Project No.: GJKZ 09-0016A2
STATEMENT OF WORK
FOR
Project No. GJKZ 09-0016A2
PROVIDE ADVANCED GAS METERS
18 FACILITIES
FAIRCHILD AIR FORCE BASE, WASHINGTON
Date: 24 Feb 10
Revised 10 March 10
1. GENERAL: The contractor shall provide wiring connections to gas meters for Buildings
1409, 2005, 2007, 2040, 2045, 2097, 2163, 2170, 2249, 2380, 2447, 2451, 2464, 2465, 1033, 1037, 2090, & 2050 at Fairchild AFB WA.
2. PROJECT DATA:
A. Project Scope Description:
The contractor shall provide connections of Government installed gas meters at multiple building at Fairchild AFB WA.
1. Buildings 1033, 1037, 2040, 2163, 2170, 2447, 2465 and 2050 have existing
Alerton control systems. The gas meters shall be connected to the control system for remote meter reading. Contractor shall provide all programming and graphics for gas meter reading at the EMCS Office Building 2451. Trending of all meter readings in (minimum 15 minute intervals) should be set up on EMCS computer and verified that they are working properly.
a. Building 1033 and 1037 are owned by the Air National Guard.
Provide all wiring from the meter to the control cabinet. The Guard will provide additional controller in each building, ATS will provide programming and graphics at the ANG HVAC Shop.
b. Building 2050 has conduit already run from the meter location straight down the hall to a control cabinet. It is approximately a 200 foot run.
2. Buildings 1409, 2005, 2007, 2045, 2090, 2097, 2249 ( 2 Meters), 2380, 2451 and 2464 have no controls. Wiring shall be provided from the gas meter to the nearest existing EMCS controller. No programming or connection is required.
Label wires with suitable markings for future connection.
a. 2380 has a pulse meter and wiring already installed.
Amendment 1, Attachment 1
b. Delete 2045 and 2090 from building list.
c. Building 2380 has conduct and wire run from the gas meter to the existing controller. Ensure the cable is the proper size, replace as required and mark the cable for future connection.
3. DESCRIPTION OF WORK AND SERVICES:
A. All wiring shall be installed per the National Electric Code.
B. Locations of buildings and gas meters are shown on the attached site drawings
Attachment 1. building floor plans. The locations shall be field verified.
C. All wiring shall be in conduit except as noted below. Wire Cable shall be 18 awg, 2 conductor shielded. Plenum rated cable is required for certain open air installations. Conduit shall be rigid steel when used for underground transitions exposed outdoors, PVC when underground and EMT when inside a building. EMT conduit maybe also be used for the exterior of buildings but shall be kept to a minimum. Underground conduit shall be buried at a minimum of 24 inches. All conduits run either on the exterior or the interior of the building will be painted to match the adjacent color. In mechanical rooms no painting is required.
D. For buildings with existing EMCS controls, provide final as-built control drawing of meter connection to Alerton controllers. This will consist of updating the existing drawing on file in the EMCS office. For the final inspection, the contractor will provide the Government inspector information on the routing of conduit and wiring so the government will document this installation. These
Government drawings will suffice as the project as-built drawings.
E. Some work is being done in restricted/controlled area. The Government will provide escorts for these buildings.
4. COMMISSIONING:
A. On meters connected to EMCS controllers, the contractor shall make observations, adjustments, calibrations, and measurements, set the time and make any necessary corrections to ensure the meter is recording properly.
5. TRAINING:
A. The contractor shall demonstrate the configuration, operation, and maintenance of the meter. The training shall also include: troubleshooting and diagnostic procedures, repair instructions, preventive maintenance procedures and schedules, testing, and calibration.
6. SUBMITTAL QUANTITIES
SUBMITTAL DESCRIPTION NUMBER OF
COPIES
Final O&M Submittal
Updated existing control page, 11 x 17 with Sequence of Operations
ATTACHMENTS:
1. Base Gas Distribution Map
2. Building summary scope of work from site walk thru 9 Mar 10