This document is a Repair Qualification Requirements document for an Antenna Mast (NSN: 5985015985631, P/N: 200425515) used in the AN/TSQ-T10 (JTE) application. The document outlines comprehensive qualification requirements for potential repair sources, including mandatory steps such as notifying the government Small Business Office, certifying facilities and testing capabilities, verifying technical data packages, and demonstrating repair process compliance. Potential offerors must prepare and submit a qualification test plan to 415 SCMS/GUEA for approval, covering performance, environmental, mechanical, and quality assurance requirements.

The document also provides six Source Qualification Waiver Criteria (QWC) that may allow sources to apply for partial or full waiver of qualification requirements. These waivers can be granted based on factors such as previous government supply history, qualification on similar or related items, and organizational changes. While approval does not guarantee a contract award, successful qualification will list the offeror as an approved repair source. The estimated qualification time is 30 days, with no associated testing and evaluation costs, and the qualification process is designed to ensure that potential repair sources meet stringent technical and quality standards for the Antenna Mast.

View the file

Other files

File Type Posted
Attachment_7_RDL.pdf PDF
Attachment_8_IUID.pdf PDF
Attachment_1_CAVAF.docx DOCX document
Attachment_6_PWS.docx DOCX document
FA8250-26-Q-0038.pdf PDF
Attachment_3_Packaging_Requirements.pdf PDF
Attachment_5_SPI.pdf PDF
Attachment_4_Packaging_SOW.pdf PDF
Attachment_9_CDRLS.pdf PDF
Attachment_2_Item_Description.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPAIR QUALIFICATION REQUIREMENTS

NSN: 5985015985631

P/N: 200425515 Noun: Antenna Mast Application: AN/TSQ-T10 (JTE)

6 Jun 2023 Section C 1/3

SECTION C:

1. QUALIFICATION REQUIREMENTS THAT MUST BE SATISFIED TO BECOME A QUALIFIED SOURCE

a. Prequalification Notice: The offeror shall notify the appropriate government Small Business Office or, if responding to a solicitation, the contracting officer in the appropriate government contracting office, of intent to qualify as a source for this Antenna Mast.

b. Facilities, Testing, and Inspection Capabilities: The offeror must certify to the government that they have, or have access to, the required facilities and equipment to repair, inspect, test, package, and store the item. The offeror shall make their facilities, equipment, tooling, and personnel available for evaluation and inspection by the government.

c. Data Verification: The offeror must verify that they have a complete data package. This verification must include a complete list of all procedures, drawings, and specifications, including change notices, in the offeror’s possession including, at a minimum Ogden Air Logistics Center (98747) drawing 200425523. The offeror may also be required to produce copies of all applicable procedures, drawings, or specifications.

d. Repair Process Verification: The offeror must repair this item to conform to the government requirements as prescribed within the ESA-approved engineering/technical data package. The offeror must show compliance with Unique Identification (UID) requirements in accordance with DFARS 211.274 as prescribed within the ESA-approved engineering/technical data package. The offeror must provide, at their own expense, data showing the results of all quality, performance, and environmental evaluations conducted by the offeror to show compliance with the government requirements as prescribed by 415 SCMS/GUEA. The offeror shall also identify its sources for materials and its standards for internally used processes.

e. Test and Evaluation and/or Verification: The offeror, at their own expense, shall prepare and submit to 415 SCMS/GUEA for their prior approval, a qualification test plan/procedure detailing how they intend to verify compliance with all performance, environmental, mechanical, and quality assurance requirements identified by Drawing 200425523.

f. Qualification Requirement Cost Estimate: Estimated likely costs for testing and evaluation, which will be incurred by the potential offering party to become qualified are $0.00.

g. Qualification Time Completion Estimate: It is the estimate of the engineering support activity that completion of this qualification effort should require 30 days. This is based on complexity of the Antenna Mast and other factors.

h. Qualification Time Limitation: An offeror may not be denied the opportunity to submit and have considered an offer for a contract if the offeror can demonstrate to the satisfaction of the contracting officer that the offeror (or its product) meets these standards for qualification or can meet them before the date specified for award of the contract. The award will not be delayed

P/N: 200425515

6 Jun 2023 Section C 2/3 to provide the vendor with an opportunity to demonstrate its ability to meet the standards specified in this qualification requirement.

i. Evaluation of Proposals Not Previously Qualified: The offeror must be fully qualified in order to be eligible for a contract award. Therefore, the offeror must fulfill all of the requirements stated, in writing, in the qualification requirement before the date specified for award of the contract. Once all requirements are met, the offeror will be listed as an approved repair source for this item. Approval, however, does not guarantee subsequent contract award.

P/N: 200425515

6 Jun 2023 Section C 3/3

2. SOURCE QUALIFICATION WAIVER REQUIREMENTS

Sources who meet any of the following Source Qualification Waiver Criteria (QWC) may apply for a waiver of all or part of the qualification requirements. If a waiver is granted and the offeror is awarded a contract, the offeror may still be required to provide a post-contract award first article exhibit to verify production capability:

a. QWC1: The potential source submits written certification that the articles have been supplied to the government or original equipment manufacturer (e.g., DD Form 250, Material Inspection and Receiving Report, Purchase Order invoice, etc).

b. QWC2: The potential source is qualified on the right-hand article and requests to be qualified on the left-hand article. If the right-and left-hand articles are mirror images of each other, then approval can generally be given.

c. QWC3: A source qualified to provide an assembly is usually qualified to provide subassemblies, major components, and items of that assembly.

d. QWC4: A source qualified to provide earlier dash numbers of a basic P/N may be qualified to provide other dash numbers of that same basic P/N, provided there is no increase in complexity, criticality, or other relevant requirements.

e. QWC5: A source qualified to provide a similar or like item can be qualified to provide the required item. However, for approval, the engineering authority must verify that there is no increase in complexity, criticality, or other requirements over that of the similar item. At a minimum, the source shall provide a complete set of drawings for the similar item and written proof, such as purchase orders, shipping documents, etc., to show that the similar item was provided to the original equipment manufacturer or DoD.

f. QWC6: A source previously qualified to provide an item, but which has been purchased, sold, merged, absorbed, reformed, split, etc., may qualify if it can be established that the qualification is currently with the requester and that the requester has the same or equivalent facilities, tooling, equipment, personnel, and utilizes the original forging, castings, etc., in the repair process.