Reman and Repair.doc
DOC document 26 KB Posted
- Attached to
- B-1B Escape Handles Federal contract opportunity
- Solicitation number
- FD20202050070
About this file
This document contains guidance on rework and repair procedures for nonconforming materials under a federal contract, as well as details of a sole source procurement opportunity for escape handles on the B-1B Weapon System. The contractor must document rework procedures and submit them to the Government Quality Assurance Representative for review prior to implementation, while repair procedures require submission of a Request for Deviation/Waiver to the Contracting Officer for written approval. For any rework or repair submission, the contractor must include a description of the cause of nonconformances and corrective actions to prevent recurrence. The procedures must also contain re-inspection provisions taking precedence over technical requirements and providing assurance that items meet reprocessing standards. The related procurement opportunity is a sole source buy from Universal Propulsion Company for 36 and 48 escape handles with specified part numbers, all critical safety items to be delivered in fiscal year 2021 under the Department of the Air Force Materiel Command Lifecycle Management Center at Hill Air Force Base.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QALI.pdf | ||
| AIR SPEC 20-50070 Amended 30 Aug 2019.pdf | ||
| SPI Part II.pdf | ||
| 20-93847 EDL.pdf | ||
| TransInstruction4.pdf | ||
| 20-50070 EDLs.pdf | ||
| ADC SOW Jan 2018.doc | DOC document | |
| 20-50070 Item Descriptions.pdf | ||
| Hazard Sheet.pdf | ||
| SPI.pdf | ||
| 20-50070 807s.pdf | ||
| 20-77091 EDL.pdf | ||
| DD 1653.pdf | ||
| 20-77090 EDL.pdf | ||
| CADPAD Item Marking Instruction - Ver 1.5 - 20190501.pdf | ||
| REPSHIP 11 Mar 14.doc | DOC document |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the non-conformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for re-inspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(ES7034)