RENOVATE UTILITIES BUILDING 13_Drawing.pdf
PDF 43 MB Posted
- Solicitation number
- 36C24224B0029
About this file
This document is a Statement of Work (SOW) for a federal contract opportunity to renovate the Utilities Building 13 at the Northport VA Medical Center in New York.
The key details are:
- The project involves renovations to the existing Laundry Facility in Building 13 to support the installation of new laundry equipment provided by the VA. Work includes general construction, HVAC, plumbing, fire protection, and electrical upgrades.
- The contract completion time is 365 calendar days from the Notice to Proceed.
- The contractor must utilize the VISN 2 Autodesk Build Construction management platform for project communications, submittals, and collaboration at no additional cost.
- The contractor must complete required training on the Autodesk platform within 12 calendar days of contract award.
- The Department of Veterans Affairs Northport Medical Center is the procuring agency, and there are records management and information security requirements outlined.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
S.G. S.M.
NORTHPORT VAMC
RENOVATE UTILITIES - BUILDING 13
PROJECT NO. 632-23-109
DEPARTMENT OF
VETERANS AFFAIRS
PROJECT COVER SHEET & NOTES
DRAWINGS INDEX
DRAWING TITLE
G-01 PROJECT COVER SHEET & NOTES
A-01 ARCHITECTURAL NOTES & SYMBOLS
A-02 ARCHITECTURAL DEMOLITION FLOOR PLAN
A-03 ARCHITECTURAL INSTALLATION FLOOR PLAN
A-04 REFLECTED CEILING FLOOR PLAN
A-05 ARCHITECTURAL DETAILS 1 OF 2
A-06 ARCHITECTURAL DETAILS 2 OF 2
E-01 ELECTRICAL DRAWINGS (NOT INCLUDED)
FP-01 FIRE PROTECTION NOTES, SYMBOLS & RISER DIAGRAM
FP-02 FIRE PROTECTION DEMOLITION & INSTALLATION FLOOR PLAN
M-01 HVAC NOTES & SYMBOLS
M-02 HVAC DEMOLITION FLOOR PLAN
M-03 HVAC INSTALLATION FLOOR PLAN
M-04 HVAC SCHEDULES
M-05 HVAC DETAILS
M-06 HVAC DETAILS & CONTROLS 1 OF 2
M-07 HVAC DETAILS & CONTROLS 2 OF 2
M-08 HVAC SEISMIC DETAILS 1 OF 2
M-09 HVAC SEISMIC DETAILS 2 OF 2
P-01 PLUMBING NOTES & SYMBOLS
P-02 PLUMBING BASEMENT DEMOLITION & INSTALLATION FLOOR PLANS
P-03 PLUMBING DEMOLITION & INSTALLATION FLOOR PLANS
P-04 PLUMBING RISER
Q-01 WASHER SPECIFICATIONS
Q-02 WASHER SPECIFICATION SHEETS
Q-03 DRYER SPECIFICATIONS
Q-04 DRYER SPECIFICATION SHEETS
S-01 STRUCTURAL NOTES
S-02 STRUCTURAL BASEMENT FLOOR PLAN
S-03 STRUCTURAL FLOOR PLAN
S-04 STRUCTURAL ROOF PLAN
S-05 CONCRETE DETAILS 1 OF 2
S-06 CONCRETE DETAILS 2 OF 2
W E
SN
4O
0 25
SITE OF WORK
LOCATION MAP
N.T.S.
APPLICABLE STANDARDS AND CODES:
VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL
CAD STANDARD APPLICATION GUIDE, AND
OTHER GUIDANCE ON THE TECHNICAL INFORMATION LIBRARY (TIL)
(HTTP://WWW.CFM.VA.GOV/TIL/).
2021 INTERNATIONAL BUILDING CODE (IBC) (ONLY WHEN SPECIFICALLY
REFERENCED IN VA DESIGN DOCUMENTS, SEE
NOTES BELOW)
2021 NFPA 101 LIFE SAFETY CODE
2021 NFPA 90A STANDARDS FOR THE INSTALLATION OF AIR-CONDITIONING
AND VENTILATING SYSTEMS
2021 NFPA 96 STANDARDS FOR VENTILATION CONTROL AND FIRE PROTECTION
OF COMMERCIAL COOKING OPERATIONS
2019 NFPA 241 STANDARD FOR SAFEGUARDING CONSTRUCTION, ALTERATION,
AND DEMOLITION OPERATIONS
2018 NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA 5000 AND
NFPA 900
OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS
2019 VA SEISMIC DESIGN REQUIREMENTS, H-18-8
2020 NATIONAL ELECTRICAL CODE (NEC) (NFPA 70)
2018 INTERNATIONAL PLUMBING CODE (IPC)
2015 ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS)
INCLUDING VA SUPPLEMENT, BARRIER FREE
DESIGN GUIDE (PG-18-13)
ENERGY POLICY ACT OF 2005 (EPACT)
EXECUTIVE ORDER 13514: FEDERAL LEADERSHIP IN ENVIRONMENTAL,
ENERGY, AND ECONOMIC PERFORMANCE.
ENERGY STANDARD FOR BUILDINGS EXCEPT LOW-RISE RESIDENTIAL
BUILDINGS - ASHRAE STANDARD 90.1- 2016.
UNLESS OTHERWISE SPECIFIED, SPECIFIC REFERENCES TO CODES,
REGULATIONS, STANDARDS,
MANUFACTURERS' INSTRUCTIONS, OR REQUIREMENTS OF REGULATORY
AGENCIES, SHALL MEAN
THE LATEST EDITION OF EACH IN EFFECT AT THE DATE OF PROJECT
SUBMISSION (U.N.O.)
G-01
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
632-23-109RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
DEMOLITION NOTES:
1. CONTRACTOR SHALL COORDINATE WITH OWNER ITEMS TO BE
STORED ON SITE FOR RE-USE AND ITEMS NOT HAVING ANY
VALUE TO OWNER TO BE LEGALLY DISPOSED OFF SITE.
2. SEE MECHANICAL, ELECTRICAL, PLUMBING AND STRUCTURAL
DRAWINGS FOR ADDITIONAL NOTES AND SCOPE OF WORK FOR
APPROPRIATE TRADES.
3. CONTRACTOR SHALL FURNISH AND INSTALL TEMPORARY (DUST
TIGHT) BARRIERS AND PROTECTIVE FLOOR COVERING SO TO
PROTECT EXISTING FLOORS, WALLS, CEILINGS AND OWNERS
EQUIPMENT. BARRIERS SHALL NOT BE REMOVED UNTIL
COMPLETION OF PROJECT OR AS AGREED UPON BY OWNER.
SEE TEMPORARY PROTECTION NOTES ON THIS SHEET.
4. CONTRACTOR SHALL PROTECT EXISTING FACILITIES AS
REQUIRED DURING DEMOLITION. DEMOLITION CONTRACTOR
SHALL REPLACE AT HIS COST ANY DAMAGE INCURRED DURING
DEMOLITION TO ANY EXISTING BUILDING COMPONENTS, WHICH
ARE TO REMAIN.
5. CONTRACTOR SHALL TEMPORARILY SUPPORT ELECTRICAL
CONDUITS, PIPING, DUCTWORK AND OTHER SERVICES AND
EQUIPMENT AFFECTED BY DEMOLITION WHICH ARE TO REMAIN.
6. ALL EXTERIOR WALL AND ROOF OPENINGS NO LONGER
REQUIRED DUE TO DEMOLITION WORK SHALL BE SEALED
WATERTIGHT AND WEATHER TIGHT. CONTRACTOR TO CLEARLY
MARK AND ERECT BARRIERS FOR ANY POTENTIALLY
HAZARDOUS CONDITIONS.
7. ALL WORK SHALL CONFORM TO ALL OSHA REGULATIONS.
8. ALL DEMOLITION AREAS SHALL BE CLEARLY MARKED WITH
SIGNAGE AND PHYSICAL BARRIER. AS PER OSHA AND OWNERS
REQUIREMENTS TO INSURE SAFETY TO OWNERS PERSONNEL
THROUGHOUT DEMOLITION PHASE OF WORK.
9. CONTRACTOR SHALL FURNISH AND INSTALL TEMPORARY
CLOSURES FOR ALL FLOOR OPENING DUE TO PIPE AND
DUCTWORK REMOVALS. DEMOLITION CONTRACTOR SHALL
FURNISH AND INSTALL TEMPORARY BARRIERS AT FLOOR
OPENINGS AS PER OSHA AND ALL GOVERNING AUTHORITIES.
10. CONTRACTOR SHALL COORDINATE TEMPORARY STORAGE AND
LAYDOWN LOCATIONS WITH VA. DEMOLITION CONTRACTOR
SHALL FURNISH AND PAY FOR ALL DUMPSTER AND DEBRIS
REMOVAL.
11. CONTRACTOR SHALL COORDINATE WITH ALL OTHER TRADES
FOR REQUIRED DEMOLITION WORK INCLUDING PROVISIONS FOR
REQUIRED FLOOR WALL AND ROOF OPENINGS TO
ACCOMMODATE NEW WORK
12. WHERE SUSPECTED HAZARDOUS MATERIAL IS ENCOUNTERED
CONTRACTOR SHALL NOTIFY VA WHO WILL HAVE MATERIAL
TESTED AND LEGALLY REMOVED. VA WILL BE RESPONSIBLE
FOR REMOVAL OF HAZARDOUS MATERIAL IN PROJECT AREA.
13. CONTRACTOR SHALL REMOVE ALL WALLS, DOORS, DOOR
FRAMES, LOUVERS, WINDOWS, ETC. AS INDICATED ON
DRAWINGS.
