AJXF 09-1508

Renovate/Upgrade 8 restrooms in building 1558

(SAB)STATEMENT OF WORK REVISED FOR ADDITIONAL RESTROOMS

2 July 2009

GENERAL: Furnish all supervision, plant labor, transportation, equipment, materials, and perform all operations necessary to upgrade the additional 2 male, 2 female, and 1 unisex restrooms to include a shower at Hangar 1 and to meet ADA compliance mandates. The dimensions of the restrooms and the location of new applicable fixtures in the restrooms must be designed and installed in accordance with all applicable ADA requirements. The floors and walls of the restroom must be tiled according to patterns and color schemes established by base standards. A new drop ceiling shall be installed to include new light fixtures. The fire sprinkler heads will be extended down to the new ceiling height. The fixtures and sanitary accessories, such as toilets, urinals, sinks, and floor drains shall be installed in compliance with ADA requirements where applicable. The rerouting of supply piping and drains, rough-ins and piping of new drains are to provide proper drainage for the restrooms and must meet BOCA standards and requirements. New toilet partitions (and urinal dividers for the men’s room) must be installed for each restroom. New light fixtures and mirrors shall be installed over the new countertops and sinks. Install new GFI duplex receptacles above the sinks for the restrooms. Perform all operations necessary to completely tile the floor and walls. New personnel doors shall be installed for the entrances to restrooms. Restroom tile colors and patterns shall be in accordance with established base standards. Provide and install water heater in a designated area to accommodate the new power plant restroom configuration as necessary. Refer to design concept on attached partial prints provided by 316 CES/CECS. These prints can be used as required layout and plan for the new restroom configurations as necessary. Any possible asbestos containing material shall be tested prior to any demolition work. If the asbestos testing yields positive results, the proper abatement measures shall be addressed.

1.0 GENERAL REQUIREMENTS:

1.1 Provide an approved electrical, lighting, plumbing, and ventilation plan prior to starting site work.

1.2 Provide plastic to seal off construction areas and cover walls as required in certain areas.

1.3 Keep the work areas clean and neat on a daily basis.

1.4 Provide protection for personnel walking through the work areas and ensure that adequate safety measures and controls are in place.

2.0 EXISTING CONDITIONS:

2.1 Provide dumpsters so they are situated where disruption to the flow of personnel and vehicular traffic is minimized.

2.2 Remove all demolition debris from both restrooms as needed.

2.3 Saw cut the concrete floor as required to install new PVC piping in the all restroom drains and to accommodate the connection for a venting system. Demo wall as required to install new PVC piping in all restrooms

2.4 Demo all sinks, mirrors, urinals, urinal partitions, toilets, and stalls in both restrooms Hangar 1.

2.5 Demo the required vent system, drainage fittings, supply mains, and associated supply and drainage components in all restrooms of building 1558.

2.6 Demo existing floor drains, building drainage components, waste piping, and sink piping to accommodate the requirements of renovating the restrooms of building 1558.

2.7 Demo all water supply piping as required for building 1558.

2.8 Demo the drop ceiling in all restrooms in building 1558.

2.11 Demo soap, paper towel, and toilet dispensers in both restrooms.

2.10 Demo all existing electrical and light fixtures.

3.0 CONCRETE:

3.1 Pour 3000 psi concrete and install reinforcement, as needed, once the required new drain lines have been installed, and tested. The contractor shall insure that the floor is level and ready to receive new tile.

4.0 MASONRY:

4.1 Grout the floor and walls - including around sinks, urinals, and toilets - for installing tile.

4.2 Install a marble-type threshold in the doorways of all restrooms.

8.0 DOORS AND WINDOWS:

8.2 Provide and install new metal personnel doors, closures, locksets, kick plates, and high-frequency-use door hinges, for the entrances to HVAC and power plant restrooms. (to include frames).

9.0 FINISHES:

9.1 Provide and install waterproof type gypsum wallboard for required walls. All new drywall shall be taped and finished.

9.2 Provide and install new floor tile and wall tile. The wall tile shall be placed from the floor to the wanes coat height (5 ft) in the restrooms. Work shall include three-color group accents, in accordance with the base standards.

9.3 Provide and install suspended ceiling system for all restrooms and shower areas, approximately 12” below existing ceiling.

9.4 Frame in a metal stud bulkhead laminated with moisture resistant gypsum board above the HVAC plant’s showers.

9.5 Prime and paint new doors and frames.

9.6 Provide one large mirror installed above the sinks for all restrooms.

10.0 SPECIALTIES:

10.1 Provide and install new floor mounted partitions and wall mounted urinal screens for all male restrooms.

10.2 Provide and install a waste receptacle with towel dispensers for each restroom (minimum of 18 gallon capacity is required).

10.3 Provide new restroom, signs (handicap-type signs required) for each restroom. Provide door stops for all doors.

10.4 Provide new toilet paper holders for each water closet.

15.0 MECHANICAL:

15.1 Provide fiberglass-insulated, copper hot and cold water distribution piping from a nearby supply main to each restrooms.

15.2 All piping shall be properly sized for the fixtures or units they serve. All terminations of the pipe shall include water hammer arresters or air chambers.

15.3 Ball-type valves shall be installed at an accessible location above the ceiling to isolate the restrooms independently. All piping will terminate with the appropriate shut-off valves. Provide and install chrome angle valves for the sinks.

15.4 Provide appropriately sized drain lines, vent systems, floor drains and p traps.

15.5 Provide angle valve and p trap protectors as required by ADA.

15.6 Provide floor drains in the each restroom.

15.7 Provide and install urinals with automatic flush-o-meters in each male restroom.

15.8 Provide and install 1 handicap ADA water closet, in each restroom.

15.9 Provide and install water closets and seats in each Men’s restroom, and each Women’s restroom.

15.10 Provide and install prefabricated Corion countertops with the same number of sink bowls that were removed, with automatic faucets, in each restroom. Countertops shall have splashguards, and be handicap accessible.

15.11 Provide a new exterior exhaust fan for each restroom. Fan shall be wired to come on when the room lighting is turned on.

15.12 Lower existing sprinkler heads and replace sprinkler heads and escutions with new as required to provide sprinkler fire suppression below the new drop ceiling height as required per NFPA code.

15.13 Provide one new shower unit in the HVAC plant restroom.

15.14 Provide and install a new 30 gallon water heater in the power plant restroom.

16.0 ELECTRICAL:

16.1 Provide and install new 2’x 2’ fluorescent light fixtures for all restrooms.

16.2 Provide receptacles under all sets of restroom sinks for the automatic faucets.

16.3 Provide one duplex, GFI receptacle over each sink in all restrooms.

16.4 Provide one incandescent light fixture over shower stall in HVAC plant restrooms.

REQUIRED SUBMITTALS:

SUBMITTALS: Provide manufacturer’s catalog data, technical data and samples for the following items

IAW the contract:

1. GFI receptacles for the restrooms

2. Electrical, lighting, ventilation, and plumbing plans

3. Doors, frames, closures, and hardware

4. Sinks, automatic faucets

5. All finishes to include suspended ceiling tile, drywall, paint colors

6. Floor and wall tiles, mirrors, floors drains

7. All restroom dispensers, to include tissue, soap, and waste/towel receptacles

8. Restroom exhaust system

9. New ceiling heaters

10. Water closets, urinals, automatic urinal flush meters, countertops

11. High-intensity distribution lights, fluorescent light fixtures, incandescent light fixtures, wiring, switches, and controls

12. Corion countertop with sinks