This is a Limited Sources Justification and Approval (J&A) document for a federal contract action by the Air Force Test Center (AFTC) Directorate of Contracting. The contracting activity is AFTC/PZZG, with Contracting Officer Jenna Jacobson, and the purchase request numbers are F1S0AD5357A001 and F1S0AD5356A001. The requirement is for the acquisition of Broadcom/VMWare Licenses with a five-year renewal period under a Multiple Award Schedule Program authority (FAR 8.405-6). The contract is classified as a brand name justification, and the estimated contract cost is redacted in the document.

The supplies required include VMware Cloud Foundation Base Year licenses (Part #: VCF-CLD-FND, Qty: 2,136) and VMware Avi Load Balancer units (Part: ANS-VMW-ALB, Qty: 16) for the base year (Period of Performance: 1/26/26 – 1/25/27), with four identical option years extending through 1/25/2031. The AFTC justifies the limited sources approach under FAR 8.405-6(b)(1), asserting that VMware is peculiar to one manufacturer and that the software represents the entirety of the virtual infrastructure currently operating on all agency networks. The justification explains that switching to alternative infrastructure would require complete redeployment, creating significant duplication of costs, labor, training, and potential downtime that would not be recovered through competition. Market research was conducted through mandatory sources (ESI—limited to Department of Navy, GSA 2GIT, and NASA SEWP), but yielded no responses; a new Department of Air Force Blanket Purchase Agreement (BPA HC108425A0002) for VMWare was subsequently identified as the vehicle for this acquisition. The Contracting Officer determined the anticipated cost represents fair and reasonable value, with pricing based on commercial item analysis consistent with FAR Part 15.404-1(b). The document was coordinated on 9 January 2026 and approved on 11 February 2026.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Limited Sources Justification and Approval (J&A)

March 2018 Page 2 of 7

( See guidance at the end of this document for completing the following sections. )

I. Contracting Activity.

The Contracting organization that is responsible for the proposed contract action is the Air Force Test Center (AFTC) Directorate of Contracting, Specialized Contracting Division, AFTC/PZZG, 5 South Wolfe Avenue, Edwards AFB, CA The Contracting Officer for this acquisition is Jenna Jacobson. This is a "Justification to Use Brand Name Restriction". 93524-1185

II. Nature and/or description of the action being processed.

The CTF has a requirement to purchase VMWare Broadcom Licenses and renewal for 5 years.

III. Description of supplies/services required to meet agency needs.

Broadcom/VMWare Licenses VMware Cloud Foundation Base Year Part #: VCF-CLD-FND Qty: 2,136 VMware Avi Load Balancer Part: ANS-VMW-ALB Qty: 16 PoP: 1/26/26 - 1/25/27

VMware Cloud Foundation Option Year 1 Part #: VCF-CLD-FND Qty: 2,136 VMware Avi Load Balancer Part: ANS-VMW-ALB Qty: 16 PoP: 1/26/27 - 1/25/28

VMware Cloud Foundation Option Year 2 Part #: VCF-CLD-FND Qty: 2,136 VMware Avi Load Balancer Part: ANS-VMW-ALB Qty: 16 PoP: 1/26/28 - 1/25/29

VMware Cloud Foundation Option Year 3 Part #: VCF-CLD-FND Qty: 2,136 VMware Avi Load Balancer Part: ANS-VMW-ALB Qty: 16 PoP: 1/26/2029 - 1/25/2030

VMware Cloud Foundation Option Year 4 Part #: VCF-CLD-FND Qty: 2,136 VMware Avi Load Balancer Part: ANS-VMW-ALB Qty: 16 PoP: 1/26/2030 - 1/25/2031

March 2018 Page 3 of 7

IV. Identification of the justification/rationale for limiting sources and demonstration of the contractor's unique qualifications to provide the required supply/service.

FAR 8.405-6 requires an ordering activity to justify its actions when restricting consideration of schedule contractors to fewer than required in FAR 8.405-1.

FAR 8.405-6(b)(1), “The item is peculiar to one manufacturer. A brand name item, whether available on one or more schedule contracts, is an item peculiar to one manufacturer.”