14. CONTRACTOR SHALL REMOVE ALL CONCRETE BLOCK,
TERRACOTTA BLOCK AND DRYWALL PARTITIONS AS INDICATED
ON DRAWINGS.
15. CONTRACTOR SHALL REMOVE ALL SUPPORTS AND HANGERS
NO LONGER REQUIRED DUE TO DUCTWORK AND PIPING
REMOVALS. ALL HANGERS FOR HUNG CEILING SHALL BE
REMOVED.
16. ELECTRICAL DISCONNECTIONS AND PANEL RELOCATIONS
SHALL BE PERFORMED BY LICENSED CONTRACTOR AND
COORDINATED BY DEMOLITION CONTRACTOR.
17. CAPPING OF ALL PIPING SERVICES AND DISCONNECTIONS
SHALL BE PERFORMED BY LICENSED PLUMBING CONTRACTOR
AND COORDINATED BY DEMOLITION CONTRACTOR.
18. CONTRACTOR SHALL FURNISH TEMPORARY LIGHTING AS
REQUIRED IN ALL AREAS WHERE WORK IS BEING DONE.
19. ALL EXISTING FLOOR DRAINS IN AREA OF WORK DESIGNATED
TO REMAIN SHALL BE TEMPORARILY SEALED TO KEEP ALL
DEBRIS FROM ENTERING TRAP.
20. NO EQUIPMENT, HVAC UNITS, SERVICE MAIN, ELECTRICAL
PANELS AND SERVICES SHALL BE DISCONNECTED OR SHUT
DOWN WITHOUT PRIOR REVIEW WITH THE VA TO CONFIRM THAT
AREAS TO REMAIN IN OPERATION WILL NOT BE AFFECTED.
21. WHERE AN AREA WILL BE AFFECTED BY A SHUTDOWN,
REMOVAL OR A DISCONNECTION, CONTRACTOR SHALL FURNISH
2 WEEKS ADVANCE NOTICE GIVEN TO THE VA REGARDING THE
PROPOSED SHUTDOWN, AND DURATION OF THE SHUTDOWN.
VA WILL REVIEW THE PROPOSED SHUTDOWN AND PROVIDE
INSTRUCTION.
22. EACH CONTRACTOR SHALL COORDINATE WITH ALL OTHER
TRADES FOR REQUIRED DEMOLITION WORK INCLUDING
PROVISIONS FOR NEEDED FLOOR AND WALL OPENINGS TO
ACCOMMODATE NEW WORK.
23. SPRINKLER PIPING SHALL BE TAKEN OUT OF SERVICE SECTION
BY SECTION, TO THE EXTENT PRACTICAL, AND CAPPED AS
DEMOLITION PROGRESSES. THE BUILDING SPRINKLER SYSTEM
SHALL BE RESTORED TO FULL OPERATING CONDITION AT THE
END OF EACH WORK DAY. COORDINATE WORK SCOPE WITH
FIRE PROTECTION DOCUMENTS.
24. THE STORAGE OF COMBUSTIBLE MATERIALS SHALL NOT BE
PERMITTED IN ANY AREA WHERE THE SPRINKLER SYSTEM HAS
BEEN TEMPORARILY SHUTDOWN.
25. WHERE NEW FLOOR FINISH ARE REQUIRED, CONCRETE SLAB
SHALL BE PREPARED AS PER MANUFACTURER'S
RECOMMENDATIONS FOR INSTALLATION OF NEW FLOOR
FINISHES.
26. WITHIN THE AREA OF WORK DEFINED BY THE DEMOLITION PLAN,
THE SURFACE OF THE EXISTING CONCRETE SLAB SHALL BE
FLASH PATCHED TO FILL IN ALL FASTENER HOLES, CHIPS AND
POCKETS CREATED BY DEMOLITION WORK AND AS NEEDED TO
PROVIDE A SMOOTH FLAT SURFACE READY TO RECEIVE NEW
CONSTRUCTION.
632-23-109
S.G. S.M.
A-01
ARCHITECTURAL NOTES & SYMBOLS
GENERAL PROTECTION NOTES:
1. CONTRACTOR SHALL FURNISH AND INSTALL TEMPORARY (DUST
TIGHT) BARRIERS. CONTRACTOR SHALL MAINTAIN THE WORK
AREA UNDER NEGATIVE PRESSURE IN RELATION TO THE
SURROUNDING AMBIENT SPACE. CONTRACTOR SHALL
FURNISHED, TEMPORARY SMOKE EATERS SHALL BE USED WITH
A MINIMUM EXHAUST CAPACITY OF .06 CFM/ SQ. FT. OF WORK
AREA. ALL OPENINGS SHALL BE PROTECTED WITH BARRIERS
BETWEEN CONSTRUCTION AND ADJACENT SPACES.
CONTRACTOR SHALL COORDINATE WITH THE OWNER ON THE
EXACT PLACEMENT OF TEMPORARY PARTITIONS, SO AS NOT TO
IMPEDE OR INTERFERE WITH FACILITY OPERATIONS.
TEMPORARY BARRIER/PARTITION SYSTEM SHALL BE AS
MANUFACTURED BY “ZIPWALL” OR AN OWNER APPROVED EQUAL.
2. CONTRACTOR SHALL PROTECT EXISTING BUILDING
COMPONENTS, EQUIPMENT AND FURNISHINGS TO REMAIN
WITHIN THE PROJECT AREAS. ANY DAMAGE TO EXISTING TO
REMAIN BUILDING COMPONENTS, EQUIPMENT AND FURNISHINGS
SHALL BE PROMPTLY CORRECTED BY THE CONTACTOR AT NO
ADDITIONAL COST TO OWNER. IF DAMAGES CANNOT BE
RECTIFIED, CONTRACTOR SHALL REPLACE THE DAMAGED ITEM IN
KIND AT NO ADDITIONAL COST TO OWNER. CONTRACTOR SHALL
DO EITHER OF THE FOLLOWING TO PROVIDE PROTECTION:
A. CONTRACTOR SHALL TEMPORARILY REMOVE/RELOCATE
EXISTING BUILDING COMPONENTS, EQUIPMENT AND
FURNISHINGS AS REQUIRED. ALL REMOVALS/RELOCATIONS
SHALL BE COORDINATED WITH THE OWNER FOR WHAT CAN AND
CANNOT BE REMOVED/RELOCATED AND WHERE THEY CAN BE
PLACED.
B. CONTRACTOR SHALL FURNISH AND INSTALL TEMPORARY
PROTECTIVE COVERINGS FOR EXISTING BUILDING COMPONENTS,
EQUIPMENT AND FURNISHINGS WHICH SHALL REMAIN.
TEMPORARY PROTECTION SHALL BE MAINTAINED CONSISTENTLY
THROUGHOUT THE DEMOLITION AND CONSTRUCTION OF EACH
OF THE AREAS AND NOT REMOVED UNTIL AREA HAS BEEN
APPROVED BY THE OWNER. TEMPORARY PROTECTION SHALL
EXTEND BEYOND THE PROJECT AREA AS REQUIRED TO PROTECT
AGAINST DEMOLITION AND CONSTRUCTION ACTIVITIES.
TEMPORARY PROTECTIVE COVERINGS SHALL INCLUDE BUT NOT
BE LIMITED TO THE FOLLOWING:
1. FLOORS: CONTRACTOR SHALL PROTECT THE EXISTING FLOORS
TO REMAIN. PROTECTION SHALL PROTECT FLOOR FINISH AND
SUBSTRATE FROM ANY DAMAGE, SCUFFS, DIRT, ETC.
2. WALLS AND BASE: EXISTING WALLS AND BASE TO REMAIN SHALL
BE PROTECTED FROM DAMAGE, SCUFFS, DIRT, ETC.
3. WALL MOUNTED COMPONENTS: CONTRACTOR SHALL
COORDINATE WITH OWNER FOR WALL MOUNTED COMPONENTS
THAT SHALL BE MOVED/RELOCATED. ALL OTHER COMPONENTS
TO REMAIN SHALL BE FURNISHED WITH A PROTECTIVE COVERING
AS REQUIRED TO PROTECT FROM DAMAGE, SCUFFS, DIRT, ETC.
GENERAL PROJECT REQUIREMENTS:
1. THE INTENT OF THESE DRAWINGS AND SPECIFICATIONS IS FOR
CONTRACTORS IN ALL TRADES TO FURNISH A COMPLETE PROJECT TO
THE VA. CONTRACTOR SHALL FURNISH ALL LABOR, SUPERVISION,
MATERIALS, AND EQUIPMENT NECESSARY TO COMPLETE ALL
DEMOLITION AND NEW WORK SHOWN IN THE PROJECT DOCUMENTS.
2. CONTRACTOR SHALL COORDINATE WITH THE VA FOR THE FOLLOWING
BEFORE STARTING WORK: BUILDING ACCESS, RULES AND
REGULATIONS, REMOVALS, DUMPSTER REQUIREMENTS, SAFETY,
DAILY CLEANUP AND REMOVALS, MATERIAL MOVEMENT THROUGH
THE GROUNDS AND FACILITY, STORAGE OF MATERIALS AND TIE-INS
TO EXISTING SERVICES.
3. CONTRACTOR IS RESPONSIBLE FOR ALL REALLOCATIONS OF
EXISTING SERVICES THAT ARE TO REMAIN, AND WHICH INTERFERE
WITH NEW WORK.
4. ROOMS AND CORRIDORS ADJACENT TO THE PROJECT AREA SHALL
REMAIN IN USE BY THE VA DURING DEMOLITION AND CONSTRUCTION
WORK ASSOCIATED WITH THE PROJECT. CONTRACTOR SHALL
MAINTAIN ALL SERVICES TO THESE OCCUPIED AREAS AND NOT
INTERFERE WITH ON-GOING OPERATIONS. WHERE NEW SERVICE
MAINS ARE TO BE INSTALLED, CONTRACTOR SHALL SCHEDULE TIE-INS
TO ACTIVE AREAS WITH THE PROJECT COR. SCHEDULED TIE-INS
SHALL BE SCHEDULED DURING AREA SHUTDOWNS.
