and property damage coverage of at least $1,000,000. A Combined
Single Limit Policy in the amount of $3,000,000 is an acceptable alternative. Automobile coverage must include non-owned vehicles.
The Automobile & General Liabilities policies shall be endorsed to include the County as an additional insured including the following language: Nothing in this endorsement shall serve to operate as a waiver of the County’s Sovereign Immunity or broaden the liability of the County beyond the provisions of Sections
537.600 to 537.610 of the Revised Statutes of Missouri. Vendor shall provide for 30 days advance written notice of any material change. A Waiver of Subrogation in favor of the County shall be endorsed on each of the policies. The required insurance shall be primary insurance with respect to any other insurance or self-insurance programs maintained by the County.
A Certificate of Insurance evidencing the above coverage(s) together with a copy of the required endorsements shall be provided to the County prior to the commencement of any work.
It shall be the contractor's responsibility to keep the respective insurance policies and coverages of any sub-contractor current and in force for the life of the contract.
Architects/Design Engineers: Errors and Omissions (Professional Liability): with limits of not less than
1,000,000.000 per claim/$3,000,000.00 aggregate covering all services provided by the Contract.
Coverage to be written on a claims-made basis.
Parks Department
Employment of Unauthorized Aliens Prohibited (Missouri Revised Statutes Section 285.530)
As a condition for the award of any contract or grant in excess of five thousand dollars by St.
Charles County to a business entity, the business entity shall, by sworn affidavit and provision of documentation**, affirm its enrollment and participation in a federal work authorization program (E- Verify) with respect to the employees working in connection with the contracted services. Every such business entity shall sign an affidavit affirming that it does not knowingly employ any person who is an unauthorized alien in connection with the contracted services. [RSMO 285.530 (2)]
An employer may enroll and participate in a federal work authorization program (E-Verify) and shall verify the employment eligibility of every employee in the employer’s hire whose employment commences after the employer enrolls in a federal work authorization program. The employer shall retain a copy of the dated verification report received from the federal government. Any business entity that participates in such program shall have an affirmative defense that such business entity has not violated subsection 1 of this section. [RSMO 285.530 (4)]
Any entity contracting with St. Charles County shall only be required to provide the referenced affidavit on an annual basis. A copy of the affidavit is included in this bid request. Vendors may choose to send the required documentation using one of the following options:
Send the notarized affidavit and E-Verify MOU signature page to: St. Charles County, Attn:
Purchasing Manager, 201 N Second Street, Room 541, St. Charles, MO 63301prior to responding to any solicitations; OR
Send the notarized affidavit and E-Verify MOU signature page along with a bid solicitation response.
These documents will be kept on file. The notarized affidavit and E-Verify MOU signature page will remain current for one year from the date of the notarized affidavit.
** PLEASE NOTE:
Acceptable enrollment and participation documentation consists of a valid copy of the signature page of the E- Verify Memorandum of Understanding, completed and signed by the Contractor, and the Department of Homeland Security - Verification Division
The online address to enroll in the E-verify program is:
https://everify.uscis.gov/account/enroll
Parks Department
Open Records
Any and all information contained in or submitted with the bid becomes a public record subject to the Missouri Sunshine Law when the bids are opened. If the bidder believes that any information contained in or submitted with the bid is protected from disclosure by the Missouri Sunshine Law, the bidder must clearly identify what information the bidder believes is so protected and must also clearly identify the legal basis therefore.
Veteran Friendly Employment Policy
"Indicate whether you have developed a veteran friendly employment policy and, if so, attach a copy of such policy to your response as a point of information."
"YES" our company has a veteran friendly employment policy.
"NO" our company does not have a veteran friendly employment policy.
Please include a copy of your veteran friendly employment policy with your submission.
Parks Department
Bid Specification
The St. Charles County Parks Department is soliciting bids for the purchase/replacement and installation of New Deck for the Lodge at Quail Ridge Park.
Quail Ridge Lodge is located at:
Quail Ridge Park
560 Interstate Dr
Wentzville, Mo 63385
These Bid Specs are based on Veka Deck materials. Unless otherwise specified, any manufacturers’ names, trade names, brand names, information and/or catalog numbers listed in this specification are descriptive, not restrictive. The bidder may offer any product that meets or exceeds the applicable specifications. The bidder must demonstrate comparability, by including appropriate catalog materials, literature, specifications, test data, etc. The County shall determine in its sole discretion whether a product is acceptable as an equivalent.