This software is the entirety of the virtual infrastructure that is currently operating on all of our networks. To overcome the restricted consideration, the agency would be required to completely redeploy the entire virtual infrastructure for all of our networks. There could potentially be all kinds of issues with trying to deploy different applications for the virtual infrastructure. No other software is compatible with the current infrastructure and there would be a significant duplication of cost/labor/training/possible downtime that would be associated with switching to another virtual infrastructure product which would not be recovered through competition.

V. Determination by the ordering activity Contracting Officer that the order represents the best value consistent with

FAR 8.404(d).

The Contracting Officer has determined that the anticipated cost to the Government for this acquisition will be fair and reasonable, and the proposal will be evaluated using price analysis for commercial items in accordance with FAR Part 15.404-1(b). The proposed price will be compared to any other companies or agencies that may have previously purchased the same or similar items. These items have been determined to be commercial items; therefore, IAW FAR 15.403-4, certified cost and pricing data is not required. Additionally, the initial BPA prices were considered fair and reasonable prior to the award of the contract.

VI. Description of the market research conducted and the results, or explain why market research was not conducted.

The CTF reached out to Broadcom to provide the quote needed. Market Research was conducted and the requirement is available through ESI, a mandatory source, however it is only open to DoN. Therefore, Contracting posted a solicitation to GSA 2GIT (mandatory) and NASA SEWP respectively, but no responses were received. As Contracting continued to do market research, the Government discovered that there was a new DAF BPA for VMWare IAW the Department of the Air Force (DAF) Software as a Service (SaaS) Procurement and Usage Requirements Memorandum, section b. The BPA number is

HC108425A0002.

VII. Other facts supporting the justification.

N/A

VIII. Actions the agency may take to remove or overcome any barriers that led to the restricted consideration before any subsequent acquisition for the supplies or services.

In the future, the Government will assess whether it is in the best interest of the Government to potentially transition to another software.

IX. Certification by the Contracting Officer.

As evidenced by my signature above, I have determined this document to be both accurate and complete to the best of my knowledge and belief.

X. Certification by the technical/requirements personnel.

As evidenced by my signature above, I certify that any supporting data contained herein, which is my responsibility, is both

March 2018 Page 4 of 7 accurate and complete.

March 2018 Page 5 of 7

GUIDANCE

I. Contracting Activity.

Fully identify the contracting activity responsible for the proposed contracting action. Include the name/phone number of the Contracting Officer. Specifically identify as a “Limited Sources” Justification. Identify purchase request number, if applicable.

II. Nature and/or description of the action being processed.

State whether the action is a new order or by modification to an existing order. Identify the GSA schedule number, the Blanket Purchase Agreement (BPA) number, the order number for the current action, and the Contactor(s). Indicate the Period of Performance (PoP). Also identify the type of the order/line items on the order (e.g. Firm Fixed Price, Labor Hour, etc).

III. Description of the supplies/services required to meet agency needs.

Specifically describe the supplies and/or services to be acquired including the price and quantity of each item in the order and state the total estimated value of the order. For services, state whether the services are performance-based and, if not, provide rationale for not being performance based. Also state the delivery/performance schedule/period for the items under the order.

IV. Identification of the justification/rationale for limiting sources and demonstration of the contractor's unique qualifications to provide the required supply/service.

This section is normally the most detailed part of the justification. To assist you in preparing this justification, an introductory sentence and the four circumstances of FAR 8.405-6 that justify restricting the number of schedule holders are provided below. Select the appropriate cite, then provide, in narrative form, a detailed explanation supporting the specific circumstance cited for limiting the number of schedule holders.

(Introductory sentence) FAR 8.405-6 requires an ordering activity to justify its actions when restricting consideration of schedule contractors to fewer than required in FAR 8.405-1 or 8.405-2.

After selecting the appropriate cite, next select one of the four sentences below and provide a detailed explanation supporting the specific circumstance cited.

FAR 8.405-6(a)(1)(i)(B), “Only one source is capable of responding due to the unique or specialized nature of the work”. (Provide a detailed justification with supporting documentation, as evidence of the “unique or highly specialized” nature of the procurement.

The user/customer typically provides this supporting information. Recommend attaching supporting documentation to the back of the document. General statements are not acceptable.)

FAR 8.405-6(a)(1)(i)(C), “The new work is a logical follow-on to an original Federal Supply Schedule order provided that the original order was placed in accordance with the applicable Federal Supply Schedule ordering procedures.” The original order was not issued under sole source or limited source procedures. (Provide details on the previously competed order and explain how this order is a logical follow-on to that order. Explain fully the connection between the previous work/order and the current one.