5. ALL CONTRACTORS ARE RESPONSIBLE TO VERIFY ALL SITE, FIELD
AND BUILDING CONDITIONS PRIOR TO SUBMITTING BIDS AND
COMMENCING WORK. IF THERE ARE ANY DISCREPANCIES BETWEEN
DRAWINGS AND FIELD CONDITIONS, CONTRACTOR SHALL SUBMIT A
REQUEST FOR INFORMATION TO THE VA FOR A RESOLUTION.
6. ALL DIMENSIONS ON THE DRAWINGS ARE TO BE FIELD VERIFIED AND
COORDINATED BY THE CONTRACTOR. CONTRACTOR SHALL SUBMIT
ELECTRONIC COPIES OF EACH SHOP DRAWING FOR REVIEW.
7. CONTRACTOR SHALL MAINTAIN AT THE SITE ONE (1) RECORD COPY
OF ALL CONTRACT DRAWINGS AND SPECIFICATIONS, ADDENDA,
CHANGE ORDERS, SHOP DRAWINGS, PRODUCT DATA, SAMPLES,
OPERATION AND MAINTENANCE DATA AND OTHER MODIFICATIONS IN
GOOD ORDER, MARKED CURRENTLY TO RECORD ALL CHANGES MADE
DURING CONSTRUCTION. THESE SHALL BE DELIVERED TO THE VA
PRIOR TO THE END OF THE WORK. UPON COMPLETION OF THE WORK
CONTRACTOR SHALL DELIVER TO THE PROJECT COR AN ELECTRONIC
COPY OF THE FOLLOWING:
a. “AS BUILT” RECORD DRAWINGS.
b. ALL CONTRACT AND SHOP DRAWINGS.
c. APPROVED PRODUCT DATA AND OPERATION AND MAINTENANCE
DATA.
ALL DOCUMENTS SHALL BE CLEARLY LEGIBLE.
8. ALL EXISTS FROM THE BUILDING SHALL ALWAYS REMAIN
UNOBSTRUCTED AND OPERABLE.
9. EXISTING SPRINKLER AND ALARM SYSTEMS SHALL REMAIN OPERABLE
AT ALL TIMES. CONTRACTOR SHALL COORDINATE WITH THE VA ANY
SHUTDOWNS OF THE SPRINKLER OR ALARM SYSTEMS.
10. SHUTDOWNS OF MECHANICAL, PLUMBING, OR ELECTRICAL SYSTEMS
SHALL BE COORDINATED WITH THE VA.
11. CONTRACTOR SHALL FURNISH, INSTALL, AND MAINTAIN ALL SAFETY
BARRICADES TO PROTECT FLOOR AND WALL OPENINGS AS REQUIRED
TO PROTECT ALL PERSONNEL WORKING ON SITE.
12. ALL CONSTRUCTION PERSONNEL SHALL BE RESTRICTED TO THE
AREA OF THE FACILITY UNDER CONSTRUCTION. ALL OTHER AREAS
OF THE FACILITY SHALL DEEMED OFF-LIMITS.
13. CONTRACTORS' PERSONNEL AND MATERIAL ENTRANCE SHALL BE
APPROVED IN ADVANCE BY VA.
14. CONTRACTOR SHALL OBTAIN APPROVAL FROM THE VA FOR ALL
TEMPORARY ELECTRICAL POWER TIE-INS, WATER HOOKUPS AND
MATERIAL STORAGE REQUIRED FOR THEIR WORK. CONTRACTOR
SHALL MAKE ALL NECESSARY ARRANGEMENTS FOR THEIR
SUBCONTRACTORS.
15. CONTRACTOR SHALL DURING THE PROJECT, MAINTAIN ALL
WORKING AREAS INCLUDING MATERIAL HANDLING, STAGING AREAS,
ENTRIES, EXITS, FIELD OFFICE, AND TOOLBOX AREAS FREE FROM
RUBBISH AND DEBRIS. RUBBISH AND DEBRIS SHALL BE REMOVED
FROM THE PREMISES DAILY. ALL AREAS SHALL BE KEPT BROOM
CLEAN. EACH CONTRACTOR SHALL BE RESPONSIBLE TO CLEAN ANY
DIRT/DUST THAT DEMOLITION AND CONSTRUCTION WORK CAUSES IN
OTHER AREAS OF THE FACILITY. AT THE COMPLETION OF THE
PROJECT, ALL SURFACES SHALL BE LEFT CLEAN AND UNDAMAGED.
16. ANY DAMAGE DONE TO THE EXISTING BUILDING COMPONENTS OR
VA OWNED EQUIPMENT DURING DEMOLITION AND/OR CONSTRUCTION
SHALL BE REPLACED OR REPAIRED TO ORIGINAL CONDITION BY THE
CONTRACTOR AT NO ADDITIONAL COST TO THE OWNER.
CONTRACTOR SHALL MATCH MATERIALS/FINISHES IN ALL AREAS
AFFECTED BY THE WORK.
17. CONTRACTOR SHALL OBTAIN AND PAY FOR ALL REQUIRED
INSPECTIONS.
18. THE CONTRACTOR SHALL COORDINATE WITH THE VA THE LOCATION
OF ANY TRAILERS, STAGING AREAS, AND THE LOCATION OF ANY
EQUIPMENT INCLUDING CRANES TO BE USED ON SITE.
19. CONTRACTOR SHALL PROVIDE TEMPORARY TOILET FACILITIES FOR
ALL CONSTRUCTION PERSONNEL. THE LOCATION OF THE FACILITIES
SHALL BE COORDINATED WITH THE COR.
20. CONTRACTOR SHALL COORDINATE THE INSTALLATION OF ALL VA
FURNISHED EQUIPMENT. CONTRACTOR SHALL OBTAIN ALL
REQUIREMENTS FOR INSTALLATION INCLUDING ROUGHING
DIAGRAMS, INSTALLATION INSTRUCTIONS, ELECTRICAL SCHEMATICS,
TEMPLATES, LAYOUTS, DIMENSIONS, AND ALL OTHER INFORMATION
NECESSARY FOR A WELL-COORDINATED INSTALLATION.
21. ALL WORK SHALL BE GUARANTEED, INCLUDING LABOR AND
MATERIALS FOR A PERIOD OF ONE YEAR AFTER FINAL COMPLETION
AND ACCEPTANCE BY THE VA.
CONTRACT LIMIT LINE
DEMOLITION LINE
ELEVATION INDICATOR
CENTER LINE INDICATOR
EXISTING TO REMAIN LINE
FEATURES ABOVE LINE INDICATOR
HIDDEN FEATURES LINE
NEW LINE
PROPERTY LINE
SMOKE BARRIER LINE
BREAK, ROUND (USER DEFINES SIZE)
BREAK, STRAIGHT (SEE SECTION INDICATORS,
BUILDING, WITH BREAK STANDARDS)
DETAIL INDICATOR
DETAIL INDICATOR
DETAIL INDICATOR FOR SMALL CONDITIONS
DIMENSION LINE
DOOR OPENING/BORROWED LIGHT IDENTIFIER
DRAWING BLOCK TITLE, TYPICAL
ELEVATION INDICATOR, EXTERIOR
ELEVATION INDICATOR, INTERIOR, MULTIPLE VIEW
ELEVATION INDICATOR, INTERIOR, SINGLE VIEW
ARCHITECTURAL SYMBOLS
CENTER LINE
FURNITURE, FIXTURE, & EQUIPMENT INDICATOR
DRAWING BLOCK TITLE
1 1/2" = 1'-0"C4
A-201 A4
A2 A-202
A
BC
D
A-202 A2
A-201 A4
A-512 D2
A-512 D2
A-512 D2
AA
COLUMN GRID
KEYNOTE
WALL OR PARTITION TYPE
NORTH ARROW
NORTH
V V ITEM - VA SUPPLIED & INSTALLED
VC ITEM - VA SUPPLIED & CONTRACTOR INSTALLED
CC ITEM - CONTRACTOR SUPPLIED & INSTALLED
A4 A-201
DETAIL NUMBER
SHEET WHERE REF.
SHEET WHERE DRAWN
A3.1 A4.3
BUILDING SECTION INDICATOR
DETAIL INDICATOR
A
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text S
CLEAN SIDE
DRYER ROOM
SOILED LINENS
WASH ROOM
MECH. ROOM
LOCKER ROOM
RESTROOM
PLANT MANAGER
LINEN DISTRIBUTION AREA
LOADING DOCK
3 4 5 6 7 8 9 10 11
A
B
C
DN
UP
AIR HANDLER
CHILLER
9' -9
16'-0"
19'-1"
6' -4
10'-4"
6' -0
3' -7
5' -0
5'
-0
5'-2" 5'-4 1/4" 5'-2"
4' -0
7' -5
'-5
'-5
'-5
'-5
'-5
'-1
1"
16'-8"
2'-0" 2'-0"
'-4
2'-3" 6'-0"
2' -2
2'-2"
2'-10"
2' -1
0"
3'-3 1/2"
3' -1
3' -9
16'-1 1/4"
4' -0
/4
9'
-9
(TYP)
4'-1 3/4" 8'-4"
12'-0" 3'-6 1/4"
6' -0
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 6WF15EXIST. 6WF15EXIST. 6WF15EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 8WF17 EXIST. 8WF17 EXIST. 8WF17 EXIST. 8WF17
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
2L S x
1/ x
5/
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
3 4 5 6 7 8 9 10 11
A
B
C
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
4'-10 1/2"
5'-6 1/4" 7'-11 1/4" 4'-0 3/4"
7' -2
/2
3'-3 1/2"
7' -1
/2
5' -7
/2
1'-10"
8'-1 1/2" 6'
-1
/2
2' -7
/2
2' -7
/2
7' -1
/2
S.G. S.M.