Bidders are required to provide a list of references for similar projects completed within the last five (5) years. A detailed timeline is required for completion of the project once the notice to proceed has been issued. Bids shall include all applicable warranty information and contact information for the contractor’s on-site supervisor
The completed project must meet the following specifications:
General Conditions for Execution of Contract
The Contractor shall supply all labor and material as required for the execution of the contract.
The Contractor shall comply with all Federal and State Employment / Labor regulations including those from the U.S. “Occupational Safety and Health Administration”.
The Contractor shall provide all applicable Insurance Certificates to the County upon the award of the bid.
The Contractor shall specifically claim any exclusions or deviations from the bid specifications.
The Contractor shall submit any such exclusions or deviations with their proposal.
The Contractor is responsible for obtaining all installation permits for the project as required. The Contractor shall include the cost of all permit fees in their proposal submitted to the County.
The Contractor shall complete the project within 120 days after the contract has been awarded by the County.
Parks Department
Bid Specifications Cont.
ALL WORK will be required to be done start to finish during the month of February 2027 when the lodge is shut down for the month for its annual cleaning. During this time there will be no reservations at the lodge.
Remove and dispose of all existing deck platform, sub structure, concrete piers/footings, stairs, and railings.
New sub-structure, all #1 pressure treated lumber, 6”x6” posts on galvanized post stands bolted to 12” diameter bell bottom piers, 30” min. depth. Lay down Veka Deck Pro planks parallel – color TBD to home and secure with concealed fasteners. Ice and water shield and blocking-all standard.
New header board attached directly to building
Vinyl railing system w/aluminum balusters – color TBD
Veka stairs with enclosed risers 4.5’ width
9’ 3” concrete landing pad at bottom of stair case
Colored fascia board to match deck
Daily clean-up of all construction materials and debris. Jobsite will be left in a broom clean condition.
The building must be secured daily and cannot be left with any open voids and the end of each day.
Protection of building and property with any needed materials.
It is the contractor’s responsibility to get all measurements.
Parks Department
Exception Sheet
If the item(s) and/or services proposed in the response to this bid is in any way different from that contained in this proposal or bid, the bidder is responsible to clearly identify all such differences in the space provided below. Otherwise, it will be assumed that the bidder’s offer is in total compliance with all aspects of the proposal or bid.
Below are the exceptions or differences to the stated specifications (attach additional sheets as needed):
Date:
Signature:
Title:
Compan
Parks Department
Please list three (3) references of similar projects you have completed in the last five (5) years
1. Name of
Project
Address
Contact Person Phone #
2. Name of
3. Name of
Parks Department
THIS FORM MUST BE COMPLETED AND ENCLOSED WITH THE BID
Audit Clause for Contracts
Examination of Records
The Contractor's records must include, but not be limited to, accounting records (hard copy, as well as computer readable data), written policies and procedures, subcontractor files, indirect cost records, overhead allocation records, correspondence, instructions, drawings, receipts, vouchers, memoranda, and any other data relating to this contract shall be open to inspection and subject to audit and/or reproduction by the County Auditor, or a duly authorized representative from the County, at the County's expense. The contractor must preserve all such records for a period of three years, unless permission to destroy them is granted by the County, or for such longer period as may be required by law, after the final payment. Since the Contractor is not subject to the Missouri Sunshine Law (Chapter 610, RSMo), information regarding the Contractor's operations, obtained during audits, will be kept confidential.
The Contractor will require all subcontractors under this contract to comply with the provisions of this article by including the requirements listed above in written contracts with the subcontractors.
Vendor Information
Company Name:
Business Address:
Business Hours:
Phone: Fax:
Email address:
Contact Person:
Authorized Signature:
(Indicates acceptance of all bid terms and conditions)
Date:
Parks Department
AFFIDAVIT OF WORK AUTHORIZATION
The bidder/contractor who meets the section 285.525, RSMo definition of a business entity must complete and return the following Affidavit of Work Authorization.
