REPLACE MAIN EMD-COOLING TOWERS_A0001 CLARIFICATIONS AND ADDED SCOPE ITEMS SF30-ATT.docx

DOCX document 19 KB Posted

Attached to
6115--526-26-102 Replace Main EMD Generators and Cooling Towers Federal contract opportunity
Solicitation number
526-26-102
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2

About this file

This document is an Amendment A0001 to Invitation for Bid (IFB) 36C24225B0038 for replacing Main EMD Generators and Cooling Towers at the James J. Peters DVA Medical Center in Bronx, NY. The amendment provides critical clarifications for bidders, including challenging rigging conditions with limited transportation access at the site, detailed equipment transportation requirements from a storage location in Deer Park, NY, and additional scope items such as installing new Motorola Avigilon cameras, PACS system, and security bollards.

The solicitation involves comprehensive infrastructure upgrades with a $200,000 allowance added to the bid pricing sheet. Key technical requirements include transporting two generators, switchgears, and related equipment, integrating a new camera and access control system into the existing facility infrastructure, and installing security bollards. The project is being conducted by the Department of Veterans Affairs Veterans Health Administration, with the associated NAICS code 236220 for General Construction. Contractors must carefully evaluate site-specific rigging challenges and transportation logistics when preparing their bids.

View the file

Other files for this federal contract opportunity

Other files attached to 6115--526-26-102 Replace Main EMD Generators and Cooling Towers, newest first.
File Type Posted
REPLACE MAIN EMD-COOLING TOWERS 36C24225B0038_AMENDMENT A0001_9.10.25.docx DOCX document
REVISED BID SHEET_MAIN EMD-COOLING TOWERS_9.10.25.docx DOCX document
Site Visis Sign-In Sheet_EMD-Cooling Towers_8.27.25.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB 36C24225B0038

Please see below clarifications and additional scope of work items based on the site visit conducted on 8/27/2025, in an effort to ensure that all bidders are provided with consistent information that may affect bid pricing, and based on the lack of RFI’s received for this solicitation:

1. Rigging conditions at the location of the Main EMD’s and Cooling Towers are extremely limited. Contractors must be aware that there have been difficulties in the past while attempting to transport generator equipment on a flat bed tractor trailer, as there is a limited “turning radius” at the lower main road leading up to the generator housing. Contractors must bid accordingly and will be required to rely on effective “means and methods” to ensure that the generators can be properly transported from the main road to the installation location of the Main EMD’s. Rigging methods will need to be evaluated and verified prior to submitting a bid and will not be a cause for delay or subject to “unforeseen site conditions” resulting in additional work or additional cost to the government. Contractors MUST bid accordingly.

2. It is the Contactor`s responsibility for transporting and the delivery of the two (2) generators, switchgears, neutral grounding resistors, loose crates, and JW/AC Radiator and all other equipment in accordance with the design from the storage location to the final installation site as indicated in the contract documents.

The equipment storage site is located at Brothers & Company Inc.

830 Long Island Ave Deer Park NY 11729

3. It is the Contractor’s responsibility to furnish and install new Motorola Avigilon cameras and PACS system (HID for PIV readers in accordance with the design). Installation shall include providing and installing CAT6A cabling from each camera to a PoE network switch to the data center caged equipped with a minimum of two (2) fiber ports. The contractor shall also provide SFPs (MM LC modules), fiber LC aqua connectors, fiber cabinet port rack mounts, and OM3 50-micron fiber optic cables as needed. All required components shall be furnished and installed to provide a complete and operational system. The system shall be routed and fully integrated into the facility’s existing Avigilon platform, with fiber connections routed to the Network Video Recorder (NVR) located in the Police Station on the first floor of Building 100. The contractor shall supply and configure all necessary software, programming, and system adjustments to ensure a full operational system and seamless integration into the existing Avigilon system.

4. Per PSRDM mitigation measures, bollards are needed near the building southwest corners and new exterior door locations.