N N
ARCHITECTURAL DEMOLITION
FLOOR PLAN
A-02
DEMOLITION FLOOR PLAN - PARTIAL BUILDING 13
3/16"= 1'-0"
DEMOLITION ROOF PLAN - PARTIAL BUILDING 13
1/8"= 1'-0"
DEMOLITION KEYED NOTES:
1. REMOVE EXISTING GYPSUM BOARD AND WALL FRAMING IN ITS ENTIRETY TO PREPARE AREA FOR
NEW INSTALLATIONS. REMOVAL SHALL INCLUDE BUT NOT BE LIMITED TO; THE PLYWOOD
WAINSCOT, WALL MOUNTED ELECTRICAL SERVICES, CONDUITS, AND WIRES, PLUMBING SERVICES, SOAP DISPENSER EQUIPMENT, ETC. FROM EACH SIDE OF THE WALL. COORDINATE REMOVALS WITH
MEP DRAWINGS.
2. REMOVE EXISTING GRATING FROM THE TRENCH DRAINS. COORDINATE WITH THE DEMOLITION
DETAIL (4) AND NEW INSTALLATION DETAILS (5) & (6) ON DRAWING A-06.
3. REMOVE ANGLE FRAMES FROM THE PERIMETER OF THE TRENCH DRAIN, DRAIN PIT AND FROM FLOOR AREAS TO PREPARE FOR NEW INSTALLATIONS. SAW CUT THE FLOOR AROUND THE FRAMES
TO A DEPTH OF 1”, CHIP AWAY THE CONCRETE AS REQUIRED TO REMOVE THE STEEL ANGLES.
COORDINATE WITH THE TRENCH DRAIN DEMOLITION DETAIL (4) AND FLOOR PATCH DETAIL (5 & 6) ON
DRAWING A-06.
4. REMOVE CONCRETE HOUSEKEEPING PADS IN ITS ENTIRETY. HOUSEKEEPING PAD REMOVAL SHALL REQUIRE SAW CUTTING THE FLOOR AROUND THE PADS TO A DEPTH OF 1” AND CHIPPING AWAY THE
CONCRETE AS REQUIRED TO REMOVE ALL ASSOCIATED REBAR, WIRE MESH, STEEL PINS OR
DOWELS EMBEDDED IN THE FLOOR. COORDINATE THE EXTENT OF THE REMOVALS WITH THE
TRENCH DRAIN PATCH DETAIL (6) SHOWN ON DRAWING A-06.
5. SERVICE PIPING TO BE REMOVED, COORDINATE SERVICE REMOVALS WITH MEP DRAWINGS.
PREPARE FLOOR PENETRATION FOR INFILL REPAIR. COORDINATE WITH FLOOR REPAIR DETAILS ON
STRUCTURAL DRAWINGS.
6. REMOVE EXISTING DOOR PANELS, DOOR FRAME AND HARDWARE.
7. REMOVE EXISTING VCT FLOOR TILE, MASTIC, ETC. AND PREPARE CONCRETE SUB-FLOOR FOR NEW
FINISH INSTALLATIONS. CONTRACTOR SHALL TEST FLOOR TILE AND MASTIC FOR HAZARDOUS
MATERIALS. IF HAZARDOUS MATERIALS ARE FOUND CONTRACTOR SHALL NOTIFY COR TO ARRANGE
ABATEMENT.
8. SCARIFY AND DRILL CONCRETE TO PREPARE SURFACE AND SET PINS FOR NEW HOUSEKEEPING
PADS. COORDINATE REQUIREMENTS WITH NEW INSTALLATION DRAWINGS APPROVED VENDOR
SHOP DRAWINGS AND HOUSEKEEPING PAD INSTALLATION DETAILS ON STRUCTURAL DRAWINGS.
9. LOCATION OF NEW EQUIPMENT PAD. EXCAVATE AND PREPARE AREA FOR INSTALLATION OF A NEW EQUIPMENT PAD. FURNISH AND INSTALL ALL OSHA REQUIRED SHORING AND FOLLOW ALL SAFETY
REQUIREMENTS. COORDINATE WITH STRUCTURAL DRAWINGS FOR INSTALLATION REQUIREMENTS.
10. LOCATION OF NEW BOLLARD. EXCAVATE AND PREPARE FOR INSTALLATION OF NEW BOLLARDS.
COORDINATE WITH DETAILS ON STRUCTURAL DRAWINGS.
11. REMOVE THE EXISTING ROOF CURB, EQUIPMENT, AND A PORTION OF THE EXISTING ROOFING
SYSTEM TO PREPARE ROOF PENETRATION FOR A ROOF PATCH. ROOFING SYSTEM SHALL BE CUT
BACK A MINIMUM OF 12” BEYOND THE ROOF OPENING. COORDINATE WITH DETAIL 1 ON DRAWING
A-06. COORDINATE WITH MECHANICAL DEMOLITION DRAWINGS.
12. PREPARE ROOF SYSTEM FOR NEW MECHANICAL INSTALLATIONS. COORDINATE LOCATIONS AND SIZE OF OPENINGS WITH MECHANICAL DRAWINGS. FURNISH AND INSTALL SUPPLEMENTAL STEEL
AS SHOWN ON STRUCTURAL DRAWINGS AND CUT A NEW OPENING THROUGH THE ROOF DECKING.
REMOVE A PORTION OF THE EXISTING ROOF AS REQUIRED FOR NEW INSTALLATIONS. COORDINATE
WITH ROOFING DETAILS SHOWN ON DRAWING A-06.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
632-23-109RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
L
SOILED LINENS
WASH ROOM
MECH. ROOM
LOCKER ROOM
RESTROOM
PLANT MANAGER
LINEN DISTRIBUTION AREA
LOADING DOCK
3 4 5 6 7 8 9 10 11
A
B
C
DN
UP
AIR HANDLER
CHILLER
9' -9
16'-0"
19'-1"
6' -4
6' -0
3' -7
5' -0
5'
-0
5'-2" 5'-4 1/4" 5'-2"
4' -0
7' -5
'-5
'-5
'-5
'-5
'-5
'-1
1"
16'-8"
2'-0" 2'-0"
8'-2 1/2" 6'-0" 19'-5 1/2"
33'-8"
'-1
1"
13'-10"
5'-8"2' -8
2'-6"
2' -6
3' -1
1" 3'
-0
'-1
0" 7"
'-3
1' -0
6'
-0
'-3
2'-2 1/2"6'-0"2'-2 1/2"
10'-4 1/2" 6'-0"
44'-11"
2'-10"
2' -1
0"
3'-3 1/2"
9' -9
4'
-0
/4
8'-4 1/4"
3'-8"
2' -0
2'-0"
6' -0
6' -0
10'-4"
'-4
2'-3" 6'-0"
3' -9
3' -1
WASHER
WASHER
WASHER WASHER
DRYER DRYER DRYER DRYER
AIR HANDLER
CHILLER
NEW WALL ONLY
12'-0"
3'-6 1/4"
6' -0
2'-8"
1'-8"
(TYP)
NEW WALL ONLY (EACH SIDE)
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 6WF15EXIST. 6WF15EXIST. 6WF15EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 6WF15
EXIST. 6WF15
EXIST. 6WF15
EXIST. 8WF17 EXIST. 8WF17 EXIST. 8WF17 EXIST. 8WF17
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EXIST. 8BL13
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
2L S x
1/ x
5/
EX
IS
T.
LS
x
/2 x
/1
EX
IS
T.
LS
x
/2 x
/1
3 4 5 6 7 8 9 10 11
A
B
C
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" R
OD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
EXIST. 7/8" ROD CROSS BRACING
4'-10 1/2"
5'-6 1/4" 7'-11" 4'-0 3/4"
7' -2
/2
2' -9
/4
5' -7
/2
1'-10"
8'-1 1/2"
3'-5 1/2"
2' -7
/2
1' -2
/4
4'-7 1/4"
S.G. S.M.
A-03
N
ARCHITECTURAL INSTALLATION
FLOOR PLAN
N
INSTALLATION FLOOR PLAN - PARTIAL BUILDING 13
3/16"= 1'-0"
INSTALLATION ROOF PLAN - PARTIAL BUILDING 13
1/8"= 1'-0"
NEW WORK KEYED NOTES:
1. INSTALL NEW METAL FRAMED AND GYPSUM BOARD WALL AS SHOWN ON THE PLAN, AS INDICATED BY WALL TYPE "A" SHOWN ON DRAWING A-5 WITH MATERIALS SPECIFIED. THE WALL SHALL EXTEND FROM THE FINISHED FLOOR TO THE UNDERSIDE OF THE ROOF DECK. INSTALL FIREPROOFING AT THE TOP AND BOTTOM OF THE WALL ASSEMBLY AND ALL PENETRATIONS TO MEET OR EXCEED THE REQUIRED 1 HOUR FIRE RATING. COORDINATE WITH PENETRATIONS DETAILS AS SHOWN ON A-06. FINISH WALL SURFACES WITH EPOXY PAINT AS SPECIFIED. CONTRACTOR SHALL COORDINATE WITH COR FOR VA INSTALLATION PRIOR TO INSTALLATION OF GYPSUM BOARD.