Comes now (Name of Business Entity Authorized Representative) as
(Position/Title) first being duly sworn on my oath, affirm
(Business Entity Name) is enrolled and will continue to participate in the E-Verify federal work authorization program with respect to employees hired after enrollment in the program who are proposed to work in connection with the services related to contract(s) with the County for the duration of the contract(s), if awarded in accordance with subsection 2 of section 285.530, RSMo. I also affirm that
(Business Entity Name) does not and will not knowingly employ a person who is an unauthorized alien in connection with the contracted services provided to the contract(s) for the duration of the contract(s), if awarded.
In Affirmation thereof, the facts stated above are true and correct. (The undersigned understands that false statements made in this filing are subject to the penalties provided under section 575.040, RSMo.)
Authorized Representative's Signature Printed Name
Title Date
E-Mail Address
Subscribed and sworn to before me this of . I am
(DAY) (MONTH, YEAR)
commissioned as a notary public within the County of , State of
(NAME OF COUNTY)
, and my commission expires on .
(NAME OF STATE) (DATE)
Signature of Notary Date
Parks Department
ST. CHARLES COUNTY
DOMESTIC PRODUCTS PROCUREMENT ACT (BUY AMERICAN)
The Missouri Domestic Products Procurement Act (34.350-34.359 RSMo) requires that for all bids with a value of $25,000 or more, the goods or commodities purchased by any public agency (which definition includes all political subdivisions of the State, including counties) or used or supplied in the construction, alteration, repair, or maintenance of any public works must be manufactured or produced in the United States. As defined in 34.350 RSMo, United States means the United States of America, the District of Columbia, and all territories and possessions subject to the jurisdiction of the United States. The law also requires that the bidder must provide proof of compliance. Note: In general, if an import tariff is applied to an item, it does not qualify for the Buy American preference. In addition, Most Favored Nation status does not allow application of the preference.
Section A – All Products Are Manufactured or Produced In U.S.
If all products bid qualify as domestic products under Missouri law, complete only Section A.
I hereby certify that all products qualify as domestic, that the information provided is true and correct, and complies with all provisions of Sections 34.350-34.359 RSMo. I understand that any misrepresentation herein constitutes the commission of a class A misdemeanor pursuant to Section 34.355 of the Revised Statutes of Missouri.
SIGNATURE
COMPANY NAME
If Section A is completed, do not complete Section B.
Section B – Only One Product Line or No Products Are Manufactured or Produced In U.S.
If only one product line or no products are manufactured or produced in the U.S. complete only section B.
I hereby certify that there is only one product line, or no product manufactured or produced in the U.S., that the information provided is true and correct, and complies with all provisions of Sections 34.350-34.359 RSMo. I understand that any misrepresentation herein constitutes the commission of a class A misdemeanor pursuant to Section 34.355 of the Revised Statutes of Missouri.
SIGNATURE
COMPANY NAME
Section C – Products May Qualify Because of Qualifying Treaty If some or all products bid qualify for domestic status because of a trade treaty, etc., then the bidder must identify each product, country and qualifying treaty, etc. below. The bidder must list ALL products which are or may qualify as domestic below. If more space is needed, please copy this form and submit as an attachment.
BID ITEM NUMBER(S) COUNTRY WHERE MANUFACTURED OR
PRODUCED
QUALIFYING TREATY, LAW,
AGREEMENT, OR REGULATION
SECTION C
I hereby certify that the specific items listed above are domestic, that the information provided is true and correct, and complies with all provisions of Sections 34.350-34.359 RSMo. I understand that any misrepresentation herein constitutes the commission of a class A misdemeanor pursuant to Section 34.355 of the Revised Statutes of Missouri.
SIGNATURE
COMPANY NAME
Parks Department
THIS FORM MUST BE COMPLETED AND ENCLOSED WITH THE BID
Anti-Discrimination Against Israel Act Certification
1. Pursuant to Section 34.600 of the Revised Statutes of Missouri, St. Charles County shall not enter into a contract to acquire or dispose of services, supplies, information technology, or construction unless the contract includes a written certification that the company is not currently engaged in and shall not, for the duration of the contract, engage in a boycott of goods or services from the State of Israel;
companies doing business in or with Israel or authorized by, licensed by, or organized under the laws of the State of Israel; or persons or entities doing business in the State of Israel.