The user/customer typically provides this supporting information. General statements are not acceptable.)

FAR 8.405-6(a)(1)(i)(A), “An urgent and compelling need exists, and following the ordering procedures would result in unacceptable delays.” (Provide a detailed justification with supporting documentation that explains the exact urgency of the requirement and the schedule impact if time were to be taken to follow FSS ordering procedures. The user/customer typically provides this supporting information. Recommend attaching supporting documentation to the back of the document. General statements of urgency are not acceptable.)

FAR 8.405-6(b)(1), “The item is peculiar to one manufacturer. A brand name item, whether available on one or more schedule contracts, is an item peculiar to one manufacturer.” (Brand name specifications should not be used unless the particular brand name, product or feature is essential to the Government's requirements. Therefore, explain why the particular brand item is essential to the Government's requirements, and why other companies' similar items, or products lacking the particular feature, do not meet, or

March 2018 Page 6 of 7 cannot meet, or cannot be modified to meet, the agency's need. The user/customer typically provides this supporting information.

General statements are not acceptable.)

V. Determination by the ordering activity Contracting Officer that the order represents the best value consistent with

FAR 8.404(d).

This section needs to be tailored based upon whether the order is for supplies/services not requiring a statement of work (FAR 8.405-1) or if the order is for services requiring a statement of work (FAR 8.405-2).

For FAR 8.405-1 orders the best value determination needs to be based upon the supply or service offered under MAS contracts by surveying at least three schedule contractors through the GSA Advantage! on-line shopping service, or by reviewing the catalogs or price lists of at least three schedule contractors. The ordering Contracting Officer's review of the Contractor's price list(s) and any price reductions sought is also required. (Contracting Officer should seek additional price discounts/concessions based on the specific order requirements on all orders over the micro-purchase threshold.) In addition to price, when determining best value, the ordering activity may consider, among other factors, past performance, special features of the supply or service required for effective program performance, trade-in considerations, probable life of the item selected as compared with that of a comparable item, warranty considerations, maintenance availability, environmental and energy efficiency considerations, and delivery terms.

When an order contains brand name specifications, the Contracting Officer shall post the Request for Quote (RFQ) along with the basis of the justification as required by FAR 8.405-6(b)(3).

For FAR 8.405-2 orders for services requiring a statement of work, FAR 8.405-2(d) requires that an evaluation be performed based on the criteria provided to the schedule contractors. Therefore, the justification must address how the FAR 8.404(d) requirement for an evaluation of the proposed level of effort and mix of labor will be conducted and include a statement that the Contracting Officer will perform a price reasonableness determination as part of the best value determination.

VI. Description of the market research conducted and the results, or explain why market research was not conducted.

Discuss market research that was conducted among schedule holders and the market research results that led to the conclusion to go sole source or to limit the number of schedule holders to be solicited. The narrative in this section should provide a high level of confidence that the requirements of 8.405-1 and 8.405-2 could not be met. If no market research was conducted, state so and provide the rationale.

VII. Other facts supporting the justification.

When FAR 8.405-6(a)(1)(i)(C) is cited for an follow-on acquisition as the basis for the justification, include an estimate of the cost that would be duplicated and the basis and derivation of the estimate, or provide details on why a delay to solicit additional schedule holders would be unacceptable.

Provide any other facts supporting the Limited Sources Justification.

VIII. Actions the agency may take to remove or overcome any barriers that led to the restricted consideration before any subsequent acquisition for the supplies or services.

Describe all efforts to be taken to remove or overcome any barriers that preclude the agency from meeting the requirements of FAR 8.405-1and FAR 8.405-2 before any subsequent acquisition for the supplies or services is made. If no actions are planned, so state and provide reasons.

IX. Certification by the Contracting Officer.

The contracting officer's signature on the signature page evidences that he/she has determined this document to be both accurate and complete to the best of his/her knowledge and belief.

X. Certification by the technical/requirements personnel

March 2018 Page 7 of 7

As evidenced by their signatures on the signature page, the technical/requirements personnel have certified that any supporting data contained herein which is their responsibility is both accurate and complete.

File details come from the government source that posted it. Updated .