2. INSTALL A NEW WAINSCOT. WAINSCOT SHALL BE; 18 GA., 304 STAINLESS SHEET STEEL, WITH A #4 EXPOSED FINISH. WAINSCOT SHALL EXTEND FROM THE FINISHED FLOOR TO A MINIMUM OF 4'-0” AFTER FINISHED FLOOR. ALL EDGES SHALL BE FILLETED TO REMOVE ALL SHARP EDGES. INSTALL USING CONSTRUCTION ADHESIVE AND FASTENERS EQUALLY SPACED NOT TO EXCEED 8” O.C. AROUND THE PERIMETER AND 16” O.C. IN THE FIELD OF THE PANEL. CORNER GUARDS SHALL BE PRE-DRILLED AND COUNTER SUNK FOR FASTENERS IN THE SHOP. FASTENERS SHALL BE STAINLESS STEEL FLAT HEAD SCREWS. INSTALL PANELS WITH A 1/8” GAP BETWEEN EACH PANEL.
SEAL PANEL GAPS AND ALL EDGES OF THE PANELS WITH A NON-SAGGING SILICONE SEALANT COLOR TO MATCH THE WAINSCOT.
EXTEND FROM CORNER TO CORNER OF WALL.
3. INSTALL NEW DOOR PANELS, DOOR FRAME AND REQUIRED HARDWARE. COORDINATE WITH DOOR SCHEDULE AND DETAILS ON DRAWING A-05. COORDINATE COMPONENT SELECTION WITH PROJECT SPECIFICATIONS. FINISH WITH PAINT AS SPECIFIED FOR
INTERIOR METAL SURFACES.
4. INSTALL NEW TRENCH DRAIN AND GRATING. COORDINATE INSTALLATION WITH TRENCH DRAIN INSTALLATION DETAIL (5) ON DRAWING
A-06 AND AS INDICATED ON PLUMBING DRAWINGS.
5. PATCH EXISTING CONCRETE FLOOR. COORDINATE INSTALLATION WITH TRENCH DRAIN PATCH INSTALLATION DETAIL (6) ON DRAWING
A-06. TROWEL SMOOTH AND LEVEL WITH ADJACENT SURFACES.
6. PATCH ALL FLOOR PENETRATIONS NO LONGER IN USE. SEE DETAIL ON STRUCTURAL DRAWINGS FOR INSTALLATION REQUIREMENTS.
7. INSTALL NEW HOUSEKEEPING PADS. COORDINATE SIZE AND LOCATION WITH APPROVED VENDER SHOP DRAWINGS AND MEP
DRAWINGS. SEE DETAIL ON STRUCTURAL DRAWINGS FOR INSTALLATION REQUIREMENTS.
8. INSTALL NEW CORNER GUARD. CORNER GUARD SHALL BE 3" x 3" x 3/16" AND SHALL EXTEND FROM FINISHED FLOOR TO MINIMUM OF 4'-0"
AFTER FINISHED FLOOR.
9. EXISTING LOUVERS TO REMAIN. FURNISH AND INSTALL 2”X 2”X 1/8” SUPPLEMENTAL STEEL ANGLES AS REQUIRED TO FASTEN 18 GA.
FACTORY PRIMED SHEET METAL TO THE EXTERIOR OF THE EXISTING LOUVER. PRIME COAT ALL STEEL AND CUT EDGES. FINISH WITH PAINT AS SPECIFIED FOR EXTERIOR METAL SURFACES. PROVIDE GASKETING AND SEALANT TO MAKE WEATHER TIGHT.
10. PREPARE CONCRETE FLOOR AND HOUSEKEEPING PAD SURFACES FOR NEW FINISHES AS SPECIFIED AND RECOMMENDED IN FINISH MANUFACTURERS PUBLISHED INSTALLATION INSTRUCTIONS. INSTALL NEW EPOXY FLOOR COATING, IN THE ENTIRE ROOM. COATING
SHALL BE INSTALLED TO COVER THE NEW HOUSEKEEPING PADS.
11. INSTALL A NEW EPOXY WALL COATING ON EACH WALL OF THE ROOM. (U.O.N)
12. INSTALL A NEW EQUIPMENT PAD FOR MECHANICAL EQUIPMENT. COORDINATE SIZE AND LOCATION WITH MECHANICAL DRAWINGS AND APPROVED VENDER SHOP DRAWINGS. COORDINATE THE INSTALLATION OF THE EQUIPMENT PAD WITH DETAILS ON STRUCTURAL
DRAWINGS.
13. INSTALL NEW HOUSEKEEPING PAD ON NEW EQUIPMENT PAD (SEE KEYED NOTE 12) COORDINATE SIZE AND LOCATION WITH MECHANICAL DRAWINGS AND APPROVED VENDOR SHOP DRAWINGS. COORDINATE THE HOUSEKEEPING PADS WITH DETAILS ON STRUCTURAL
DRAWINGS.
14. INSTALL A NEW CHAIN-LINK FENCE WITH A 6'-0” LOCKABLE DOUBLE SWING GATE.
15. PATCH EXISTING ROOF DECK AND ROOFING SYSTEM AS SHOWN IN DETAIL (1) ON DRAWING A-06.
16. INSTALL A NEW ROOF CURB AS SHOWN IN DETAIL (2) ON DRAWING A-06. COORDINATE SIZE AND LOCATION WITH MECHANICAL
DRAWINGS AND APPROVED VENDOR SHOP DRAWINGS.
17. INSTALL A NEW EQUIPMENT CURB AS SHOWN IN DETAIL (3) ON DRAWING A-06. COORDINATE SIZE AND LOCATION WITH MECHANICAL
DRAWINGS AND APPROVED VENDOR SHOP DRAWINGS.
18. INSTALL (9) BALLARDS 6" DIA x 4'-7" HT. (SEE DWG DETAIL (2) ON DWG. S-03)
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
632-23-109RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text A
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
AutoCAD SHX Text L
AutoCAD SHX Text C
L
3 4 5 6 7 8 9 10 11
A
B
C
DN
UP
1'-5 1/2"
2' -1
1/
2" 1'
-4
/2
1'-5 1/2"
LEGEND:
CEILING GRID AND TILE
2X4 LIGHTING TROFFER
2X4 LIGHTING TROFFER
WITH EMERGENCY BATTERY
CEILING DIFFUSER
CEILING REGISTER
EXHAUST DUCT
S.G S.M.
A-04
ARCHITECTURAL REFLECTED
CEILING PLAN
REFLECTED CEILING FLOOR PLAN - PARTIAL BUILDING 13
3/16= 1'-0"1 REFLECTED CEILING KEYED NOTES:
1. INSTALL NEW ACOUSTIC TILE CEILING AND GRID. COORDINATE WITH DETAIL 5 ON DRAWING A-05.
CEILING TO BE INSTALLED AT AN ELEVATION OF 9'-0” ABOVE FINISHED FLOOR. COORDINATE WITH
STRUCTURAL DRAWINGS FOR SEISMIC DESIGN CATEGORY REQUIREMENTS, AND MANUFACTURERS
PUBLISHED INSTALLATION INSTRUCTIONS AND DETAILS FOR THE IDENTIFIED SEISMIC CATEGORY.
2. LED CEILING TROFFERS. TO BE FURNISHED AND INSTALLED BY VA CONTRACTOR. SHALL
COORDINATE WITH COR FOR VA INSTALLATIONS PRIOR TO INSTALLATION OF CEILING GRID
3. INSTALL NEW CEILING DIFFUSERS AND REGISTERS. COORDINATE SIZE AND LOCATION WITH
MECHANICAL DRAWINGS AND APPROVED VENDOR SHOP DRAWINGS.
4. COORDINATE WITH FIRE PROTECTION DRAWINGS FOR LOCATIONS OF MODIFIED SPRINKLER
SYSTEM AND NEW SPRINKLER HEADS.
5. COORDINATE WITH MEP DRAWING FOR WALL PENETRATIONS AND EQUIPMENT INSTALLATIONS.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
632-23-109RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
CONC. SLAB SEAMLESS EPOXY FLOORING
VINYL TRANSITION STRIP
AS MFD BY JOHNSONITE,
MODEL No. CTA-40-X OR
AN APPROVED EQUAL.
DOOR PANEL
℄ OF TRANSITION TO MATCH ℄
OF DOOR
SCALE:
TRANSITION - VCT TO SEAMLESS EPOXY FLOORING
6" = 1'-0"4
VCT FLOOR
FINISH
JAMB DETAIL
HEAD DETAIL
SCALE:
SINGLE RABBETED FRAME IN DRYWALL PARTITION (1-LAYER ON
EACH SIDE) W/ AUTO-SWING DOOR OPERATOR
3" = 1'-0"2
WALL BOARD:
(1) LAYER ON EACH SIDE PER
WALL TYPE AND
SPECIFICATIONS
STEEL CRIPPLE STUDS:
STUD AT 16" 0.C.
(COORDINATE WIDTH WITH
WALL TYPE.)
FRAME REINFORCED FOR
INSTALLATION OF AUTOMATIC
DOOR OPERATOR
STEEL RUNNER AS HEADER
ATTACH TO STRUT-STUD
ALIGN DOOR FRAME AND WALL
SURFACE FLUSH
AUTOMATIC DOOR
OPERATOR AS
SPECIFIED
18 GA. BRUSHED STAINLESS
STEEL HOOD WITH END CAPS
AS FURNISHED BY OPERATOR
MANUFACTURER
6" HIGH x 1/8" THICK STEEL
BLOCKING PLATE. PLATE SHALL
BE FABRICATED FROM A SINGLE
PIECE & SHALL BE SCREW
FASTENED TO STUD FRAMING.
(1) LAYER OF 1/2" WALL BOARD
MOUNTED OVER BLOCKING
PLATE. WALL BOARD VARIETY
PER WALL TYPE AND
SPECIFICATIONS.