2. This requirement shall not apply to contracts with a total potential value of less than one hundred thousand dollars or to contractors with fewer than ten employees.
3. Vendor affirms they have reviewed the requirements and definitions contained in RSMo. § 34.600.
Vendor hereby certifies they have complied with the terms of RSMo § 34.600, as applicable to this agreement, and will comply for the duration of the contract period.
Vendor Date
Parks Department
COUNTY-CONTRACTORS AGREEMENT
Bid 26-091 Replacement of deck for the Lodge at Quail Ridge Park
This agreement, made by and between , hereinafter called the CONTRACTOR, and St. Charles County, Missouri, hereinafter called the COUNTY.
Now therefore, CONTRACTOR and COUNTY, in consideration of mutual covenants herein set forth, agree as follows:
ARTICLE 1. CONTRACT PRICE
COUNTY shall pay CONTRACTOR in current funds, for completion of the Work designated in Article 2 in accordance with the Contract Documents, an amount equal to the quantity of the project bid as indicated in the CONTRACTOR'S Bid, for the total amount of:
(in words)
($ ) (in figures)
ARTICLE 2. SCOPE OF THE WORK
The scope of the work is described in the Bid Specifications for this project, which are incorporated herein by this reference.
ARTICLE 3. TIME OF COMPLETION
The CONTRACTOR shall commence operations upon receiving the written Notice to Proceed from the COUNTY and at such time to complete the contract work by the dates indicated below. Project completion shall be defined as 100% completion of all items of the project including correction of deficiencies. The project shall be fully complete as follows:
Complete all work within one hundred twenty (120) calendar days from the original Notice to Proceed.
The time of completion is an essential condition of this Contract.
ARTICLE 4. PAY QUANTITIES
The COUNTY shall pay the CONTRACTOR for all work done on the basis of final computations for all work acceptably completed according to this Contract.
ARTICLE 5. PROGRESS PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment monthly according to “General Requirements” section entitled “Progress Payments”. Applications for Payment will be processed by the COUNTY. COUNTY shall make progress payments on account of the Contract Price on the basis of CONTRACTOR’S Applications for Payment as approved by the COUNTY. All progress payments will be on the basis of the progress of
Parks Department the Work measured by the schedule of values, and in the case of Unit Price Work based on the number of units completed. No progress payments will be made if the CONTRACTOR does not have a current progress schedule accepted by the COUNTY.
ARTICLE 6. FINAL PAYMENT AND ACCEPTANCE
When all work provided for under this contract has been completed in conformance with the specifications and requirements of this contract, and accepted without regard to the provisions of guarantee as provided under the terms of this contract, a final cost estimate shall be prepared by the CONTRACTOR and approved by the COUNTY and filed with the COUNTY and with the CONTRACTOR within fifteen (15) days after the date of acceptance of the work as a statement of the amount due the CONTRACTOR. This estimate shall be based on appropriate unit quantities of material placed, including any charges for extra work ordered and properly chargeable under this contract, and deducting any sum properly deductible under this contract.
ARTICLE 7. THE CONTRACT DOCUMENTS
The Contract Documents which comprise the entire agreement between COUNTY and CONTRACTOR concerning the Work consist of the following:
a. This County-Contractors Agreement.
b. Exhibits to this County-Contractors Agreement, including the General Requirements.
c. Performance and Payment Bonds.
d. Notice of Award.
e. Notice to Proceed.
f. Request for Bid and Specifications for the project
g. Drawings with each sheet bearing the following general title:
h. Addenda through .
i. Bid Form.
j. All Written Amendments and other documents amending, modifying, or supplementing the Contract Documents, which may be delivered or issued after the Effective Date of the Agreement, and are not attached hereto.
There are no Contract Documents other than those listed in this article. The Contract Documents may be amended, modified, or supplemented only in one or more of the following ways: (i) a Written Amendment; (ii) a Change Order; or (iii) a Work Change Directive.
The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by a Field Order, or COUNTY’S written interpretation or clarification.
