Replace Boiler Prebid Meeting Minutes.pdf
PDF 161 KB Posted
- Attached to
- 511/21177. AGY; Dowagiac Armory - Replace Boiler
- Solicitation number
- RFQ 171 210000000464 4
- Issued by
- Calhoun County, Dodgeville CDP, Michigan
About this file
This document is mandatory pre-bid meeting minutes for a boiler replacement project at the Dowagiac Armory in Dowagiac, Michigan, involving the Department of Military and Veterans Affairs (DMVA) and the Department of Technology, Management & Budget (DTMB). The project requires replacement of a fire-tube boiler system and associated feed system components at the armory facility. The mandatory pre-bid meeting was held on-site on August 25, 2021, at 11:00 AM, which served as the only authorized site visit for bidding purposes. Bidders were required to sign the mandatory pre-bid sign-in sheet or their bids would not be accepted. Request for Information (RFI) submissions were accepted until September 1, 2021, at 10:00 AM local time, with bid addendums posted no later than close of business on September 3, 2021. The bid opening was scheduled for September 8, 2021, at 2:00 PM local time, with electronic bidding through the SIGMA VSS website (sigma.michigan.gov). DTMB anticipated 45 days to award the contract following bid receipt. Project completion is required within 120 calendar days after the preconstruction meeting, with work hours limited to 8:00 AM to 4:00 PM at the site location.
Bid security of 5 percent of the awarded base bid cost is required; however, if the bid is less than $50,000, payment and performance bonds are not required. Prevailing wage requirements apply to this project. The project includes a $10,000 contingency allowance with no alternates available. Liquidated damages are assessed at $200 per day for schedule delays. All required permits (boiler, mechanical, and electrical) must comply with Michigan codes. Pre-award submittals for boiler feed system and fire-tube boiler sections must be provided prior to construction commencement. The contractor must submit approved shop drawings before work begins and maintain a full-time superintendent or project manager on-site throughout construction. A construction waste management and disposal plan with a goal to salvage or recycle 60 percent by weight of non-hazardous solid waste must be implemented. All work is coordinated with the designer, Ben Kopietz (benjamin.o.kopietz.nfg@mail.mil), and project inspector, Adam Pohl (adam.j.pohl3.nfg@mail.mil), with electronic payment applications required in PDF format.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Drawings 21177.pdf | ||
| 26A8415020 Replace Boiler Addendum #1 signed.pdf | ||
| Replace Boiler Prebid Sign-in_w signatures.pdf | ||
| Advertisement 21177.pdf | ||
| Specs 21117.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MANDATORY PRE-BID MEETING MINUTES for Replace Boiler Dowagiac Armory – Dowagiac, MI DMVA Project No. 26A8515020 Index No. 1350 DTMB Project No. 511/21177.AGY
Meeting Date: Wednesday August 25th, 2021 at 11:00 AM on site
Introductions: Ben Kopietz – Project Manager/Designer, Adam Pohl - Project Inspector, SFC Andrew Rench - Armory Manager, Armory Maintenance Mechanic interviews currently ongoing
Design POC is Ben Kopietz, benjamin.o.kopietz.nfg@mail.mil
Project inspection POC is Adam Pohl, adam.j.pohl3.nfg@mail.mil Contractor to coordinate all work with Adam.
Today is the only site visit for bidding purposes. Bidders must sign the mandatory pre bid sign in sheet or the bids will not be accepted by DTMB.
Dates:
Bidding RFI’s accepted until: September 1st, 2021 at 10:00am Local Time Bid Addendums posted NLT: COB September 3rd, 2021
An addendum will be issued proceeding this date with all RFI’s submitted including response and any project changes.
Bid Opening: September 8th, 2021 @ 2:00pm local time
Follow Section 00100 Instructions to Bidders carefully for instructions on submitting bids.
Bidding will be electronic. Bidding documents located on the following site: www.michigan.gov click on the Go to SIGMA VSS website https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
Payment Applications: Electronic Pay Apps are required; PDF format.
Prevailing wages do apply to this project. Refer to specifications.
There are no Alternates for this project.
There is a $10,000 Contingency Allowance for this project.
Bid Security (bond) of 5% of awarded base bid cost is required
If bid is less than $50,000 no payment and performance bonds are required.
Pre award submittals: Sections 232223.11 Boiler Feed System, 235239 Fire-Tube Boilers will be requested for this project.
Project completion date is 120 calendar days after preconstruction meeting. DTMB is typically taking 45 days to award contracts after receipt of the bids. Preconstruction meeting will take mailto:benjamin.o.kopietz.nfg@mail.mil mailto:adam.j.pohl3.nfg@mail.
http://www.michigan.gov/ https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService place on site. Notice To Proceed will be given at the Preconstruction Meeting and hence, 120 Days will begin. No work is to begin until the written notice is given to the General Contractor.
There are liquidated damages for this project at $200/day.
Permits- Boiler, Mechanical & Electrical. Must meet all Michigan codes
Hour of work at particular location – 8:00AM to 4:00PM. Contractor to have full time superintendent/project manager to remain on site while construction work is being performed.
Site access concerns: Comply with all special working rules listed in the specifications.
All deliveries will need to be coordinated with security and handled by the contractor.
Contractor must submit shop drawings prior to construction scope of work. No work shall commence until adequate amount of approved shop drawings have been issued by designer.
All work is to be per the contract documents. No changes to the contract to be made unless approved by DMVA.
Contractor to track all changes on As-Built drawings.
There must be a construction waste management and disposal plan in place for this project, see section 017419. Forms are provided in specifications. Documents are to be submitted with quantities and weights. Goal is to salvage/recycle 60 percent by weight of total non-hazardous solid waste generated by the work.
Site walk thru
END