DOOR FRAME (REFER
TO DOOR SCHEDULE
FOR MATERIAL)
FASTEN "ZEE" ANCHOR TO
STUD USING SCREWS
WALL BOARD:
(1) LAYER ON EACH SIDE
PER WALL TYPE AND
SPECIFICATIONS
STEEL STRUT-STUDS:
WALL STUDS AT 16" 0.C.
(COORDINATE WIDTH WITH
WALL TYPE.)
'ZEE' ANCHORS (MIN. 3 PER JAMB)
(MIN. 4 FOR 8'-0" HIGH DOORS)
DOOR FRAME (REFER TO DOOR
SCHEDULE FOR MATERIAL)
CONTINUOUS SEALANT, BOTH
SIDES OF FRAME
ALIGN DOOR FRAME AND WALL
SURFACE FLUSH, (TYP.)
METAL "J"-TRIM, EACH SIDE
CONTINUOUS SEALANT
JAMB DETAIL
HEAD DETAIL
SCALE:
DOUBLE RABBETED FRAME IN DRYWALL PARTITION
(1-LAYER ON EACH SIDE)
3" = 1'-0"3
WALL BOARD:
(1) LAYER ON EACH SIDE PER
WALL TYPE AND
SPECIFICATIONS
STEEL CRIPPLE STUDS:
STUD AT 16" 0.C.
(COORDINATE WIDTH WITH
WALL TYPE.)
STEEL RUNNER AS HEADER
ATTACH TO STRUT-STUD
CONTINUOUS SEALANT, BOTH
SIDES OF FRAME
DOOR FRAME (REFER
TO DOOR SCHEDULE
FOR MATERIAL)
FASTEN "ZEE" ANCHOR TO
STUD USING SCREWS
CONTINUOUS SEALANT, BOTH
SIDES OF FRAME
DOOR FRAME (REFER TO DOOR
SCHEDULE FOR MATERIAL)
WALL BOARD:
(1) LAYER ON EACH SIDE PER
WALL TYPE AND
SPECIFICATIONS
STEEL STRUT-STUDS:
WALL STUDS AT 16" 0.C.
(COORDINATE WIDTH WITH
WALL TYPE.)
'ZEE' ANCHORS (MIN. 3 PER JAMB)
(MIN. 4 FOR 8'-0" HIGH DOORS)
LAY IN GRID
HANGER WIRE SHALL BE 12 GA. AND
SPACED 4'-0" O.C. (WIRES SHALL NOT BE
HUNG FROM PIPES, DUCTS OR
EQUIPMENT)
ACOUSTIC CEILING TILE
WALL CONSTRUCTION
CEILING INSTALLATION NOTES:
1. CEILING INSTALLATION TO CONFORM TO THE
REQUIREMENTS OF ASTM C636.
2. ALL WIRE TIES ARE TO BE THREE TURNS AROUND
ITSELF WITHIN THREE INCHES.
SCALE:
DETAIL AT ACOUSTIC CEILING TILE
3" = 1'-0"5
HANG FROM ROOF
STRUCTURE
STEEL DECKING OF
STRUCTURE ABOVE
CONT. 3 5/8" GALV.
STEEL TRACK.
3 5/8" STEEL STUDS @ 16" O.C.
(TYPICAL)
LAYER OF 5/8" GYP.
BD. (TYPICAL BOTH
SIDES)
SEE FINISHES AS IDENTIFIED
ON THE PLAN.
DEEP LEG DEFLECTION TRACK.
BOLTED TO CEILING (TYP.)1/4"Ø KWIK BOLT II @
48" O.C. (3-1/2" EMBED)
TYP. ALL STUD
PARTITIONS
BLOCKING:
CONT. 3 5/8" GALV. STEEL
TRACK AT THE TOP OF
WAINSCOT AND AS
REQUIRED FOR WALL
MOUNTED EQUIPMENT AND
CASEWORK
SCALE:
PARTITION TYPE A
1 1/2" = 1'-0"A
PACK VOID WITH MINERAL WOOL
COORDINATE WITH MEP
DRAWING FOR THROUGH WALL
PENETRATIONS
SEE PENETRATION DETAILS ON
A-06
INSTALL FIRE
SEALANT FOR
EACH SIDE TOP &
BOTTOM
6'-0" x 7'-0"
DOOR SCHEDULE
DOOR
NO.ROOM NAME SIZE MAT. TYPE
DOOR
MAT. DETAIL
FRAME
PARTITION
TYPE
FIRE
RATING REMARKS
01 DRYER ROOM
02 DRYER ROOM
03 MECHANICAL ROOM
04 WASH ROOM
05 WASH ROOM
HM 2HG *1/A-501 A
DOOR
NO.
HARDWARE
SET
6'-0" x 7'-0" 6'-0" x 7'-0" 6'-0" x 7'-0" 3'-0" x 7'-0"
HM 1/A-601
HM FL 2/A-501
HM 1/A-501
HM HG 2/A-501
1 HR
DOOR SCHEDULE LEGEND:
FL - FLUSH PANEL
HG - HALF GLASS PANEL
HM - HOLLOW METAL
HM
HM
HM
HM
HM
A A A A
1 HR
1 HR
1 HR
1 HR
2HG
2HG
SCALE:
DOOR TYPE ELEVATIONS
1/4" = 1'-0"1
S.G S.M.
A-05
ARCHITECTURAL DETAILS 1 OF 2
ROOM FINISH GENERAL NOTES:
1. FINAL COLOR SELECTIONS AND/OR PATTERN SELECTIONS FOR FINISHES SHALL BE PERFORMED BY THE VA.
2. WHERE MATERIALS ARE NOT REFERENCED ON DRAWINGS, ARE NOT SPECIFIED AND ARE NECESSARY TO COMPLETE THE WORK OF THIS CONTRACT, IT IS INTENDED TO MATCH EXISTING MATERIALS. WHERE MATERIALS ARE INTENDED TO MATCH EXISTING, PROVIDE
CLOSEST POSSIBLE MATCH. ALL SELECTIONS ARE SUBJECT TO VA'S APPROVAL.
3. ALL ITEMS AND WORK ON DRAWINGS ARE NEW, UNLESS OTHERWISE NOTED.
4. ALL NEW INSTALLATIONS OR BUILDING COMPONENTS TO REMAIN, THAT ARE DAMAGED DURING DEMOLITION OR CONSTRUCTION, SHALL BE REPAIRED OR REPLACED. WHERE ITEMS CANNOT BE REPAIRED TO A "NEW CONDITION", OR THE STRUCTURAL INTEGRITY
HAS BEEN AFFECTED, ITEM SHALL BE REPLACED AT NO COST TO THE VA.
5. ALL CONTRACTORS ARE RESPONSIBLE TO VERIFY ALL SITE, FIELD AND BUILDING CONDITIONS PRIOR TO SUBMITTING BIDS AND COMMENCING WORK. IF THERE ARE ANY DISCREPANCIES BETWEEN DRAWINGS AND FIELD CONDITIONS, SUBMIT A REQUEST FOR
INFORMATION TO VA FOR RESOLUTION.
6. WHERE EXISTING CONSTRUCTION OR BUILDING COMPONENTS HAVE BEEN REMOVED AND/OR DISTURBED FOR INSTALLATION OF NEW WORK, CAUSING THE EXPOSURE OF UNFINISHED AND/OR DAMAGED SURFACES, THE RESULTING SURFACES SHALL BE INFILLED/RECONSTRUCTED WITH MATERIALS TO MATCH FINISHED AREAS. ALL ABANDONED OPENINGS (I.E. DUCT/PIPE REMOVALS, ETC.) AT WALLS, ROOF OR FLOOR TO BE INFILLED SOLID.
7. WHERE REMOVAL OF EXISTING CONSTRUCTION HAS RESULT IN DEPRESSIONS AND/OR UNEVEN FLOOR CONDITIONS, PATCH, LEVEL AND FEATHER AREAS AS REQUIRED TO PROVIDE LEVEL, SMOOTH SURFACE FOR INSTALLATION OF NEW FLOOR FINISH.
8. ALTHOUGH NOT NECESSARILY SHOWN ON DRAWINGS, DEMOLITION/REMOVAL AND REPAIR/REINSTALLATION IS REQUIRED IN SOME AREAS AFFECTED BY MEP WORK. WORK MAY INCLUDE BY NOT NECESSARILY BE LIMITED TO; THE REMOVAL/REPLACEMENT OF PORTIONS OF CEILINGS, WALLS, FINISHES, AND OTHER CONSTRUCTION AS NECESSARY TO PERFORM THE INSTALLATIONS OF MEP SYSTEMS. ONCE INSTALLATIONS ARE COMPLETE, CONTRACTOR SHALL RESTORE THESE SPACES, AREAS, AND/OR BUILDING
COMPONENTS TO THEIR ORIGINAL CONDITION.
9. CONTRACTOR SHALL OBTAIN FROM VA ALL REQUIREMENTS FOR INSTALLATION OF VA PROVIDED EQUIPMENT INCLUDING ROUGHING DIAGRAMS, INSTALLATION INSTRUCTIONS, ELECTRICAL SCHEMATICS, TEMPLATES, LAYOUTS AND DIMENSIONS AND ALL OTHER INFORMATION NECESSARY FOR A PROPER, WELL-COORDINATED INSTALLATION. PRIOR TO ROUGH-IN OF SERVICES, CONFER WITH
OWNER FOR EXACT LOCATION OF ALL ITEMS.
10. ALL PENETRATIONS THROUGH FLOORS AND FULL HEIGHT WALLS SHALL BE FIRE STOPPED. ALL GAPS AND JOINTS AT RATED FLOORS, ROOFS AND WALLS SHALL BE FIRE STOPPED. GAPS AND JOINTS INCLUDE (BUT ARE NOT LIMITED TO) TOP OF WALL TO FLOOR OR ROOF DECK, WALL TO BEAMS, AND CONTROL OR EXPANSION JOINTS. FIRE STOPPING INCLUDES FOAM OR SEALANT AND THE FILL, VOID OR CAVITY PACKING MATERIAL.