ARTICLE 8. RATES OF PAY
The CONTRACTOR hereby agrees that the prevailing rates of pay shall be paid to skilled and unskilled labor employed under the terms of this contract. The CONTRACTOR shall forfeit to the COUNTY one hundred dollars ($100) for each workman employed, for each calendar day, or portion thereof, such workman is paid less than the said stipulation rates for any work done under said contract, by him or by any subcontractor under him. Annual Wage Order #33 as amended 05/28/26 shall be in effect for this project.
ARTICLE 9. PERFORMANCE OF THE WORK
The CONTRACTOR, acting as an independent contractor, shall furnish all supervision, labor, equipment, tools, materials, and supplies necessary to perform and shall perform all work in accordance with the Contract Documents and any applicable County ordinances, and state and federal laws. CONTRACTOR
Parks Department represents and warrants that he has special skills which qualify him to perform the Work in accordance with the Contract and that he is free to perform all such Work and is not a party to any other agreement, written or oral, the performance of which would prevent or interfere with the performance, in whole or in part, of the Work. The prime CONTRACTOR must perform, with its own organization, contract work amounting to not less than 40% of the total original contract.
ARTICLE 10. SUPERVISION
The CONTRACTOR shall supervise and direct the Work, using the CONTRACTOR'S best skill and attention. The CONTRACTOR shall be solely responsible for and have control over construction means, methods, techniques, sequences, and procedures and for coordinating all portions of the Work under the Contract, unless Contract Documents give other specific instructions concerning those matters.
ARTICLE 11. SAFETY
The COUNTY and any consulting engineer hired by the COUNTY may have personnel on the project site from time to time. All information and/or instructions shall be requested in writing by the CONTRACTOR and responded to in writing. No opinion or instructions will be given to the CONTRACTOR on safety.
The CONTRACTOR shall be solely responsible for the safety on and around the project site including shoring, ladders, drop cords, scaffolding, barricades, construction means, methods, techniques, sequences and procedures.
The CONTRACTOR shall comply with all requirements of Section 292.675 RSMo., as amended, which is incorporated herein by this reference. Said statute relates to the OSHA Construction Safety Program.
COUNTY hereby notifies CONTRACTOR that the penalties for failure to comply with the training and all other requirements set forth in said statute include the forfeiture of penalties to COUNTY of two thousand five hundred dollars ($2,500.00) plus one hundred dollars ($100.00) for each employee employed by CONTRACTOR or a subcontractor, for each calendar day, or portion thereof, such employee is employed without the required training.
ARTICLE 12. INDEMNITY
To the fullest extent permitted by law, the CONTRACTOR shall indemnify and hold harmless the COUNTY, any consulting engineer hired by the COUNTY, their consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorneys' fees, arising out of or resulting from performance of the Work, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property other than the Work itself, including loss of use resulting there from, but only to the extent caused in whole or in part by negligent acts or omissions of the CONTRACTOR, a Subcontractor, or anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity, which would otherwise exist as to a party or person described in this Section.
In claims against any person or entity indemnified under the above paragraph by an employee of the CONTRACTOR, a Subcontractor, or anyone directly or indirectly employed by them or anyone whose acts they may be liable, the indemnification obligation under this paragraph shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the CONTRACTOR or a Subcontractor under workers' or workmen's compensation acts, disability benefit acts or other employee benefit acts.
The obligations of the CONTRACTOR under this Section shall not extend to the liability of the COUNTY, the COUNTY’S consultants, and agents and employees of any of them arising out of (1) the preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, designs or specifications, or (2) the giving of or the failure to give directions, after requested in writing by the CONTRACTOR, or instructions by
Parks Department the COUNTY, the COUNTY’S consultants, and agents and employees of any of them provided such instructions or failure to give is the primary cause of the injury or damage.
ARTICLE 13. TERMINATION BY COUNTY OR CONTRACTOR
(a) If the CONTRACTOR is adjudged to be bankrupt, or if the CONTRACTOR makes a general assignment for the benefit of creditors, or if a receiver is appointed on account of the CONTRACTOR’s insolvency, or if the CONTRACTOR fails, except in cases for which extension of time is provided, to make progress in accordance with the Construction Schedule, or if the CONTRACTOR fails to make prompt payment to Subcontractors or prompt payment for material or labor, or disregards laws, ordinances or the instructions of the COUNTY, or otherwise breaches any provision of the Contract, the COUNTY may, without prejudice to any other right or remedy, terminate the Contract by giving written notice to the CONTRACTOR and his surety. Upon such notification the COUNTY shall be entitled to take possession of the Work and of all materials and equipment thereon and finish the Work by whatever method the COUNTY may deem expedient, which may include, but is not limited to, the COUNTY itself completing the work or the COUNTY hiring others to complete said work. In such case, the CONTRACTOR shall not be entitled to receive any further payment until the Work is finished. If the unpaid balance of the Contract Sum shall exceed the expenses of finishing the Work, including additional engineering, architectural, managerial and administrative expenses, such excess shall be paid to the CONTRACTOR. If such expenses and damages exceed the unpaid balance of the Contract Sum, the CONTRACTOR shall pay the difference to the COUNTY promptly upon demand. In the event of termination pursuant to this paragraph, the CONTRACTOR, upon the request of the COUNTY, shall promptly:
i. assign to the COUNTY in the manner and to the extent directed by the COUNTY all right, title and interest of the CONTRACTOR under any subcontracts, purchase orders and construction equipment leases to which the CONTRACTOR is a party and which relate to the Work or to construction equipment required therefore, and
ii. make available to the COUNTY to the extent directed by the COUNTY all construction equipment owned by the CONTRACTOR and employed in connection with the Work.
(b) Performance of the Work hereunder may be terminated by the COUNTY by giving three (3) days prior written notice to the CONTRACTOR if the COUNTY, in its sole discretion, decides to discontinue or suspend construction. In the event of such termination, as opposed to termination pursuant to paragraph
(a) of this Article 13, the Contract Sum shall be reduced in an equitable manner by agreement between the parties.
ARTICLE 14. AUDIT CLAUSE
Examination of Records
The CONTRACTOR’s records which shall include, but not be limited to, accounting records (hard copy, as well as computer readable data), written policies and procedures, subcontractor files, indirect cost records, overhead allocation records, correspondence, instructions, drawings, receipts, vouchers, memoranda, and any other data relating to this contract shall be open to inspection and subject to audit and/or reproduction by the County Auditor, or a duly authorized representative from the COUNTY, at the COUNTY’s expense.
The CONTRACTOR shall preserve all such records for a period of three years, unless permission to destroy them is granted by the COUNTY, or for such longer period as may be required by law, after the final payment. Since the CONTRACTOR is not subject to the Missouri Sunshine Law (Chapter 610, RSMo), information regarding the CONTRACTOR’s operations obtained during audits will be kept confidential.
Parks Department
IN WITNESS WHEREOF the parties hereto have caused this instrument to be executed in four (4) original counterparts as of the day and year last written below. CONTRACTOR:
By: Name (printed) _________________________ Date: ______________________
Title: _____________________________________
ATTESTED BY:
County Registrar
ST. CHARLES COUNTY, MISSOURI
By: ____________________________________ Date: __________________________ Steve Ehlmann, County Executive
CERTIFICATE OF FINANCE DIRECTOR
I certify pursuant to § 50.660 RSMo., as amended, that there is a balance otherwise unencumbered to the credit of the appropriation to which this contract is chargeable, and a cash balance otherwise unencumbered in the treasury to the credit of the fund from which payment is to be made, each sufficient to meet this obligation.
Mike Sommer, Finance Director
Parks Department
GENERAL REQUIREMENTS
1. SUMMARY OF WORK
The work to be performed under this Contract is summarized as follows:
Replacement of deck for the lodge at Quail Ridge Park Construction shall include all clearing, excavation, construction, and cleanup.
The complete scope of the work is described in the Bid Specifications for this project, which are incorporated herein by this reference.
2. GENERAL
St. Charles County reserves the right to add or reduce any quantity of all Contract bid items at the Contract unit price for that item.
3. DRAWINGS
Accompanying these specifications are drawings, entitled “Replacement of deck for the lodge at Quail Ridge Park” which are to illustrate and become a part of these specifications.
These drawings and specifications are intended to be so coordinated that any work included in one and not in the other, shall be executed as if included in both.
All work contemplated and described in the specifications shall be carried out in accordance with the general and detail drawings made a part thereof and with such additional detail drawings and directions as may be given from time to time during the progress of the work. On all drawings, computed dimensions shall take precedence over measurements by scale and full-sized details over scale drawings.
The CONTRACTOR shall maintain a record set of drawings at the site and mark thereon any changes as the work proceeds. These drawings shall indicate the vertical and horizontal location of improvements in plan and profile view.
Upon completion of the work, these “as-built” changes shall be transferred, with changes clearly identified, onto blueprint drawings which will be furnished to the COUNTY. These “as-built” drawings, certified by a Land Surveyor or Engineer registered in the State of Missouri, shall be delivered to the COUNTY for its review and approval prior to final payment.
4. INSURANCE
The CONTRACTOR shall maintain all required insurance and provide required certificates in accordance with the insurance requirements listed in the Request for Bid and/or Specifications for the project.
5. PERFORMANCE BOND
Parks Department
A bond will be required for the full amount of the contract price with a surety company, conditioned for the faithful performance of this Contract and the guarantee of the work. Both Contract and bond shall be executed in quadruplicate and in a form acceptable to the COUNTY.
The cost of the performance bond shall be incidental to the price bid.
6. PAYMENT AND MATERIALS BOND
A bond will be required for the full amount (100 percent Labor and Material) of the contract price with a surety company. The bond shall be executed in quadruplicate and in a form acceptable to the COUNTY. The cost of the payment and materials bond shall be incidental and included in the bid price.
7. REFERENCE STANDARDS
Reference to standards, specifications, manuals, or codes of any technical society, organization, or association, or to the Laws or Regulations of any governmental authority, whether such reference be specific or by implication, shall mean the latest standard specification, manual, code, or Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the Agreement if there were no Bids), except as may be otherwise specifically stated. However, no provision of any referenced standard, specification, manual, or code (whether or not specifically incorporated by reference in the Contract Documents) shall be effective to change the duties and responsibilities of COUNTY, CONTRACTOR, or Engineer, or any of their Consultants, agents, or employees from those set forth in the Contract Documents, nor shall it be effective to assign to Engineer, or any of Engineer's Consultants, agents, or employees, any duty or authority to supervise or direct the furnishing or performance of the Work.
8. [Deleted for Parks projects]
9. COORDINATION WITH OTHER CONTRACTORS
There is a possibility that other CONTRACTORS may be working in the vicinity during the construction of this Contract, particularly in the area of the parking lot and proposed future barn.
The CONTRACTOR shall inform himself fully of the conditions relating to construction and labor under which the work will be or is now being performed, and the CONTRACTOR must employ as far as possible such methods and means in carrying out his work as will not cause any interruptions or interference to any other CONTRACTOR. When necessary for proper prosecution of work, each CONTRACTOR shall permit the other access through the overlapping construction areas and the use of any access or haul roads constructed by others.
10. SHOP DRAWINGS
In all cases where details or shop drawings are required, the CONTRACTOR shall submit copies of such drawings to the COUNTY for review before any of the work is begun. Should extensive changes be necessary, corrected drawings shall be submitted for final review. The CONTRACTOR shall thoroughly review the shop drawings for compliance with the Contract drawings and specifications before submitting them to the COUNTY. The shop drawings shall be stamped “reviewed” by the CONTRACTOR BEFORE submitting them to the COUNTY. When it is required to submit material or equipment, shop drawings, manufacturer’s brochures, or samples for review, said submittals are to be made to the COUNTY through the General
CONTRACTOR.
Each item submitted for approval must be identified by reference to specification paragraph number
Parks Department and/or plan drawing number.
If the item described or submitted is not exactly as specified by the plans and/or specifications, the procedure shall be as follows:
With the submittal CONTRACTOR shall state in writing that the item is not exactly as specified by the plans and/or specifications and he shall state the difference. The COUNTY will then evaluate the submittal and will transmit the accepted or rejected submittal to the CONTRACTOR.
When substitutions for the specified items are approved, the submitting CONTRACTOR will be responsible for all costs incurred due to the changes from plans and/or specifications. This includes additional design costs, material and equipment costs and any appurtenant cost that may be incurred by other trades.