11. SO THAT THE WORK AND SCHEDULE ARE NOT IMPEDED, THE GENERAL CONTRACTOR SHALL COORDINATE THE WORK OF EACH TRADE WITH OTHER CONTRACTORS WHO MAY BE ON SITE ON OTHER PROJECTS. SCHEDULE WORK PROGRESS THROUGHOUT THE ENTIRE PROJECT TO PREVENT CONFLICTS AND INTERFERENCES. OBTAIN ALL NECESSARY INFORMATION SUCH AS SIZES, LOCATIONS, TEMPLATES, LAYOUT, DIMENSIONS AND ALL OTHER INFORMATION NECESSARY FOR A PROPER AND WELL COORDINATED
INSTALLATION.
12. CONTRACTOR SHALL COORDINATE ALL ACTIVITIES WITH OWNER TO PREVENT DISRUPTION TO BUSINESS OPERATIONS.
13. CONTRACTOR SHALL BE RESPONSIBLE FOR ESTABLISHING TEMPORARY DUST TIGHT PARTITIONS TO SEGREGATE AREAS UNDER
CONSTRUCTION FROM OCCUPIED SPACES. SEE GENERAL PROTECTION NOTES ON DRAWING A-01.
14. ALL EXTREME DUST, NOISE AND VIBRATION CREATING ACTIVITIES SHALL BE COORDINATED WITH THE VA AND IF DIRECTED, THEY
SHALL BE DONE OFF HOURS.
15. ALL CEILING SUSPENSION SYSTEMS AS WELL AS OTHER CONSTRUCTION SYSTEMS SHALL COMPLY WITH THE GOVERNING CODE REQUIREMENTS FOR SEISMIC CONDITIONS. THE CONTRACTOR SHALL INCORPORATE THESE REQUIREMENT INTO HIS BID PRICE.
16. AS A MINIMUM REQUIREMENT, CLASS C DESIGNATED INTERIOR FINISH MATERIALS SHALL BE FURNISHED AND INSTALLED WITHIN ALL SPACES SCHEDULED TO RECEIVE NEW INTERIOR WALL AND CEILING FINISHES. WITHIN SPACES DESIGNATED TO RECEIVE NEW FLOOR
FINISHES, PROVIDE CLASS II OR BETTER MATERIALS.
17. ANY CRACKS FOUND IN CONCRETE SLAB SHALL BE REPAIRED UTILIZING A HIGH STRENGTH, TWO-COMPONENT, 100% SOLIDS EPOXY CRACK FILLER. PRODUCT SHALL BE TK-9000 EPOXY FILLER AS MANUFACTURED BY TK PRODUCTS, OR AN APPROVED EQUAL.
18. ALL EXISTING PAINTED SURFACES AFFECTED BY DEMOLITION AND/OR NEW WORK SHALL BE TOUCHED UP AS NEEDED TO MATCH
ADJACENT SURFACES.
19. ALL EXIST. PAINTED WALL SURFACES AFFECTED BY DEMOLITION AND OR NEW WORK SHALL RECEIVE A NEW PAINT FINISH. PAINT ENTIRE WALL PLANE, CORNER TO CORNER. COLOR TO MATCH ADJACENT EXISTING WALL SURFACES.
20. WHERE THE FINISHES STIPULATES RESINOUS FLOOR INSTALLATION, CONTRACTOR SHALL SHOT BLAST AND PREPARE EXISTING FLOOR FOR INSTALLATION OF NEW FINISHES AS REQUIRED IN MANUFACTURERS PUBLISHED INSTALLATION MANUAL.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Fi le
P at h
/1 5/
1:
:0
AM
DESIGN DEVELOPMENT
Office of
Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
STAMP
321 4 5 6 7 8 9 10
Project Director
Revisions: Date:
79 MIDDLEVILLE RD, NORTHPORT, NY 11768
632-23-109RENOVATE UTILITIES
BUILDING 13
DECEMBER 27, 2023
AutoCAD SHX Text
DOOR PANEL
AutoCAD SHX Text 2 1/2"
AutoCAD SHX Text 2 1/2"
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
DOOR WIDTH
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
COORDINATE W/
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
DOOR HEIGHT
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text
REFER TO
AutoCAD SHX Text 1/2"
AutoCAD SHX Text 1/2"
AutoCAD SHX Text 1/2"
AutoCAD SHX Text 1/2"
AutoCAD SHX Text 8"
AutoCAD SHX Text 8"
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
HG
AutoCAD SHX Text
SEE DOOR
AutoCAD SHX Text
SEE DOOR
AutoCAD SHX Text
1/4" LAMINATED SAFETY GLASS
2HG
SEALING MASTIC
STAINLESS STEEL CLAMPING
RING
GALV. STEEL CAP
GALV. STEEL
COUNTERFLASHING
COVER BOARD
DUCT INSULATION
PRE-FAB INSULATED METAL ROOF
CURB WITH BUILT-IN RAISED CANT
& WOOD NAILER
BASE FLASHING BONDED TO CURB
(EXTEND FLASHING UP AND OVER
WOOD BLOCKING AT TOP OF CURB).
INSTALL PER MANUFACTURERS
INSTALLATION INSTRUCTIONS.
EXISTING BUILT-UP
ROOFING MEMBRANE
CONT. TREATED WOOD
BLOCKING
20 GA. "J" CLOSURE STRIP OVER
EDGE OF DECK
NEW REINFORCEMENT (TYP.)
COORDINATE WITH
STRUCTURAL DRAWINGS.
EXISTING METAL DECK
20 GA. SHT. METAL CLOSURE
ALL AROUND
EXISTING RIGID
INSULATION
MECH. EQUIPMENT (SEE MECH.
DWGS.)
FULLY ADHERE FLASHING TO
INSULATED ROOF CURB (FLASHING
TO EXTEND UP CURB AND OVER
WOOD BLOCKING AT TOP OF CURB).
INSTALL PER MANUFACTURERS
INSTALLATION INSTRUCTIONS.
EXISTING COVER BOARD
EXISTING RIGID INSULATION
EXISTING METAL DECK
NEW REINFORCEMENT (TYP.)
COORDINATE WITH
STRUCTURAL DRAWINGS.
20 GA. "J" CLOSURE STRIP
OVER EDGE OF DECK
PREFABRICATED 18 GA. GALV. STEEL
INSULATED ROOF CURB, W/FACTORY
INSTALLED WOOD NAILER AND BUILT-IN
RAISED CANT
SECURE ROOFING AND FLASHING TO
TREATED WOOD NAILERS TOP AND
BOTTOM
METAL CURB FLASHING
AND DRIP (SUPPLIED BY
FAN MANUF.)
CANT STRIP
EXISTING BUILT-UP
ROOFING MEMBRANE
SEALING MASTIC
EXISTING BUILT-UP
ROOFING MEMBRANE
OVERLAP DECK PATCH A
MINIMUM OF 12" ALL
AROUND EXISTING
OPENING.
EXISTING OPENING.
COORDINATE WITH
MECHANICAL DRAWINGS
AND FIELD CONDITIONS.
OVERLAP EXISTING
BUILT-UP ROOFING WITH
NEW A MINIMUM OF 12"
ALL AROUND.
CUT BACK EXISTING
ROOFING SYSTEM A
MINIMUM OF 12" ALL
AROUND EXISTING
OPENING.
NEW METAL ROOF
DECKING TO MATCH
EXISTING.
NEW RIGID INSULATION
TO MATCH EXISTING.
NEW COVER BOARD TO
MATCH EXISTING.
NEW BUILT-UP ROOFING
MEMBRANE SHALL BE
COMPATIBLE WITH THE
EXISTING SYSTEM
SEALING MASTIC
SCALE:
TYPICAL ROOF OPENING REPAIR DETAIL
1 1/2" = 1'-0"1 SCALE:
TYPICAL ROOF CURB DETAIL (DUCT PENETRATION)
1 1/2" = 1'-0"2 SCALE:
TYPICAL ROOF EQUIPMENT CURB DETAIL
1 1/2" = 1'-0"3
CONT. TREATED WOOD
CONU. BLOCKING
ANSI/UL1479 (ASTM E814)
SECTION A-A
A
A
1B
1A
1. WALL ASSEMBLY — SHALL BE CONSTRUCTED AS INDICATED BY WALL TYPE. THE FOLLOWING INDICATES THE MINIMUM REQUIREMENTS FOR THE
PENETRATION:
THE 1 OR 2 HR FIRE RATED GYPSUM BOARD/STUD WALL ASSEMBLY SHALL BE CONSTRUCTED OF THE MATERIALS AND IN THE MANNER SPECIFIED IN THE INDIVIDUAL U300, U400, V400 OR W400 SERIES WALL AND PARTITION DESIGNS IN THE UL FIRE RESISTANCE DIRECTORY AND SHALL INCLUDE THE FOLLOWING
CONSTRUCTION FEATURES:
A. STUDS — WALL FRAMING SHALL CONSIST STEEL CHANNEL STUDS. STEEL STUDS TO BE MIN 2-1/2 IN. WIDE AND SPACED MAX 24 IN. OC.
B. GYPSUM BOARD* — 5/8 IN. THICK, 4 FT WIDE WITH SQUARE OR TAPERED EDGES. THE GYPSUM BOARD TYPE, THICKNESS, NUMBER OF LAYERS, FASTENER
TYPE AND SHEET ORIENTATION SHALL BE AS SPECIFIED IN THE INDIVIDUAL WALL AND PARTITION DESIGN. MAX DIA. F OPENING IS 7-1/2 IN. THE HOURLY F AND FH RATINGS OF THE FIRESTOP SYSTEM ARE EQUAL TO THE HOURLY FIRE RATING OF THE WALL ASSEMBLY IN WHICH IT IS INSTALLED.