The COUNTY and/or any consulting engineer hired by the COUNTY will not be responsible for errors in the shop drawings which their examination and scrutiny many have failed to detect, and the CONTRACTOR shall be absolutely responsible for the correctness of the drawings furnished by it or its subcontractors.
11. RIGHTS-OF-WAY
All improvements will be constructed within land owned by the COUNTY and the public right-of-way shown on the plans.
Upon completion of the contract work, the CONTRACTOR shall restore, without additional cost to the COUNTY, all improvements within the park and right-of-way to substantially the same conditions as they were at the commencement of the construction work, unless otherwise noted.
At project closeout, the COUNTY will ensure the conditions of areas located outside of the construction area and existing right-of-way were not damaged, and if damaged were repaired to the same as at the commencement of the work. Non-approval can result in the withholding of final payment.
All costs resulting from the maintenance or improvement of areas outside the construction limits depicted on the plans – such as incidental grading, and the repair of improvements damaged by the CONTRACTOR – shall be borne by the CONTRACTOR.
12. INSPECTIONS
The CONTRACTOR shall assure that representatives of the COUNTY shall have the privilege of inspecting and reviewing work done by the CONTRACTOR or his subcontractors on this project.
The CONTRACTOR shall also assure that all of his subcontractors, if any, maintain all books, documents, papers and other evidence pertaining to cost incurred in connection with the Contract and make such materials available at such CONTRACTOR’s office at all reasonable times during the contract period.
13. LABOR POSTINGS
All information as required by State and/or Federal wage/labor laws shall be posted by the CONTRACTOR on the job site.
Parks Department
14. CONFLICT WITH PERSONNEL
If a conflict between personnel of the CONTRACTOR and the COUNTY escalates to the point that it hinders the progress of the Work and cannot be settled amicably, the CONTRACTOR’s personnel involved in the conflict shall be removed from the project.
A personnel conflict shall not give cause for the CONTRACTOR to terminate this Contract nor to pull off employees from active job sites. If the CONTRACTOR withdraws crews, the COUNTY may, at its sole discretion, consider the Contract to be terminated under the provisions of Article 13 of the County-Contractors Agreement. If the COUNTY so determines, notices shall be given as set forth therein.
15. EROSION CONTROL MEASURES
The COUNTY will provide as a part of the Construction Plans an Erosion Control Plan, but the CONTRACTOR shall provide adequate erosion control features in accordance with any local, state and federal regulations, this includes the St. Charles County Erosion Control and Sediment Guidelines as well as in accordance with the Construction Plans. The CONTRACTOR shall submit any additions or deletions from the provided erosion control plan to the COUNTY for approval prior to the start of construction.
16. PROGRESS SCHEDULE
The CONTRACTOR shall, prior to or at the preconstruction meeting, prepare and submit to the COUNTY for approval a detailed schedule of all operations showing the following: 1. The anticipated time of commencing and completion of various operations to be performed under this Contract.
2. The estimated time required for fabrication and/or delivery of all materials and equipment required for the work.
3. Utilities relocations by others and how it affects CONTRACTOR schedules.
The COUNTY may require the CONTRACTOR to adjust his plan, equipment or construction forces, if progress falls behind the approved schedule such that completion within the specified time appears doubtful.
The CONTRACTOR must update the progress schedule and resubmit to the County for acceptance anytime work falls behind the current accepted schedule.
17. PROGRESS REPORTS
The CONTRACTOR shall submit progress reports on a monthly basis beginning the first Friday after award of the project and continuing through closeout of the project. The reports shall briefly describe work accomplished during the time period and projected work for the next time period.
They shall indicate the project number, and the days the CONTRACTOR was unable to work due to conditions beyond his control (list specific reason, i.e. rain, cold, etc.). They shall be in a neat, legible form and submitted to the COUNTY (four copies).
18. PROGRESS PAYMENTS
CONTRACTOR shall submit original signed monthly pay requests to the COUNTY by the tenth of the month. Payment will be made by the first of the next month. The pay request will reflect the
Parks Department following changes and totals made on past invoices for:
Contract Amount Total Change Order amounts Pay Item quantities of work completed that month Additional pay items Previously…