2. THROUGH PENETRATES — ONE METALLIC PIPE OR TUBING TO BE CENTERED WITHIN THE FIRESTOP SYSTEM. PIPE OR TUBING TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF WALL ASSEMBLY. THE FOLLOWING TYPES AND SIZES OF METALLIC PIPES OR TUBING MAY BE USED:
A. STEEL PIPE — NOM 4 IN. DIAM (OR SMALLER) SCHEDULE 40 (OR HEAVIER) STEEL PIPE.
B. COPPER TUBING — NOM 2 IN. DIAM (OR SMALLER) TYPE L (OR HEAVIER) COPPER TUBING.
C. COPPER PIPE — NOM 2 IN. DIAM (OR SMALLER) REGULAR (OR HEAVIER) COPPER PIPE.TUBE INSULATION — PLASTICS+ — MIN 1/2 IN. TO MAX 1 IN. THICK
ACRYLONITRILE BUTADIENE/POLYVINYL CHLORIDE (AB/PVC) FLEXIBLE FOAM FURNISHED IN THE FORM OF TUBING. AN ANNULAR SPACE OF MIN 0 IN. (POINT CONTACT) TO MAX 1-1/2 IN. IS REQUIRED WITHIN THE FIRESTOP SYSTEM. THE T, FT AND FTH RATINGS ARE 1 HR WHEN THE 1 IN. THICK TUBE INSULATION IS USED AND 3/4 HR WHEN THE 3/4 IN. THICK TUBE INSULATION IS USED. WHEN TUBE INSULATION THICKNESS IS LESS THAN 3/4 IN., THE T, FT AND FTH
RATINGS ARE 0 HR.
SEE PLASTICS+ (QMFZ2) CATEGORY IN THE RECOGNIZED COMPONENT DIRECTORY FOR NAMES OF MANUFACTURERS. ANY RECOGNIZED COMPONENT TUBE INSULATION MATERIAL MEETING THE ABOVE SPECIFICATIONS AND HAVING A UL 94 FLAMMABILITY CLASSIFICATION OF 94-5VA MAY BE USED.
3. FILL, VOID OR CAVITY MATERIAL* — SEALANT — MIN 5/8 IN. THICKNESS OF FILL MATERIAL APPLIED WITHIN THE ANNULUS, FLUSH WITH BOTH SURFACES OF WALL. AT THE POINT CONTACT LOCATION BETWEEN PIPE COVERING AND GYPSUM BOARD, A MIN 1/2 IN. DIAM BEAD OF FILL MATERIAL SHALL BE APPLIED AT
THE PIPE COVERING/GYPSUM BOARD INTERFACE ON BOTH SURFACES OF WALL.
* INDICATES SUCH PRODUCTS SHALL BEAR THE UL CERTIFICATION MARK FOR JURISDICTIONS EMPLOYING THE UL CERTIFICATION.
THE FOLLOWING ARE BASES OF DESIGN PRODUCTS ARE FS-ONE SEALANT OR FS-ONE MAX INTUMESCENT SEALANT AS MANUFACTURED BY HILTI CONSTRUCTION CHEMICALS, DIV OF HILTI INC. CONTRACTOR MAY FURNISH FOR REVIEW AND ACCEPTANCE ALTERNATE MANUFACTURERS AND PRODUCTS
THAT MEET OR EXCEED THE IDENTIFIED PRODUCTS.
F Ratings — 1 and 2 Hr (See Item 1) T Ratings — 0, 3/4 and 1 Hr (See Item 3) L Rating At Ambient — Less Than 1 CFM/sq ft.
L Rating At 400 F — Less Than 1 CFM/sq ft
SCALE:
PIPE PENETRATION THROUGH 1-2HR. RATED FRAMED WALL
N.T.S.8
System No. W-L-5028
System No. W-L-7040
1. WALL ASSEMBLY — THE FIRE-RATED GYPSUM WALLBOARD/STUD WALL ASSEMBLY SHALL BE CONSTRUCTED OF THE MATERIALS AND IN THE MANNER SPECIFIED IN THE INDIVIDUAL U300, U400, V400 OR V400 SERIES WALL AND PARTITION DESIGNS IN THE FIRE RESISTANCE DIRECTORY AND SHALL INCLUDE
THE FOLLOWING CONSTRUCTION FEATURES:
A. STUDS — WALL FRAMING MAY CONSIST OF EITHER WOOD STUDS OR STEEL CHANNEL STUDS. WOOD STUDS TO CONSIST OF NOM 2 BY 4 IN.
LUMBER SPACED 16 IN. OC. STEEL STUDS TO BE MIN 2-1/2 IN. WIDE AND SPACED MAX 24 IN. ADDITIONAL FRAMING MEMBERS SHALL BE USED TO
COMPLETELY FRAME AROUND OPENING.
B. GYPSUM BOARD* — NOM 5/8 IN. THICK WITH SQUARE OR TAPERED EDGES. THE GYPSUM WALLBOARD TYPE, NUMBER OF LAYERS AND SHEET ORIENTATION SHALL BE AS SPECIFIED IN THE INDIVIDUAL WALL AND PARTITION DESIGN NUMBER. MAX AREA OF OPENING IS 1300 IN.2 WITH THE DIMENSION OF 50 IN. THE HOURLY F AND FH RATINGS OF THE FIRESTOP SYSTEM ARE EQUAL TO THE HOURLY FIRE RATING OF THE WALL
ASSEMBLY IN WHICH IT IS INSTALLED.
2. STEEL DUCT — NOM 24 IN. BY 48 IN. (OR SMALLER) NO. 24 GAUGE (OR HEAVIER) GALV STEEL DUCT TO BE INSTALLED WITHIN THE FIRESTOP SYSTEM. THE ANNULAR SPACE SHALL BE MIN 0 (POINT CONTACT) IN. TO A MAX 2 IN. DUCT TO BE RIGIDLY SUPPORTED ON BOTH SIDES OF THE WALASSEMBLY.
3. FIRESTOP SYSTEM — THE FIRESTOP SYSTEM SHALL CONSIST OF THE FOLLOWING:
A. FILL, VOID OR CAVITY MATERIAL*—SEALANT — MIN 5/8 IN. THICKNESS OF FILL MATERIAL APPLIED WITHIN ANNULUS FLUSH WITH BOTH SURFACES OF WALL. AT POINT CONTACT LOCATION, A MIN 1/2 IN. DIAM. BEAD OF FILL MATERIAL SHALL BE APPLIED TO THE WALL/DUCT INTERFACE
ON BOTH SURFACES OF WALL.
B. STEEL RETAINING ANGLE — NO. 18 MSG (0.048 IN.) GALV STEEL ANGLES CUT TO FIT CONTOUR OF DUCT WITH A 2 IN. OVERLAP ON THE DUCT AND A MIN 1 IN. OVERLAP ON THE GYPSUM BOARD ASSEMBLY ON BOTH SUFACES OF WALL. 2 IN. LEG OF ANGLE SECURED TO DUCT WITH MIN NO.
8 BY 3/4 IN. LONG SHEET METAL SCREWS, SPACED A MAX OF 6 IN. OC. WHEN BEAD OF FILL MATERIAL IS USED AT JOINT CONTACT LOCATIONS, ANGLES SHALL BE INSTALLED PRIOR TO FULL MATERIAL CURING.
* INDICATES SUCH PRODUCTS SHALL BEAR THE UL CERTIFICATION MARK FOR JURISDICTIONS EMPLOYING THE UL CERTIFICATION.
1A 3B3A
1B 3B 3A
System No. C-AJ-5091
1. FLOOR OR WALL ASSEMBLY — MIN 4-1/2 IN. THICK REINFORCED LIGHTWEIGHT OR NORMAL WEIGHT (100-150 PCF ) CONCRETE. WALL MAY ALSO BE CONSTRUCTED OF ANY UL CLASSIFIED CONCRETE BLOCKS*. MAX DIAM OF OPENING IS 29 IN.
SEE CONCRETE BLOCKS (CAZT) CATEGORY IN THE FIRE RESISTANCE DIRECTORY FOR NAMES OF MANUFACTURERS.
2. METALLIC SLEEVE — (OPTIONAL) — NOM 30 IN. DIAM (OR SMALLER) SCHEDULE 10 (OR HEAVIER) STEEL PIPE SLEEVE CAST OR GROUTED INTO FLOOR OR WALL ASSEMBLY, FLUSH WITH FLOOR OR WALL SURFACES OR EXTENDING A MAX OF 3 IN. ABOVE FLOOR OR BEYOND BOTH SURFACES OF WALL. IF THE STEEL SLEEVE EXTENDS BEYOND THE TOP SURFACE OF THE FLOOR OR BOTH SURFACES OF THE WALL, THE T
RATING OF THE FIRESTOP SYSTEM IS 0 HR.
2A. SHEET METAL SLEEVE — (OPTIONAL) - MAX 6 IN. DIAM, MIN 26 GA GALV STEEL PROVIDED WITH A 26 GA GALV STEEL SQUARE FLANGE SPOT WELDED TO THE SLEEVE AT APPROXIMATELY MID- HEIGHT, OR FLUSH WITH BOTTOM OF SLEEVE IN FLOORS, AND SIZED TO BE A MIN OF 2 IN. LARGER THAN THE SLEEVE DIAM. THE SLEEVE IS TO BE CAST IN PLACE FLUSH WITH BOTTOM SURFACE OF FLOOR AND MAY EXTEND A MAX OF 1 IN. ABOVE
THE TOP SURFACE OF THE FLOOR.
2B.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .