About this file

This is a set of architectural drawings from Grimm + Parker Architects for a window replacement project at two Rappahannock Community College (RCC) campuses - the Glenns Campus at 12745 College Drive in Glenns, Virginia and the Warsaw Campus at 52 Campus Drive in Warsaw, Virginia. The project, identified as DEB #260-B4260-073, involves replacing existing windows with new aluminum storefront systems at both campus locations. The bid set is dated February 24, 2025 and includes detailed architectural plans, demolition plans, elevations, and frame details for both buildings. The scope includes removal of existing windows, frames, clips, sealants and blocking, and installation of new storefront systems with manual translucent roller shades and blackout shades in specified locations.

The project falls under the Virginia Community College System and must comply with the 2021 Virginia Existing Building Code, 2021 Virginia Construction Code, and 2024 Virginia Construction & Professional Services Manual. Both buildings are classified as Type IIB construction with Business (B) occupancy. The project is exempt from the High Performance Buildings Act as the renovated area is less than 5,000 gross square feet. The drawings note lead and asbestos disclosure requirements, with the owner responsible for asbestos abatement prior to construction. Technical specifications include 1" insulating glass systems with low-E coating and custom color exterior sealants to be selected by the architect.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A

T e l:

-2

-5

DEB #

260-B4260-073

RC

C

5 C oll eg e D riv e, Gl en ns , V irg ini a

2/24/2025

BID SET

GP #22006.24

VIRGINIA COMMUNITY COLLEGE SYSTEM

300 Arboretum Place, Suite 200 Richmond, Virginia 23236

OWNER ARCHITECT

D E S I G N T E A M

BID SET 2/24/2025

DATE DESCRIPTION

X. TONG WANG, RA

Capital Outlay Program Manager twang@vccs.edu Tel: (804) 819-4919

RAPPAHANNOCK COMMUNITY COLLEGE

Glenns Campus 12745 College Drive, Glenns, Virginia

COLLEGE

RICHARD P. LEWTER

Facilities Manager,Glenns Campus

RLEWTER@rappahannock.edu Tel: (804) 758-6840

GRIMM + PARKER ARCHITECTS

123 East Main St, Second Floor Charlottesville, Virginia 22902

Annette McDaniels AIA, CCCA, LEED AP BD+C Associate Principal amcdaniels@gparch.com Tel: (434) 270-0141

02/21/2025

RCC GLENNS CAMPUS

WINDOW REPLACEMENT

12745 College Drive, Glenns, Virginia

RCC - WARSAW CAMPUS

WINDOW REPLACEMENT

52 Campus Dr, Warsaw, Virginia

LIST OF DRAWINGS

TS TITLE SHEET

ARCHITECTURAL

A002 OVERALL FIRST FLOOR PLAN

D101 OVERALL FIRST FLOOR DEMOLITION PLAN

A101 PARTIAL FIRST FLOOR PLAN

A102 PARTIAL FIRST FLOOR PLAN

A201 BUILDING ELEVATIONS

A305 FRAME ELEVATIONS

LIST OF DRAWINGS

TS TITLE SHEET

ARCHITECTURAL

A002 OVERALL FIRST FLOOR PLAN

A003 OVERALL FIRST FLOOR PLAN - ANNEX

D101 OVERALL FIRST FLOOR DEMOLITION PLAN

D102 OVERALL FIRST FLOOR DEMOLITION PLAN - ANNEX

A101 PARTIAL FLOOR PLAN

A102 PARTIAL FLOOR PLAN

A103 PARTIAL FLOOR PLAN

A201 BUILDING ELEVATIONS

A202 BUILDING ELEVATIONS - ANNEX

A305 FRAME ELEVATIONS

VICINITY MAP LOCATION MAP

EXISTING CLASSROOM BUILDING

RAPPAHANNOCK

COMMUNITY COLLEGE

E LEWIS B PULLER MEM HWY

C O

LLE

G

E D

R

H W

Y

C O

LLE

G

E D

R

E LEWIS B PULLER

MEM HWY

HWY 17

RAPPAHANNOCK COMMUNITY COLLEGE

ABBREVIATIONS

VICINITY MAP LOCATION MAP

EXISTING CLASSROOM

BUILDING

RICHMOND ROAD

H W

Y

EXISTING ANNEX

BUILDING

DEB PROJECT CODE 260-B4260-073

W

IN

DO

W

R

EP

LA

CE

ME

NT

RAPPAHANNOCK COMMUNITY COLLEGE

WINDOW REPLACEMENT

CS

CO

MB

IN

ED

C

OV

ER

S

HE

ET

GLENNS CAMPUS AND WARSAW CAMPUS

EARTH

GRAVEL

CONCRETE

CONCRETE MASONRY UNITS

SOLID CONCRETE

MASONRY UNITS

BRICK

WOOD-FINISHED

WOOD ROUGH

PLYWOOD

GYPSUM BOARD

ACOUSTIC TILE

STEEL - LARGE SCALE

ALL METALS - SMALL SCALE

GLASS - LARGE SCALE

BATT INSULATION

RIGID INSULATION

CERAMIC TILE

CARPET

Above finished floor AFF Acoustic ACST Acoustic Panel Ceiling APC Addendum ADD Alternate ALT Aluminum AL Angle L Approximate APPROX Architecture, ARCH architectural Asbestos ASB Asphalt ASPH Assistant ASST Association ASSN Automatic AUTO Average AVG Base plate BP Basement BSMT Beam BM Bearing BRG Bedroom BR Benchmark BM Board BD Boiler BLR Bottom BOT Brick BRK Building line BL Building BLDG Built-up-roof BUR Cabinet CAB Carpet CPT Catalog CAT Ceiling height CH Ceiling CLG Center CTR Centerline CL Ceramic Tile CT Ceramic CER Chalkboard CB Clear CLR Closet CLO Coated CTD Cold rolled CR Column COL Company CO Composition COMP Concrete Masonry Unit CMU Concrete CONC Construction joint CJ Construction CONSTR "Continue, Continuous" CONT Corridor CORR Countersink CSK Cubic CU Curve(d) CRV Dampproofing DP Degree DEG Department(al) DEPT Detail DET Diagonal DIAG Diameter DIA Dimension DIM Dishwasher DW Dispenser DISP Door DR Double DBL Double-hung DH Down DN Downspout DS Drain DR Drawing DWG Each EA East E Electric Water Cooler EWC "Electric, electrical" ELEC Elevation EL Elevator ELEV Engineer ENGR Entrance ENTR

Maximum MAX Mechanical MECH Membrane MEMB Men M Metal MET, MTL Mezzanine MEZZ Minimum MIN Mirror MIR Miscellaneous MISC Mounted MTD Mounting MTG Necessary NEC Noise-reduction NRC coefficient Nominal NOM Non Combustible NC, NONCOM North N Not in Contract NIC Not to scale NTS Not available NA Number NO Office OFF On center OC Opening OPNG Opposite OPP Outside diameter OD Overall OA Overhead OVHD Page P Painted PTD Pair PR Panel PNL Partition PTN Percent PCT Perforate(d) PERF Permanent PERM Perpendicular PERP Piece PC Plastic Laminate PLAM Plastic Laminate PLAS.LAM Plate PL Plumbing PLMB Plywood PLYWD Point PT Polyvinyl chloride PVC Precast PRCST Prefabricated PREFAB Preliminary PRELIM Preparation, prepare PREP Program PRGM Projection Screen PS Project PROJ Property PROP Public Address PA Quality control QC Quality QUAL Quantity QTY Quarry Tile QT Radius RAD Rain Leader RL Received RCVD Receptacle RCPT Receptionist RECPT Recess(ed) REC Refer, reference REF Refrigerate, refrigerator REFR Reinforce REINF Reinforced concrete RC Remove RMV Repair RPR Required REQD Revise, revision REV Right hand RH Road RD Roof Drain RD Roof RF Roofing RFG Room RM Rubber tile floor RTF

Rubber RBR Schedule SCHED Schematic SCHEM Section SECT Service SVCE "Sheet, sheeting" SHT Shower SH Siding SDG Similar SIM Slope SL Sound-transmission STC class South S Speaker SPKR Specification SPEC Sprinkler SPR Square SQ Stainless steel SS Standard STD Standpipe SP Steel STL Storage STOR Structural Glazed SGFT Facing Tile Structural, structure STRUCT Substitute SUBST Surface SURF Suspend(ed) SUSP Switch SW Symmetrical SYM System SYS Tackboard TB Tackstrip TS Telephone TEL Television TV Temporary TEMP Terrazzo TER Thick THK Through THRU Toilet T Tongue and groove T&G Top and bottom T&B Top chord TC Top of Masonry Parapet TMP Top of Bearing TOFB Top of Steel T.O.S.

Topping TOPG Total TOT Transformer XFMR Transom TR Transparent TRANS Tread TRD Threshold THRESH Typical TYP Underground UG Underwriters UL Laboratories Unfinished UNF Unit Ventilator UV Unless Otherwise Noted UON Urinal UR US Gypsum Company USG Verify in Field VIF Vertical VERT Vestibule VEST, V Vinyl Reducing Strip VRS Vinyl Composite Tile VCT Vinyl asbestos tile VAT Wardrobe WARD Water closet WC Waterproof WP Weight WT Welded WLD Welded Wire Mesh WWM With W/ Without W/O Women W Wood WD Wrought Iron WI

Equal EQ Equipment EQUIP Exhaust EXH Existing EXIST Existing to Remain ETR Expansion joint EXP JT Exposed EXP Exterior EXT Fabricate FAB Face of Stud F. OF S.

Fan Coil Unit FCU Fiberglass-reinforced FRP plastics Finish FIN Finished Floor FF Fire Extinguisher FE Fire Extinguisher & FEC Cabinet Fire Retardant Treated FRT Fireproof FPRF Fixture FXTR Flange FLG Flashing FL Floor FL Floor drain FD Flooring FLG Fluorescent FLUOR Footing FTG Foundation FDN Furnish(ed), furniture FURN Furring FURR Gage (gauge) GA Galvanize(d) GALV Galvanized Iron GALVI Glazed Wall Tile GWT Grab Bar GB Grade GR Gravel GVL Gypsum Wallboard GWB Gypsum GYP Handicapped HC Hardware HDW Heating ventilating and HVAC air conditioning Height HGT High Point HPT High Performance HP High Performance HPC Coating Hollow Metal HM Horizontal HORIZ Include(d), inclusive INCL Incorporated INC Information INFO Inside diameter ID Install(ed), installation INSTL Insulation INSUL Interior INT Janitor JAN Joint JT Joist J, JST Junction box JB Knock down KD Laboratory LAB Lavatory LAV Left Hand LH Left L Length LG Level LVL Light LT Machine MACH Maintenance MAINT Manager MGR Manual MNL Manufacturing MFG Markerboard MB Masonry opening MO Masonry MSNRY Master bedroom MBR Material MATL

B101a

SIM

SIM

A102 A103

DEPT.

ADD

GRID LINES

SECTIONS

DETAIL NUMBER

SHEET NUMBER

DETAIL NUMBER

SHEET NUMBER

DETAILS IN PLAN/SECTION

ROOM NUMBER

DOOR NO. ON PLAN

H.M. FRAME NO.

ON PLAN

REVISION: TYPE =

A.S.I/P.R./C.C.D./ADD.

CASEWORK

(FURNISHING PLANS ONLY)

ALUM. FRAME/WINDOW

TYPE

WALL TYPE

# # INTERIOR ELEVATION

DETAIL NUMBER

SHEET NUMBER

A3ROOM NAME

B101a

REF SHEET

NUMBER

REF SHEET NUMBER

NOT IN SCOPE

NOT IN SCOPE

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

TS

TI

TL

E S

H E

E T

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

LIST OF DRAWINGS

TS TITLE SHEET

ARCHITECTURAL

A002 OVERALL FIRST FLOOR PLAN

D101 OVERALL FIRST FLOOR DEMOLITION PLAN

A101 PARTIAL FIRST FLOOR PLAN

A102 PARTIAL FIRST FLOOR PLAN

A201 BUILDING ELEVATIONS

A305 FRAME ELEVATIONS

SYMBOLS OF MATERIALS

ABBREVIATIONS

1/16" = 1'-0"TSA201

A13 CODE STUDY PLAN - FIRST FLOOR

VIRGINIA COMMUNITY COLLEGE SYSTEM

300 Arboretum Place, Suite 200 Richmond, Virginia 23236

OWNER ARCHITECT

VICINITY MAP LOCATION MAP

LEAD DISCLOSURE STATEMENT

AN INSPECTION TO IDENTIFY LEAD CONTAINING OR COATED BUILDING COMPONENTS HAS BEEN CONDUCTED AND CAN BE FOUND IN THE PROJECT SPECIFICATIONS. THIS REPORT IS PROVIDED FOR THE CONTRACTOR’S USE AND MAY NOT BE ALL INCLUSIVE. IT IS THE CONTRACTOR’S RESPONSIBILITY TO COMPLY WITH ALL VIRGINIA OCCUPATIONAL SAFETY AND HEALTH (VOSH) REGULATIONS AS THEY PERTAIN TO EMPLOYEE EXPOSURES TO LEAD. ALL LEAD AND LEAD-COATED BUILDING COMPONENTS SHALL BE RECYCLED

TO THE EXTENT POSSIBLE.

DRAWING KEY

EXISTING CLASSROOM BUILDING

HIGH PERFORMANCE BUILDNG ACT

IN ACCORD WITH THE HIGH PERFORMANCE BUILDINGS ACT, THE BUILDING IS EXEMPT FROM COMPLIANCE

BECAUSE THE RENOVATED BUILDING AREA IS NOT GREATER THAN 5,000 GROSS SQUARE FEET.

PROJECT NAME AND LOCATION

NAME RAPPAHANNOCK COMMUNITY COLLEGE - WINDOW REPLACEMENT

STREET ADDRESS 12745 COLLEGE DRIVE

COUNTY GLOUCESTER COUNTY

CITY, STATE GLENNS, VA

PROJECT DESCRIPTION: WINDOW REPLACEMENT ON AN EXISTING BUILDING AT RCC.

THERE IS NO WORK INSIDE THE BUILDING - NO CHANGE IN OCCUPANCY OR OCCUPANTS

APPLICABLE CODES

BUILDING CODE 2021 Part 2, VIRGINIA EXISTING BUILDING CODE (VEBC), Level 1

2021 VIRGINIA CONSTRUCTION CODE (VCC)

2024 VIRGINIA CONSTRUCTION & PROFESSIONAL SERVICES MANUAL (CPSM)

ACCESSIBILITY ADA90-TITLE II,Scoping Requirements of the Department of Justice’s 2010 ADA Standards for Accessible Design, dated September 15, 2010 and technical design are Chapters 1 and 3 thru 11 of Standards for Accessible and Usable Buildings and Facilities (ICC A117.1-2017) approved March 28, 2017

BUILDING USE AND CONSTRUCTION CLASSIFICATION

VCC

USE GROUP: B, BUSINESS 304.1

BUILDING AREA (PER VCC): 55,158 SF (92,000 SF ALLOWABLE)

PROPOSED CONSTRUCTION TYPE TYPE IIB (EXISTING)

ALLOWABLE BUILDING HEIGHT/STORIES: 75' (VCC TABLE 504.3), 3 STORIES (VCC TABLE 504.4)

ACTUAL BUILDING HEIGHT/STORIES: 20' MAXIMUM, 1 STORY

BUILDING VOLUME: 1,103,160 CUBIC FEET (EXISTING)

APPLICABLE CODES AND TABULATIONS

RAPPAHANNOCK

COMMUNITY COLLEGE

E LEWIS B PULLER MEM HWY

C O

LLE

G

E D

R

H W

Y

C O

LLE

G

E D

R

E LEWIS B PULLER

MEM HWY

HWY 17

RAPPAHANNOCK COMMUNITY COLLEGE

DEB PROJECT CODE 260-B4260-073

D E S I G N T E A M

RCC GLENNS CAMPUS

WINDOW REPLACEMENT

BID SET 2/24/2025

12745 College Drive, Glenns, Virginia

ASBESTOS DISCLOSURE STATEMENT

AN ASBESTOS INSPECTION WAS PERFORMED AND ACM WAS FOUND GENERALLY IN THE AREA INDICATED. THE ASBESTOS INSPECTION REPORT IS INCLUDED IN SECTION 02 80 00 IN THE PROJECT SPECIFICATIONS. THE OWNER SHALL SUBMIT AN APPLICATION FOR PERMIT TO HAVE THE ASBESTOS-CONTAINING MATERIALS ABATED BY A LICENSED ASBESTOS CONTRACTOR UNDER A SEPARATE CONTRACT USING APPROVED PROCEDURES PRIOR TO ISSUING A NOTICE TO PROCEED TO THE GENERAL CONTRACTOR. ANY ACM THAT IS TO REMAIN AND THE NEW NON ASBESTOS-CONTAINING MATERIAL SHALL BE LABELED ACCORDINGLY. THE ASBESTOS ABATEMENT CONTRACTOR SHALL MARK UP THE AS-BUILT DRAWINGS RESULTING FROM ITS WORK TO INCLUDE AREAS WHERE ASBESTOS WAS ABATED, AREAS WHERE ASBESTOS WAS ENCAPSULATED, AND AREAS WHERE ACM EXIST BUT WERE LEFT IN PLACE. THE GENERAL CONTRACTOR SHALL REVIEW AND CERTIFY THE LOCATIONS WHERE ACM WAS ABATED, AREAS WHERE ACM WAS ENCAPSULATED AND AREAS WHERE ACM WAS LEFT IN PLACE AS MARKED ON THE AS-BUILT

DRAWINGS AND WILL PROVIDE THE DRAWINGS TO THE ARCHITECT.

DATE DESCRIPTION

X. TONG WANG, RA

Capital Outlay Program Manager twang@vccs.edu Tel: (804) 819-4919

RAPPAHANNOCK COMMUNITY COLLEGE

Glenns Campus 12745 College Drive, Glenns, Virginia

COLLEGE

RICHARD P. LEWTER

Facilities Manager,Glenns Campus

RLEWTER@rappahannock.edu Tel: (804) 758-6840

GRIMM + PARKER ARCHITECTS

123 East Main St, Second Floor Charlottesville, Virginia 22902

Annette McDaniels AIA, CCCA, LEED AP BD+C Associate Principal amcdaniels@gparch.com Tel: (434) 270-0141

02/21/2025

N

GENERAL NOTE APPLICABLE TO ALL DRAWINGS - ITEMS AND CONDITIONS DETAILED, NOTED

OR OTHERWISE IDENTIFIED ON ONE OF THE SECTIONS OR DETAILS ARE APPLICABLE AND

BINDING TO ALL OTHER SECTIONS AND DETAILS FOR IDENTICAL OR SIMILAR CONDITIONS.

1. ALL CONSTRUCTION AND WORK REPRESENTED IN THE COMPLETE SET OF DOCUMENTS IS

ASSUMED TO BE NEW AND FURNISHED AND INSTALLED BY THE CONTRACTOR UNLESS

OTHERWISE NOTED.

2. THE DRAWINGS AND SPECIFICATIONS ARE COMPLIMENTARY AND WHAT IS REQUIRED BY

ONE SHALL BE AS BINDING AS IF REQUIRED BY ALL. NO DRAWING SHALL HAVE

PRECEDENCE ONE OVER THE OTHER. IN THE EVENT OF A CONFLICT IN THE DOCUMENTS,

THE CONTRACTOR SHALL SEEK THE INTERPRETATION OF THE ARCHITECT. THE

CONTRACTOR SHALL NOT PROCEED WITH WORK UNTIL SUCH INTERPRETATION IS

OBTAINED. IF THE CONTRACTOR PROCEEDS WITHOUT CLARIFICATION, THE CONTRACTOR

WILL BE RESPONSIBLE TO REMOVE AND REPLACE ANY WORK NOT CONFORMANCE WITH

THE ARCHITECT'S DIRECTION WITHOUT ADDITIONAL COST TO THE OWNER. IN THE EVENT

OF A CONFLICT IN THE DRAWINGS OR SPECIFICATIONS, BIDDERS SHALL SEEK

CLARIFICATION FROM THE ARCHITECT. RESOLUTIONS TO SUCH CONFLICTS WILL BE

ISSUED THROUGH ADDENDA TO THE BID DOCUMENTS. IF CLARIFICATION FROM THE

ARCHITECT IS NOT RECEIVED THROUGH AN ADDENDUM PRIOR TO THE RECEIPT OF BIDS,

THE BIDDER SHALL ASSUME THE MORE COSTLY REQUIREMENT APPLIES, AND THE

AWARDED CONTRACTOR SHALL SEEK CLARIFICATION FROM THE ARCHITECT PRIOR TO THE

EXECUTION OF THE WORK.

3. IF A CONFLICT EXISTS BETWEEN DRAWINGS OF DIFFERENT SCALES, CONSULT THE

ARCHITECT FOR CLARIFICATION.

4. IN THE ABSENCE OF A WRITTEN DIMENSION, OR IN CASE OF DOUBT AS TO THE PROPER

MEASUREMENT, CONSULT THE ARCHITECT FOR CLARIFICATION.

5. IF AN AREA OR SPACE IS SHOWN, BUT IS NOT CLEARLY DEFINED OR INDICATED BY NOTES, PROVIDE THE SAME MATERIALS AND FINISHES AS SCHEDULED OR DETAILED FOR AREAS

OF SIMILAR USE ELSEWHERE IN THE BUILDING,

6. SECTIONS INDICATED ARE INTENDED TO SHOW THE SPECIFIC CONSTRUCTION WHERE

REFERENCED AS WELL AS ESTABLISH THE GENERAL CONSTRUCTION DETAILS FOR

SECTIONS THROUGHOUT THE PROJECT WHICH DO NOT HAVE SPECIFIC SECTIONS DRAWN.

THE MOST SIMILAR SECTIONS TO BE ADAPTED TO ANY SECTIONS NOT DETAILED. ANY

SPECIFIC QUESTIONS CONCERNING CONSTRUCTION NOT ADEQUATELY COVERED BY THE

ABOVE SHOULD BE DIRECTED TO THE ARCHITECT DURING THE BIDDING.

7. TYPICAL DETAILS THROUGHOUT THE DRAWING SET TO APPLY FOR ALL APPLICABLE

CONDITIONS EVEN IF NOT SPECIFICALLY SHOWN OR REFERENCED.

8. ALL APPURTENANCES BUILT INTO OR THROUGH WALLS, INCLUDING DOORS, DUCTS,

WINDOWS, LOUVERS, GRILLES, MECHANICAL WORK, ETC. TO FIT TIGHT AND BE

THOROUGHLY SEALED AROUND PERIMETERS. WORK AT EXTERIOR WALLS TO BE FLASHED

OR OTHERWISE WATERPROOF SEALED.

9. FIELD CHECK ROUGH AND/OR FINISHED DIMENSIONS FOR ACCURATE FITTING OF

WINDOWS, AND OTHER INSTALLATIONS PRIOR TO SHOP OR FACTORY FABRICATION.

PROVIDE FILLER STRIPS, SCRIBE STRIPS, BASES, CLOSURE FINISHES AND TRIM FOR A

COMPLETE INSTALLATION.

10. EACH CONTRACTOR MUST REFER TO ALL DRAWINGS AND BE RESPONSIBLE FOR WORK

PERTAINING TO THEIR PARTICULAR TRADE. ALL CONTRACTORS MUST COORDINATE THE

WORK OF ALL TRADES AND FIELD CHECK AGAINST ANY CONFLICTS BETWEEN DRAWINGS.

REPORT CONFLICTS TO THE ARCHITECT FOR CLARIFICATION.

11. FOR THE PURPOSES OF BIDDING (UNLESS OTHERWISE NOTED), ALL SYMBOLS (LABELED /

TAGGED OR UNLABELED/UNTAGGED) WHICH ARE LOCATED ON THE

FURNISHING/EQUIPMENT PLANS TO BE CONSIDERED AS IN CONTRACT WORK TO BE

PROVIDED BY THE CONTRACTOR. ALL SYMBOLS LOCATED ON THE PLANS DENOTE EITHER

FURNITURE, EQUIPMENT, CASEWORK OR MILLWORK. WHERE A SYMBOL IS LOCATED ON

THE PLANS BUT IS NOT LABELED OR TAGGED TO A SCHEDULE, THE CONTRACTOR MUST

SEEK CLARIFICATION FROM THE OWNER OR ARCHITECT BEFORE PROCEEDING. FOR

PURPOSES OF BIDDING ONLY, IF CLARIFICATION CANNOT BE OBTAINED FROM THE OWNER

OR ARCHITECT THROUGH ADDENDUM PRIOR TO THE BID DATE, THE CONTRACTOR MUST

NEVERTHELESS INCLUDE THE ITEM IN QUESTION IN THEIR BID, CONSIDERING IT THE SAME

AS THE TAGGED SYMBOL MOST NEARLY RESEMBLING THE UNTAGGED SYMBOL BASED ON

ITS SHAPE, SIZE, LINEWEIGHT(S), LOCATION, AND SCHEDULED USAGE IN SPACES OF

SIMILAR FUNCTION. THE CONTRACTOR MUST OBTAIN CLARIFICATION FROM THE

ARCHITECT PRIOR TO PROCEEDING WITH SHOP DRAWINGS.

GENERAL NOTES

KEY PLAN

AREA A AREA B

AREA C

G10 A201

L13 A201

E10 A201

J13 A201

OFFICE

105E

OPEN OFFICE

OFFICE

105D

STORAGE

105F

OFFICE

119C

OFFICE

119B

OFFICE

105G

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

Room

131B

Room

131D

Room

131E Room

133E

Room

Room

133A

Room

Room

132A

Room

144A

Room

Room

Room

146A

Room

140C

Room

140D

Room

Room

150C

Room

151C

Room

Room

152A

Room

154A

Room

Room

Room

Room

Room

Room

Room

Room

Room

Room

108Q Room

108P

Room

108E

Room

Room

108D

Room

105C

Room

105B

Room

105A Room

Room

100B

Room

Room

100A

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A002

O V

E R

A

LL

F

IR

S T

FL

O

O R

P

LA

N

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

1/16" = 1'-0"A002A201

B16 OVERALL FIRST FLOOR PLAN

0 8' 16'4'

DATE DESCRIPTION

KEY PLAN

AREA A AREA B

AREA C

G10 A201

L13 A201

E10 A201

J13 A201

OFFICE

105E

OPEN OFFICE

OFFICE

105D

STORAGE

105F

OFFICE

119C

OFFICE

119B

OFFICE

105G

NOTE 2

NOTE 1

NOTE 2

NOTE 1

NOTE 1

NOTE 1

NOTE 1

NOTE 2

NOTE 1

NOTE 3

NOTE 1

Room

131B

Room

131D

Room

131E Room

133E

Room

Room

133A

Room

Room

132A

Room

144A

Room

Room

Room

146A

Room

140C

Room

140D

Room

Room

150C

Room

151C

Room

Room

152A

Room

154A

Room

Room

Room

Room

Room

Room

Room

Room

Room

Room

108Q Room

108P

Room

108E

Room

Room

108D

Room

105C

Room

105B

Room

105A

Room

100B

Room

Room

100A

1. DOUBLE WINDOW "A" REMOVE EXISTING SET OF WINDOWS, INCLUDING FRAME, CLIPS, SEALANT, EXISTING BLOCKING, ETC.

2. QUADRUPLE WINDOW "A" REMOVE EXISTING SET OF WINDOWS, INCLUDING FRAME, CLIPS, SEALANT, EXISTING BLOCKING, ETC.

3. DOUBLE WINDOW "B" REMOVE EXISTING SET OF WINDOWS, INCLUDING FRAME, CLIPS, SEALANT, EXISTING BLOCKING, ETC.

DEMOLITION KEY NOTES

1. ALL WORK SHOWN IS EXISTING TO REMAIN UNLESS NOTED OR INDICATED AS DASHED

LINES TO BE REMOVED. THE EXTENT OF DEMOLITION WORK SHALL INCLUDE ALL

INCIDENTAL DEMOLITION WORK NECESSARY TO PROPERLY PROVIDE ALL NEW WORK

SHOWN AND SPECIFIED, TO INCLUDE MECHANICAL, ELECTRICAL, & PLUMBING ITEMS.

2. DEMOLITION WORK SHOWN IS BASED ON EXISTING DRAWINGS AND INSPECTIONS. THE

CONTRACTOR SHALL VISUALLY INSPECT ALL EXISTING CONDITIONS, AND IS RESPONSIBLE

FOR PERFORMING THE INDICATED DEMOLITION WORK EVEN IF ACTUAL CONDITIONS

DIFFER FROM THESE SHOWN ON THE DRAWINGS.

3. DEMOLITION CONTRACTOR SHALL COORDINATE WITH NEW WORK SECTIONS FOR

ADDITIONAL INFORMATION RELATED TO EXTENT OF DEMOLITION.

4. REFER TO ALL OTHER DRAWINGS IN THIS SET FOR INCIDENTAL DEMOLITION WORK NOT

NOTED ON THE DEMOLITION PLANS.

5. THE OWNER HAS FIRST RIGHT OF REFUSAL OF ALL SALVAGE ITEMS. THE CONTRACTOR

SHALL PROPERLY DISPOSE OF ALL CONSTRUCTION DEBRIS. DO NOT STOCKPILE DEBRIS

ON SITE.

6. ITEMS TO BE DEMOLISHED SHALL BE REMOVED COMPLETELY INCLUDING ALL ANCHORS,

HANGERS, FASTENERS, ADHESIVES, SEALANTS, ETC. FINISHES TO REMAIN SHALL BE

PATCHED, PAINTED, AND REPAIRED TO MATCH EXISITNG ADJACENT FINISHES.

7. REMOVE, PATCH AND REPAIR PORTIONS OF WALL PARTITIONS WHICH CONFLICT WITH NEW

WORK TO BE INSTALLED, EVEN IF NOT SPECIFICALLY NOTED TO BE DEMOLISHED ON

PLANS.

8. ALL EXISTING STRUCTURE SHALL REMAIN, UNLESS NOTED OTHERWISE.

9. TEMPORARILY SUPPORT ALL BEAMS, LINTELS, PORTIONS OF WALLS ETC., TO BE

DISTURBED BY DEMOLITION WORK, UNTIL THEY ARE RE-SUPPORTED BY NEW WORK.

10. CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING THE INTEGRITY OF EXISTING

BUILDING ELEMENTS TO REMAIN THROUGHOUT SEQUENCE OF WORK. ANY DAMAGE TO

EXISTING BUILDING CONDITIONS SHOWN TO REMAIN SHALL BE RESTORED TO NEW WORK

CONDITION AT NO ADDITIONAL COST TO THE OWNER.

11. WHERE FINISHES ARE INDICATED TO BE REMOVED, REMOVAL SHALL INCLUDE ANY GROUT,

ADHESIVES, FASTENERS, AND ALL OTHER ITEMS USED TO ATTACH THE FINISHES TO THE

SURFACES THAT THEY COVER.

12. ANY FLOOR AREAS DAMAGED BY THE DEMOLITION CONTRACTOR SHALL BE PATCHED TO

MATCH EXISTING.

13. WHERE CEILINGS ARE TO BE REMOVED, REMOVE ALL CEILINGS SYSTEMS COMPLETE

INCLUDING GRID, TRIM HANGER, CLIPS, ETC. REUSE SALVAGED COMPONENTS WHERE

INDICATED. WHERE NEW CEILINGS ARE SPECIFIED, NO DOUBLE CEILINGS PERMITTED.

REMOVE ALL ORIGINAL CONCEALED CEILINGS WHERE ENCOUNTERED.

14. ALL EXISTING SURFACES TO REMAIN SHALL BE PROTECTED, PATCHED IF DAMAGED AND

CLEANED PRIOR TO APPLICATION OF FINISHES.

15. CONTRACTOR TO PROTECT ALL EQUIPMENT AND OTHER ELEMENTS IN AREA OF NEW OR

DEMOLITION WORK.

16. REMOVE ALL EXISTING WINDOW TREATMENTS: HORIZONTAL BLINDS, SHADES AND THE

LIKE.

17. REMOVE AND REPLACE ALL EXISTING, DAMAGED SILLS.

GENERAL DEMOLITION NOTES

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

D101

O V

E R

A

LL

F

IR

S T

FL

O

O R

D E

M O

LI

TI

O N

P

LA

N

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

0 8' 16'4'

1/16" = 1'-0"D101A201

C16 FIRST FLOOR - DEMOLITION PLAN

1. DIMENSIONS ON PLANS ARE FROM FACE OF MASONRY TO FACE OF MASONRY, FACE OF

MASONRY TO FACE OF GYPSUM BOARD OR FACE OF GYPSUM BOARD TO FACE OF

GYPSUM BOARD.

2. PLAN LOCATION OF WINDOWS AND FRAMES RELATIVE TO THE PLANE OF THE WALL IS

DIAGRAMMATIC ONLY. REFER TO THE REFERENCED JAMB AND HEAD CONDITION DETAILS

TO DETERMINE ACTUAL PLACEMENT OF WINDOW AND FRAME.

GENERAL PLAN NOTES

KEY PLAN

AREA A AREA B

AREA C

L13 A201

G7

A101 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

OFFICE

119B

OFFICE

105E

OFFICE

105D

STORAGE

105F

OFFICE

119C

OFFICE

105G

Room

131B

Room

131D

Room

131E

Room

133E

Room

Room

133A

Room

Room

132A

Room

108Q Room

108P

Room

108E

Room

Room

108D

Room

105C

Room

105B

Room

105A

Room

100B

Room

Room

100A

NOTE 1 NOTE 1

NOTE 1 NOTE 1 NOTE 1 NOTE 1

NOTE 1

NOTE 1

NUMBERED REMARKS

NOTE 1: PROVIDE MANUAL TRANSLUCENT ROLLER SHADES AT THIS FRAME OPENING.

NOTE 2: PROVIDE BOTH TRANSLUCENT AND BLACK-OUT SHADES AT THIS FRAME OPENING. BOTH ARE

MANUALLY-OPERATED.

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A101

P A

R

TI

A L

FI

R

S T

FL

O

O R

P

LA

N

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

0 4' 8'2'

1/8" = 1'-0"A101A201

D16 FLOOR PLAN - AREA A

AREA A AREA B

AREA C

L7

A102 A305

L7

A102 A305

L7

A102 A305

G7

A101 A305

G7

A101 A305

G7

A101 A305

L7

A102 A305

L7

A102 A305

G7

A101 A305

G7

A101 A305

Room

144A

Room

Room

Room

146A

Room

140C

Room

140D

Room

Room

150C

Room

151C

Room

Room

152A

Room

154A

Room

Room

Room

Room

Room

Room

Room

Room

Room

NOTE 2

NOTE 2

NOTE 2

NOTE 1

NOTE 1 NOTE 1 NOTE 1

NOTE 1

NOTE 1NOTE 1

NOTE 1

J7

A102 A305

J7

A102 A305

Room

NOTE 1NOTE 1

1. DIMENSIONS ON PLANS ARE FROM FACE OF MASONRY TO FACE OF MASONRY, FACE OF

MASONRY TO FACE OF GYPSUM BOARD OR FACE OF GYPSUM BOARD TO FACE OF

GYPSUM BOARD.

2. PLAN LOCATION OF WINDOWS AND FRAMES RELATIVE TO THE PLANE OF THE WALL IS

DIAGRAMMATIC ONLY. REFER TO THE REFERENCED JAMB AND HEAD CONDITION DETAILS

TO DETERMINE ACTUAL PLACEMENT OF WINDOW AND FRAME.

GENERAL PLAN NOTES

NUMBERED REMARKS

NOTE 1: PROVIDE MANUAL TRANSLUCENT ROLLER SHADES AT THIS FRAME OPENING.

NOTE 2: PROVIDE BOTH TRANSLUCENT AND BLACK-OUT SHADES AT THIS FRAME OPENING. BOTH ARE

MANUALLY-OPERATED.

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A102

P A

R

TI

A L

FI

R

S T

FL

O

O R

P

LA

N

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

0 4' 8'2'

1/8" = 1'-0"A102A201

D13 FLOOR PLAN - AREA B

1/8" = 1'-0"A102A201

A11 FLOOR PLAN - AREA C

1. NOT USED.

2. REFER TO LARGE SCALE ELEVATION DETAILS AND SPECS FOR MASONRY PATTERNS, BONDING, SPECIAL SHAPES AND

MORTAR COLOR PATTERNS.

3. PROVIDE SEALANT AT ALL INTERSECTIONS OF DISSIMILAR MATERIALS IN ACCORDANCE WITH THE SPECIFICATIONS. ALL

EXTERIOR SEALANTS TO BE A CUSTOM COLOR SELECTED BY THE ARCHITECT. MORE THAN ONE SEALANT COLOR MAY BE SELECTED FOR USE ALONG THE HEIGHT OF THE SAME JOINT TO MATCH ADJOINING MASONRY OR MORTAR.

(NOTES APPLY TO ALL ELEVATION SHEETS)ELEVATION NOTES

Level 1 0' - 0"

Level 2 13' - 0"

A18

A201 A201

E18

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

E18 Sim

A201 A201

Level 1 0' - 0"

Level 2 13' - 0"

Level 3 20' - 0"

H18

A201 A201

H18 Sim

A201 A201A18 Sim

A201 A201

A18 Sim

A201 A201

A18 Sim

A201 A201

Level 1 0' - 0"

Level 2 13' - 0"

E18 Sim

A201 A201

E18 Sim

A201 A201

A18 Sim

A201 A201

Level 1 0' - 0"

Level 2 13' - 0"

E18 Sim

A201 A201Level 1 0' - 0"

EXISTING BRICK PIER, TYP.

NEW ALUMINUM FRAMED

STOREFRONT SYSTEM, TYP.

EXISTING BRICK, TYP.

SF01 SF01

RESINOUS CEMENT COATING, TYP.

RESINOUS CEMENT COATING, TYP.

NOTE:

CONTRACTOR SHALL POWER

WASH ALL RESINOUS CEMENT

COATINGS AT NEW WINDOWS

Level 1 0' - 0"

EXISTING BRICK PIER, TYP.

NEW ALUMINUM FRAMED

STOREFRONT SYSTEM, TYP.

EXISTING BRICK, TYP.

SF01 SF01 SF01 SF01

RESINOUS CEMENT COATING, TYP.

RESINOUS CEMENT COATING, TYP.

NOTE:

CONTRACTOR SHALL POWER

WASH ALL RESINOUS CEMENT

COATINGS AT NEW WINDOWS

Level 1 0' - 0"

1313.5

EXISTING BRICK PIER, TYP.

NEW ALUMINUM FRAMED

STOREFRONT SYSTEM, TYP.

SF02SF02

EXISTING BRICK, TYP.

RESINOUS CEMENT COATING, TYP.

RESINOUS CEMENT COATING, TYP.

NOTE:

CONTRACTOR SHALL POWER

WASH ALL RESINOUS CEMENT

COATINGS AT NEW WINDOWS

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A201

B U

IL

D

IN

G

E

LE

V A

TI

O

N S

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

0 8' 16'4'

1/16" = 1'-0"A201A002

L13 SOUTH ELEVATION

1/16" = 1'-0"A201A002

J13 NORTH ELEVATION

1/16" = 1'-0"A201A002

G10 EAST ELEVATION

1/16" = 1'-0"A201A002

E10 WEST ELEVATION

1/4" = 1'-0"A201A201

E18 ELEVATION - DOUBLE "A" WINDOW ARRANGEMENT

1/4" = 1'-0"A201A201

A18 ELEVATION - QUAD "A" WINDOW ARRANGEMENT

1/4" = 1'-0"A201A201

H18 ELEVATION - DOUBLE "B" WINDOW ARRANGEMENT

NOTES APPLY TO ALL FRAME ELEVATION SHEETS

STOREFRONT NOTES

GLASS TYPE KEY

1. VERIFY ROUGH OPENINGS, INCLUDING BUT NOT LIMITED TO STRUCTURAL LINTEL LOCATIONS, PRIOR TO FABRICATION.

2. COORDINATE REQUIRED TOLERANCES IN ALL DIMENSIONS NEEDED TO MANUFACTURE AND INSTALL WINDOWS, STOREFRONT INCLUDING SUBFRAMES, AS REQUIRED.

3. CONTINUOUSLY SEAL ALL SIDES OF STOREFRONT AND SUBFRAMES ABUTTING DISSIMILAR MATERIALS AT JAMBS, HEADS, AND SILLS, TYPICALLY.

4. PROVIDE APPROPRIATE ANCHORAGE SYSTEM FOR ALL CONDITIONS. PROVIDE SUBFRAMING AS SHOWN ON DETAILS OR

SPECIFIED.

5. PROVIDE FOR THERMAL EXPANSION AT ALL FRAMING SYSTEMS.

6. COORDINATE FRAMES WITH PLAN WHEN MORE THAN ONE CONSTRUCTION DETAIL IS REFERENCED.

7. AS REQUIRED FOR DESIGN LOADING, MANUFACTURER TO PROVIDE MULLION REINFORCING AND VERTICAL EXTENSIONS UP

TO STRUCTURE ABOVE (ATTACHMENT TO STRUCTURE BY MANUFACTURER). SEE SECTIONS AND DETAILS FOR ADDITIONAL

WORK RELATING TO FRAMING SYSTEM.

8. IDENTIFICATION OF OPENING TYPES AS STOREFRONT IS BASED ON SYSTEM REQUIREMENTS OF A PARTICULAR MANUFACTURER. CONTRACTOR IS TO DETERMINE BEST APPLICATION OF SUBMITTED MANUFACTURER AND SYSTEM

BASED ON PERFORMANCE REQUIREMENTS, SIZE OF OPENING, AND INSTALLATION CONDITION.

9. CONTRACTOR TO COORDINATE REQUIRED TOLERANCES IN ALL DIMENSIONS NEEDED TO MANUFACTURE AND INSTALL STOREFRONT, INCLUDING SUBFRAMES, AS REQUIRED. CONTRACTOR MUST VERIFY ACTUAL DIMENSIONS IN THE FIELD WITH THOSE SHOWN ON ALL DRAWINGS, INCLUDING DETAILS SHOWN ON OTHER SHEETS, PRIOR TO FABRICATION.

10. NOT USED.

11. COORDINATE FRAMING SYSTEMS WITH AIR BARRIER TRANSITION MEMBRANE SYSTEM AND MANUFACTURER-

RECOMMENDED DETAILS FOR A COMPLETE AIR BARRIER SYSTEM.

G-1 NOT USED.

G-2 NOT USED.

G-3 NOT USED.

G-4 NOT USED.

G-5 1" INSULATING GLASS; CONSISTING OF

1/4" CLEAR GLASS, EXTERIOR LITE WITH LOW E COATING

1/2" AIR SPACE, AND

1/4" CLEAR GLASS

G-6 NOT USED.

G-7 NOT USED.

G-8 NOT USED.

G-9 1" INSULATING GLASS; SPANDREL UNIT CONSISTING OF

1/4" CLEAR GLASS, EXTERIOR LITE WITH LOW E COATING

1/2" AIR SPACE, AND

1/4" CLEAR GLASS, CERAMIC-COATED 4TH SURFACE

REMARKS

REFER TO FLOOR PLANS FOR LOCATIONS OF SHADING DEVICES.

2' - 8" 2' - 8"

SF01 SF01

SF01 SF01 SF01 SF01

2' - 8" 2' - 8"2' - 8" 2' - 8"

2' - 8" 2' - 8"

SF02 SF02

Level 1 0' - 0"

6'

8" 2'

8"

2" 5'

0"

2" 1'

2"

2"

2' - 8"

2" 2' - 4" 2"

G-5

G-5

B12

A305

B12

A305

B7

A305

B18

A305

G-9 AT LABS:

173, 175, 176

2'

8"

2" 1'

2"

2" 8'

4"

2" 1'

2"

2" 2' - 8"

2" 2' - 4" 2"

G-5

G-5

G-5

B12

A305

B12

A305

B7

A305

B18

A305

CONTRACTOR TO V.I.F.

EXISTING WALL CONSTRUCTION

PRE-FIN ALUM. STOREFRONT HIGH

PERFORMANCE SILL FLASHING W/ END DAM

AND WEEPS

PRE-FIN ALUM. STOREFRONT SYSTEM W/ 1"

INSULATED GLAZINGCONT. BACKER ROD AND SEALANT AT

FULL PERIMETER INT. AND EXT. -

COLOR TO MATCH FRAME, TYP.

LOCATE PRIMARY SEALANT LINE TO ENGAGE

TRANSITION MEMBRANE @ FULL PERIMETER OF

OPENING, TYP.

4 1/2" V.I.F. +/- 7 1/2"

EXISTING WALL CONSTRUCTION

(SHOWN GRAY), NO WORK

EXISTING ACCENT BRICK

(BEYOND), NO WORK

EXISTING RESINOUS CEMENT COATING

PRE-FINISHED SILL. NEW OR

EXISTING, REFER TO PLANS

SEALANT AT SILL,

COLOR TO MATCH

ADJACENT SURFACE

FINISHED JAMB (BEYOND)

CONTRACTOR SHALL CLEAN ALL

EXTERIOR, CONCRETE SILLS

NOTE:

ACTUAL CONSTRUCTION OF EXISTING WALL MAY VARY.

CONTRACTOR SHALL VERIFY IN FIELD

FURRED WALL MAY OCCUR. CONTRACTOR

TO VERIFY IN FIELD. INCREASE SIZE OF SILL

WHERE REQUIRED.

CASEWORK

(SHOWN DASHED) OCCURS

IN SOME LOCATIONS

CONT. BACKER ROD AND SEALANT AT FULL

PERIMETER INT. AND EXT. - COLOR TO MATCH

FRAME, TYP.

SHIM, AS REQ'D

PRE-FIN ALUM. STOREFRONT SYSTEM W/ 1"

INSULATED GLAZING

- 4

/2

1/ 2"

CONTINUOUS MULLION FILLER

- 7

/2

EXISTING WALL CONSTRUCTION

(SHOWN GRAY), NO WORK

EXISTING RESINOUS CEMENT COATING SILL

NOTE:

ACTUAL CONSTRUCTION OF EXISTING WALL MAY VARY.

CONTRACTOR SHALL VERIFY IN FIELD

PRE-FINISHED SILL. NEW OR EXISTING, REFER TO PLANS

CONTRACTOR TO V.I.F.

EXISTING WALL CONSTRUCTION

4 1/2" +/- 4 1/2" +/- 7 1/2"

SHIM, AS REQ'D

CONT. BACKER ROD AND SEALANT AT FULL PERIMETER

INT. AND EXT. - COLOR TO MATCH FRAME, TYP.

PRE-FIN ALUM. STOREFRONT SYSTEM

W/ 1" INSULATED GLAZING

CONTINUOUS MULLION FILLER

EXISTING WALL CONSTRUCTION (SHOWN GRAY), NO WORK

EXISTING RESINOUS CEMENT COATING

ROLLER SHADE, SEE PLANS/NOTES

EXISTING, GYP BOARD

WINDOW WELL BEYOND

EXISTING FINISHED

CEILING SYSTEM

CONTRACTOR TO V.I.F.

EXISTING WALL CONSTRUCTION

4 1/2" +/- 4 1/2" +/- 7 1/2"

SHIM, AS REQ'D

PRE-FIN ALUM. STOREFRONT SYSTEM

W/ 1" INSULATED GLAZING

CONTINUOUS MULLION FILLER

EXISTING WALL CONSTRUCTION

(SHOWN GRAY), NO WORK

EXISTING RESINOUS CEMENT

COATING

ROLLER SHADE, SEE PLANS/NOTES

NOTE:

ACTUAL CONSTRUCTION OF EXISTING WALL MAY VARY.

CONTRACTOR SHALL VERIFY IN FIELD

EXISTING, GYP BOARD

WINDOW WELL BEYOND

EXISTING FINISHED

CEILING SYSTEM CONT. BACKER ROD AND SEALANT AT

FULL PERIMETER INT. AND EXT. -

COLOR TO MATCH FRAME, TYP.

FURRRED WALL CONDITIONBLOCK WALL CONDITION

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A305

FR

A

M E

E

LE

V A

TI

O

N S

RC

C

GL

EN

NS

C

AM

PU

S W

IN

DO

W R

EP

LA

CE

ME

NT

5 C oll eg e D riv e, Gl en ns

, V irg ini a

2/24/2025

BID SET

GP #22006.24

SCALE 1/4" = 1'-0"STOREFRONT TYPES

3" = 1'-0"A305A305

B7 HEAD DETAIL - STOREFRONT @ EXISTING WALL

3" = 1'-0"A305A305

B18 SILL DETAIL - STOREFRONT @ EXISTING WALL

3" = 1'-0"A305A305

B12 JAMB DETAIL - STOREFRONT @ CMU

1/4" = 1'-0"A305A101

G7 PLAN - DOUBLE "A" WINDOW ARRANGEMENT

1/4" = 1'-0"A305A102

L7 PLAN - QUAD "A" WINDOW ARRANGEMENT

1/4" = 1'-0"A305A102

J7 PLAN - DOUBLE "B" WINDOW ARRANGEMENT

SF-01 - "A"SF-02 - "B"

HEAD, SILL, JAMB DETAILS

B101a

SIM

SIM

A102 A103

DEPT.

ADD

GRID LINES

SECTIONS

DETAIL NUMBER

SHEET NUMBER

DETAIL NUMBER

SHEET NUMBER

DETAILS IN PLAN/SECTION

ROOM NUMBER

DOOR NO. ON PLAN

H.M. FRAME NO.

ON PLAN

REVISION: TYPE =

A.S.I/P.R./C.C.D./ADD.

CASEWORK

(FURNISHING PLANS ONLY)

ALUM. FRAME/WINDOW

TYPE

WALL TYPE

# # INTERIOR ELEVATION

DETAIL NUMBER

SHEET NUMBER

A3ROOM NAME

B101a

REF SHEET

NUMBER

REF SHEET NUMBER

EARTH

GRAVEL

CONCRETE

CONCRETE MASONRY UNITS

SOLID CONCRETE

MASONRY UNITS

BRICK

WOOD-FINISHED

WOOD ROUGH

PLYWOOD

GYPSUM BOARD

ACOUSTIC TILE

STEEL - LARGE SCALE

ALL METALS - SMALL SCALE

GLASS - LARGE SCALE

BATT INSULATION

RIGID INSULATION

CERAMIC TILE

CARPET

Above finished floor AFF Acoustic ACST Acoustic Panel Ceiling APC Addendum ADD Alternate ALT Aluminum AL Angle L Approximate APPROX Architecture, ARCH architectural Asbestos ASB Asphalt ASPH Assistant ASST Association ASSN Automatic AUTO Average AVG Base plate BP Basement BSMT Beam BM Bearing BRG Bedroom BR Benchmark BM Board BD Boiler BLR Bottom BOT Brick BRK Building line BL Building BLDG Built-up-roof BUR Cabinet CAB Carpet CPT Catalog CAT Ceiling height CH Ceiling CLG Center CTR Centerline CL Ceramic Tile CT Ceramic CER Chalkboard CB Clear CLR Closet CLO Coated CTD Cold rolled CR Column COL Company CO Composition COMP Concrete Masonry Unit CMU Concrete CONC Construction joint CJ Construction CONSTR "Continue, Continuous" CONT Corridor CORR Countersink CSK Cubic CU Curve(d) CRV Dampproofing DP Degree DEG Department(al) DEPT Detail DET Diagonal DIAG Diameter DIA Dimension DIM Dishwasher DW Dispenser DISP Door DR Double DBL Double-hung DH Down DN Downspout DS Drain DR Drawing DWG Each EA East E Electric Water Cooler EWC "Electric, electrical" ELEC Elevation EL Elevator ELEV Engineer ENGR Entrance ENTR

Maximum MAX Mechanical MECH Membrane MEMB Men M Metal MET, MTL Mezzanine MEZZ Minimum MIN Mirror MIR Miscellaneous MISC Mounted MTD Mounting MTG Necessary NEC Noise-reduction NRC coefficient Nominal NOM Non Combustible NC, NONCOM North N Not in Contract NIC Not to scale NTS Not available NA Number NO Office OFF On center OC Opening OPNG Opposite OPP Outside diameter OD Overall OA Overhead OVHD Page P Painted PTD Pair PR Panel PNL Partition PTN Percent PCT Perforate(d) PERF Permanent PERM Perpendicular PERP Piece PC Plastic Laminate PLAM Plastic Laminate PLAS.LAM Plate PL Plumbing PLMB Plywood PLYWD Point PT Polyvinyl chloride PVC Precast PRCST Prefabricated PREFAB Preliminary PRELIM Preparation, prepare PREP Program PRGM Projection Screen PS Project PROJ Property PROP Public Address PA Quality control QC Quality QUAL Quantity QTY Quarry Tile QT Radius RAD Rain Leader RL Received RCVD Receptacle RCPT Receptionist RECPT Recess(ed) REC Refer, reference REF Refrigerate, refrigerator REFR Reinforce REINF Reinforced concrete RC Remove RMV Repair RPR Required REQD Revise, revision REV Right hand RH Road RD Roof Drain RD Roof RF Roofing RFG Room RM Rubber tile floor RTF

Rubber RBR Schedule SCHED Schematic SCHEM Section SECT Service SVCE "Sheet, sheeting" SHT Shower SH Siding SDG Similar SIM Slope SL Sound-transmission STC class South S Speaker SPKR Specification SPEC Sprinkler SPR Square SQ Stainless steel SS Standard STD Standpipe SP Steel STL Storage STOR Structural Glazed SGFT Facing Tile Structural, structure STRUCT Substitute SUBST Surface SURF Suspend(ed) SUSP Switch SW Symmetrical SYM System SYS Tackboard TB Tackstrip TS Telephone TEL Television TV Temporary TEMP Terrazzo TER Thick THK Through THRU Toilet T Tongue and groove T&G Top and bottom T&B Top chord TC Top of Masonry Parapet TMP Top of Bearing TOFB Top of Steel T.O.S.

Topping TOPG Total TOT Transformer XFMR Transom TR Transparent TRANS Tread TRD Threshold THRESH Typical TYP Underground UG Underwriters UL Laboratories Unfinished UNF Unit Ventilator UV Unless Otherwise Noted UON Urinal UR US Gypsum Company USG Verify in Field VIF Vertical VERT Vestibule VEST, V Vinyl Reducing Strip VRS Vinyl Composite Tile VCT Vinyl asbestos tile VAT Wardrobe WARD Water closet WC Waterproof WP Weight WT Welded WLD Welded Wire Mesh WWM With W/ Without W/O Women W Wood WD Wrought Iron WI

Equal EQ Equipment EQUIP Exhaust EXH Existing EXIST Existing to Remain ETR Expansion joint EXP JT Exposed EXP Exterior EXT Fabricate FAB Face of Stud F. OF S.

Fan Coil Unit FCU Fiberglass-reinforced FRP plastics Finish FIN Finished Floor FF Fire Extinguisher FE Fire Extinguisher & FEC Cabinet Fire Retardant Treated FRT Fireproof FPRF Fixture FXTR Flange FLG Flashing FL Floor FL Floor drain FD Flooring FLG Fluorescent FLUOR Footing FTG Foundation FDN Furnish(ed), furniture FURN Furring FURR Gage (gauge) GA Galvanize(d) GALV Galvanized Iron GALVI Glazed Wall Tile GWT Grab Bar GB Grade GR Gravel GVL Gypsum Wallboard GWB Gypsum GYP Handicapped HC Hardware HDW Heating ventilating and HVAC air conditioning Height HGT High Point HPT High Performance HP High Performance HPC Coating Hollow Metal HM Horizontal HORIZ Include(d), inclusive INCL Incorporated INC Information INFO Inside diameter ID Install(ed), installation INSTL Insulation INSUL Interior INT Janitor JAN Joint JT Joist J, JST Junction box JB Knock down KD Laboratory LAB Lavatory LAV Left Hand LH Left L Length LG Level LVL Light LT Machine MACH Maintenance MAINT Manager MGR Manual MNL Manufacturing MFG Markerboard MB Masonry opening MO Masonry MSNRY Master bedroom MBR Material MATL

NOT IN SCOPE

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

TS

TI

TL

E S

H E

E T

RC

C

-W

AR

SA

W

C

AM

PU

S

W

IN

DO

W

R

EP

LA

CE

ME

NT

C am pu s D r, W ars aw

, V irg ini a

02/24/2025

BID SET

GP #22006.24

LIST OF DRAWINGS

TS TITLE SHEET

ARCHITECTURAL

A002 OVERALL FIRST FLOOR PLAN

A003 OVERALL FIRST FLOOR PLAN - ANNEX

D101 OVERALL FIRST FLOOR DEMOLITION PLAN

D102 OVERALL FIRST FLOOR DEMOLITION PLAN - ANNEX

A101 PARTIAL FLOOR PLAN

A102 PARTIAL FLOOR PLAN

A103 PARTIAL FLOOR PLAN

A201 BUILDING ELEVATIONS

A202 BUILDING ELEVATIONS - ANNEX

A305 FRAME ELEVATIONS

DRAWING KEY

SYMBOLS OF MATERIALS

ABBREVIATIONS

1/16" = 1'-0"TSA201

A12 CODE STUDY PLAN - FIRST FLOOR

PROJECT NAME AND LOCATION

NAME RAPPAHANNOCK COMMUNITY COLLEGE - WINDOW REPLACEMENT

STREET ADDRESS 52 CAMPUS DRIVE

COUNTY RICHMOND COUNTY

CITY, STATE WARSAW, VA

PROJECT DESCRIPTION: WINDOW REPLACEMENT ON AN EXISTING BUILDING AT RCC.

THERE IS NO WORK INSIDE THE BUILDING - NO CHANGE IN OCCUPANCY OR OCCUPANTS

APPLICABLE CODES

BUILDING CODE 2021 Part 2, VIRGINIA EXISTING BUILDING CODE (VEBC), Level 1

2021 VIRGINIA CONSTRUCTION CODE (VCC)

2024 VIRGINIA CONSTRUCTION & PROFESSIONAL SERVICES MANUAL (CPSM)

ACCESSIBILITY ADA90-TITLE II,Scoping Requirements of the Department of Justice’s 2010 ADA Standards for Accessible Design, dated September 15, 2010 and technical design are Chapters 1 and 3 thru 11 of Standards for Accessible and Usable Buildings and Facilities (ICC A117.1-2017) approved March 28, 2017

BUILDING USE AND CONSTRUCTION CLASSIFICATION

VCC

USE GROUP: B, BUSINESS 304.1

BUILDING AREA (PER VCC): 55,158 SF (92,000 SF ALLOWABLE)

PROPOSED CONSTRUCTION TYPE TYPE IIB (EXISTING)

ALLOWABLE BUILDING HEIGHT/STORIES: 75' (VCC TABLE 504.3), 3 STORIES (VCC TABLE 504.4)

ACTUAL BUILDING HEIGHT/STORIES: 20' MAXIMUM, 1 STORY

BUILDING VOLUME: 1,103,160 CUBIC FEET (EXISTING)

APPLICABLE CODES AND TABULATIONS

VICINITY MAP LOCATION MAP

DEB PROJECT CODE 260-B4260-073

D E S I G N T E A M

RCC - WARSAW CAMPUS

WINDOW REPLACEMENT

BID SET 02/24/2025

52 Campus Dr, Warsaw, Virginia

EXISTING CLASSROOM

BUILDING

RICHMOND ROAD

H W

Y

LEAD DISCLOSURE STATEMENT

AN INSPECTION TO IDENTIFY LEAD CONTAINING OR COATED BUILDING COMPONENTS HAS BEEN CONDUCTED AND CAN BE FOUND IN THE PROJECT SPECIFICATIONS. THIS REPORT IS PROVIDED FOR THE CONTRACTOR’S USE AND MAY NOT BE ALL INCLUSIVE. IT IS THE CONTRACTOR’S RESPONSIBILITY TO COMPLY WITH ALL VIRGINIA OCCUPATIONAL SAFETY AND HEALTH (VOSH) REGULATIONS AS THEY PERTAIN TO EMPLOYEE EXPOSURES TO LEAD. ALL LEAD AND LEAD-COATED BUILDING COMPONENTS SHALL BE RECYCLED

TO THE EXTENT POSSIBLE.

HIGH PERFORMANCE BUILDNG ACT

IN ACCORD WITH THE HIGH PERFORMANCE BUILDINGS ACT, THE BUILDING IS EXEMPT FROM COMPLIANCE

BECAUSE THE RENOVATED BUILDING AREA IS NOT GREATER THAN 5,000 GROSS SQUARE FEET.

ASBESTOS DISCLOSURE STATEMENT

AN ASBESTOS INSPECTION WAS PERFORMED AND ACM WAS FOUND GENERALLY IN THE AREA INDICATED. THE ASBESTOS INSPECTION REPORT IS INCLUDED IN SECTION 02 80 00 IN THE PROJECT SPECIFICATIONS. THE OWNER SHALL SUBMIT AN APPLICATION FOR PERMIT TO HAVE THE ASBESTOS-CONTAINING MATERIALS ABATED BY A LICENSED ASBESTOS CONTRACTOR UNDER A SEPARATE CONTRACT USING APPROVED PROCEDURES PRIOR TO ISSUING A NOTICE TO PROCEED TO THE GENERAL CONTRACTOR. ANY ACM THAT IS TO REMAIN AND THE NEW NON ASBESTOS-CONTAINING MATERIAL SHALL BE LABELED ACCORDINGLY. THE ASBESTOS ABATEMENT CONTRACTOR SHALL MARK UP THE AS-BUILT DRAWINGS RESULTING FROM ITS WORK TO INCLUDE AREAS WHERE ASBESTOS WAS ABATED, AREAS WHERE ASBESTOS WAS ENCAPSULATED, AND AREAS WHERE ACM EXIST BUT WERE LEFT IN PLACE. THE GENERAL CONTRACTOR SHALL REVIEW AND CERTIFY THE LOCATIONS WHERE ACM WAS ABATED, AREAS WHERE ACM WAS ENCAPSULATED AND AREAS WHERE ACM WAS LEFT IN PLACE AS MARKED ON THE AS-BUILT

DRAWINGS AND WILL PROVIDE THE DRAWINGS TO THE ARCHITECT.

DATE DESCRIPTION

VIRGINIA COMMUNITY COLLEGE SYSTEM

300 Arboretum Place, Suite 200 Richmond, Virginia 23236

OWNER ARCHITECT

X. TONG WANG, RA

Capital Outlay Program Manager twang@vccs.edu Tel: (804) 819-4919

RAPPAHANNOCK COMMUNITY COLLEGE

Glenns Campus 12745 College Drive, Glenns, Virginia

COLLEGE

CHERYL BOLTZ

Facilities Manager, Warsaw Campus cboltz@rappahannock.edu Tel: (804) 333-6840

GRIMM + PARKER ARCHITECTS

123 East Main St, Second Floor Charlottesville, Virginia 22902

Annette McDaniels AIA, CCCA, LEED AP BD+C Associate Principal amcdaniels@gparch.com Tel: (434) 270-0141

EXISTING ANNEX

BUILDING

GENERAL NOTES

OR OTHERWISE IDENTIFIED ON ONE OF THE SECTIONS OR DETAILS ARE APPLICABLE AND

BINDING TO ALL OTHER SECTIONS AND DETAILS FOR IDENTICAL OR SIMILAR CONDITIONS.

1. ALL CONSTRUCTION AND WORK REPRESENTED IN THE COMPLETE SET OF DOCUMENTS IS

ASSUMED TO BE NEW AND FURNISHED AND INSTALLED BY THE CONTRACTOR UNLESS

OTHERWISE NOTED.

2. THE DRAWINGS AND SPECIFICATIONS ARE COMPLIMENTARY AND WHAT IS REQUIRED BY

ONE SHALL BE AS BINDING AS IF REQUIRED BY ALL. NO DRAWING SHALL HAVE

PRECEDENCE ONE OVER THE OTHER. IN THE EVENT OF A CONFLICT IN THE DOCUMENTS,

THE CONTRACTOR SHALL SEEK THE INTERPRETATION OF THE ARCHITECT. THE

CONTRACTOR SHALL NOT PROCEED WITH WORK UNTIL SUCH INTERPRETATION IS

OBTAINED. IF THE CONTRACTOR PROCEEDS WITHOUT CLARIFICATION, THE CONTRACTOR

WILL BE RESPONSIBLE TO REMOVE AND REPLACE ANY WORK NOT CONFORMANCE WITH

THE ARCHITECT'S DIRECTION WITHOUT ADDITIONAL COST TO THE OWNER. IN THE EVENT

OF A CONFLICT IN THE DRAWINGS OR SPECIFICATIONS, BIDDERS SHALL SEEK

CLARIFICATION FROM THE ARCHITECT. RESOLUTIONS TO SUCH CONFLICTS WILL BE

ISSUED THROUGH ADDENDA TO THE BID DOCUMENTS. IF CLARIFICATION FROM THE

ARCHITECT IS NOT RECEIVED THROUGH AN ADDENDUM PRIOR TO THE RECEIPT OF BIDS,

THE BIDDER SHALL ASSUME THE MORE COSTLY REQUIREMENT APPLIES, AND THE

AWARDED CONTRACTOR SHALL SEEK CLARIFICATION FROM THE ARCHITECT PRIOR TO THE

EXECUTION OF THE WORK.

3. IF A CONFLICT EXISTS BETWEEN DRAWINGS OF DIFFERENT SCALES, CONSULT THE

ARCHITECT FOR CLARIFICATION.

4. IN THE ABSENCE OF A WRITTEN DIMENSION, OR IN CASE OF DOUBT AS TO THE PROPER

MEASUREMENT, CONSULT THE ARCHITECT FOR CLARIFICATION.

5. IF AN AREA OR SPACE IS SHOWN, BUT IS NOT CLEARLY DEFINED OR INDICATED BY NOTES, PROVIDE THE SAME MATERIALS AND FINISHES AS SCHEDULED OR DETAILED FOR AREAS

OF SIMILAR USE ELSEWHERE IN THE BUILDING,

6. SECTIONS INDICATED ARE INTENDED TO SHOW THE SPECIFIC CONSTRUCTION WHERE

REFERENCED AS WELL AS ESTABLISH THE GENERAL CONSTRUCTION DETAILS FOR

SECTIONS THROUGHOUT THE PROJECT WHICH DO NOT HAVE SPECIFIC SECTIONS DRAWN.

THE MOST SIMILAR SECTIONS TO BE ADAPTED TO ANY SECTIONS NOT DETAILED. ANY

SPECIFIC QUESTIONS CONCERNING CONSTRUCTION NOT ADEQUATELY COVERED BY THE

ABOVE SHOULD BE DIRECTED TO THE ARCHITECT DURING THE BIDDING.

7. TYPICAL DETAILS THROUGHOUT THE DRAWING SET TO APPLY FOR ALL APPLICABLE

CONDITIONS EVEN IF NOT SPECIFICALLY SHOWN OR REFERENCED.

8. ALL APPURTENANCES BUILT INTO OR THROUGH WALLS, INCLUDING DOORS, DUCTS,

WINDOWS, LOUVERS, GRILLES, MECHANICAL WORK, ETC. TO FIT TIGHT AND BE

THOROUGHLY SEALED AROUND PERIMETERS. WORK AT EXTERIOR WALLS TO BE FLASHED

OR OTHERWISE WATERPROOF SEALED.

9. FIELD CHECK ROUGH AND/OR FINISHED DIMENSIONS FOR ACCURATE FITTING OF

WINDOWS, AND OTHER INSTALLATIONS PRIOR TO SHOP OR FACTORY FABRICATION.

PROVIDE FILLER STRIPS, SCRIBE STRIPS, BASES, CLOSURE FINISHES AND TRIM FOR A

COMPLETE INSTALLATION.

10. EACH CONTRACTOR MUST REFER TO ALL DRAWINGS AND BE RESPONSIBLE FOR WORK

PERTAINING TO THEIR PARTICULAR TRADE. ALL CONTRACTORS MUST COORDINATE THE

WORK OF ALL TRADES AND FIELD CHECK AGAINST ANY CONFLICTS BETWEEN DRAWINGS.

REPORT CONFLICTS TO THE ARCHITECT FOR CLARIFICATION.

11. FOR THE PURPOSES OF BIDDING (UNLESS OTHERWISE NOTED), ALL SYMBOLS (LABELED /

TAGGED OR UNLABELED/UNTAGGED) WHICH ARE LOCATED ON THE

FURNISHING/EQUIPMENT PLANS TO BE CONSIDERED AS IN CONTRACT WORK TO BE

PROVIDED BY THE CONTRACTOR. ALL SYMBOLS LOCATED ON THE PLANS DENOTE EITHER

FURNITURE, EQUIPMENT, CASEWORK OR MILLWORK. WHERE A SYMBOL IS LOCATED ON

THE PLANS BUT IS NOT LABELED OR TAGGED TO A SCHEDULE, THE CONTRACTOR MUST

SEEK CLARIFICATION FROM THE OWNER OR ARCHITECT BEFORE PROCEEDING. FOR

PURPOSES OF BIDDING ONLY, IF CLARIFICATION CANNOT BE OBTAINED FROM THE OWNER

OR ARCHITECT THROUGH ADDENDUM PRIOR TO THE BID DATE, THE CONTRACTOR MUST

NEVERTHELESS INCLUDE THE ITEM IN QUESTION IN THEIR BID, CONSIDERING IT THE SAME

AS THE TAGGED SYMBOL MOST NEARLY RESEMBLING THE UNTAGGED SYMBOL BASED ON

ITS SHAPE, SIZE, LINEWEIGHT(S), LOCATION, AND SCHEDULED USAGE IN SPACES OF

SIMILAR FUNCTION. THE CONTRACTOR MUST OBTAIN CLARIFICATION FROM THE

ARCHITECT PRIOR TO PROCEEDING WITH SHOP DRAWINGS.

KEY PLAN

AREA A AREA B

AREA C

G8 A201

L13 A201

E9 A201

J13 A201

WAITING

OFFICE

113A

OFFICE

113B

OFFICE

113C

OFFICE

182B

CONFERENCE

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

NEW STOREFRONT SYSTEM

Room

121B

Room

121C

Room

121A

Room

121D

Room

Room

Room

141A

Room

Room

141B

Room

141C

Room

Room

Room

Room

Room

Room

Room

152A

Room

Room

Room

Room

Room

Room

A R

E A

A A

R E

A B

NEW STOREFRONT SYSTEM

A R

E A

A A

R E

A B

AREA C

AREA A

AREA C

AREA A

Room

CORRIDOR

LOBBY

100BRoom

Room

100A

Room

Room

Room

Room

117J

Room

117H

Room

117C

Room

117B

123456789101112131415161718

123456789101112131415161718

A

B

C

D

E

F

G

H

J

K

L

M

A

B

C

D

E

F

G

H

J

K

L

M w w w .g ri m m a n d p a rk e r.

c o m

E a s t

M a in

S tr e e t n d F lo o r

C h a rl o tt e s v ill e

V A l:

-2

-5

DEB #

260-B4260-073

A002

O V

E R

A

LL

F

IR

S T

FL

O

O R

P

LA

N

RC

C

-W

AR

SA

W

C

AM

PU

S

W

IN

DO

W

R

EP

LA

CE

ME

NT

C am pu s D r, W ars aw

, V irg ini a

02/24/2025

BID SET

GP #22006.24

1/16" = 1'-0"A002A201

C16 OVERALL FIRST FLOOR PLAN

GENERAL NOTES

OR OTHERWISE IDENTIFIED ON ONE OF THE SECTIONS OR DETAILS ARE APPLICABLE AND

BINDING TO ALL OTHER SECTIONS AND DETAILS FOR IDENTICAL OR SIMILAR CONDITIONS.

1. ALL CONSTRUCTION AND WORK REPRESENTED IN THE COMPLETE SET OF DOCUMENTS IS

ASSUMED TO BE NEW AND FURNISHED AND INSTALLED BY THE CONTRACTOR UNLESS

OTHERWISE NOTED.

2. THE DRAWINGS AND SPECIFICATIONS ARE COMPLIMENTARY AND WHAT IS REQUIRED BY

ONE SHALL BE AS BINDING AS IF REQUIRED BY ALL. NO DRAWING SHALL HAVE

PRECEDENCE ONE OVER THE OTHER. IN THE EVENT OF A CONFLICT IN THE DOCUMENTS,

THE CONTRACTOR SHALL SEEK THE INTERPRETATION OF THE ARCHITECT. THE

CONTRACTOR SHALL NOT PROCEED WITH WORK UNTIL SUCH INTERPRETATION IS

OBTAINED. IF THE CONTRACTOR PROCEEDS WITHOUT CLARIFICATION, THE CONTRACTOR

WILL BE RESPONSIBLE TO REMOVE AND REPLACE ANY WORK NOT CONFORMANCE WITH

THE ARCHITECT'S DIRECTION WITHOUT ADDITIONAL COST TO THE OWNER. IN THE EVENT

OF A CONFLICT IN THE DRAWINGS OR SPECIFICATIONS, BIDDERS SHALL SEEK

CLARIFICATION FROM THE ARCHITECT. RESOLUTIONS TO SUCH CONFLICTS WILL BE

ISSUED THROUGH ADDENDA TO THE BID DOCUMENTS. IF CLARIFICATION FROM THE

ARCHITECT IS NOT RECEIVED THROUGH AN ADDENDUM PRIOR TO THE RECEIPT OF BIDS,

THE BIDDER SHALL ASSUME THE MORE COSTLY REQUIREMENT APPLIES, AND THE

AWARDED CONTRACTOR SHALL SEEK CLARIFICATION FROM THE ARCHITECT PRIOR TO THE

EXECUTION OF THE WORK.

3. IF A CONFLICT EXISTS BETWEEN DRAWINGS OF DIFFERENT SCALES, CONSULT THE

ARCHITECT FOR CLARIFICATION.

4. IN THE ABSENCE OF A WRITTEN DIMENSION, OR IN CASE OF DOUBT AS TO THE PROPER

MEASUREMENT, CONSULT THE ARCHITECT FOR CLARIFICATION.

5. IF AN AREA OR SPACE IS SHOWN, BUT IS NOT CLEARLY DEFINED OR INDICATED BY NOTES, PROVIDE THE SAME MATERIALS AND FINISHES AS SCHEDULED OR DETAILED FOR AREAS

OF SIMILAR USE ELSEWHERE IN THE BUILDING,

6. SECTIONS INDICATED ARE INTENDED TO SHOW THE SPECIFIC CONSTRUCTION WHERE

REFERENCED AS WELL AS ESTABLISH THE GENERAL CONSTRUCTION DETAILS FOR

SECTIONS THROUGHOUT THE PROJECT WHICH DO NOT HAVE SPECIFIC SECTIONS DRAWN.

THE MOST SIMILAR SECTIONS TO BE ADAPTED TO ANY SECTIONS NOT DETAILED. ANY

SPECIFIC QUESTIONS CONCERNING CONSTRUCTION NOT ADEQUATELY COVERED BY THE

ABOVE SHOULD BE DIRECTED TO THE ARCHITECT DURING THE BIDDING.

7. TYPICAL DETAILS THROUGHOUT THE DRAWING SET TO APPLY FOR ALL APPLICABLE

CONDITIONS EVEN IF NOT SPECIFICALLY SHOWN OR REFERENCED.

8. ALL APPURTENANCES BUILT INTO OR THROUGH WALLS, INCLUDING DOORS, DUCTS,

WINDOWS, LOUVERS, GRILLES, MECHANICAL WORK, ETC. TO FIT TIGHT AND BE

THOROUGHLY SEALED AROUND PERIMETERS. WORK AT EXTERIOR WALLS TO BE FLASHED

OR OTHERWISE WATERPROOF SEALED.

9. FIELD CHECK ROUGH AND/OR FINISHED DIMENSIONS FOR ACCURATE FITTING OF

WINDOWS, AND OTHER INSTALLATIONS PRIOR TO SHOP OR FACTORY FABRICATION.

PROVIDE FILLER STRIPS, SCRIBE STRIPS, BASES, CLOSURE FINISHES AND TRIM FOR A

COMPLETE INSTALLATION.

10. EACH CONTRACTOR MUST REFER TO ALL DRAWINGS AND BE RESPONSIBLE FOR WORK

PERTAINING TO THEIR PARTICULAR TRADE. ALL CONTRACTORS MUST COORDINATE THE

WORK OF ALL TRADES AND FIELD CHECK AGAINST ANY CONFLICTS BETWEEN DRAWINGS.

REPORT CONFLICTS TO THE ARCHITECT FOR CLARIFICATION.

11. FOR THE PURPOSES OF BIDDING (UNLESS OTHERWISE NOTED), ALL SYMBOLS (LABELED /

TAGGED OR UNLABELED/UNTAGGED) WHICH ARE LOCATED ON THE

FURNISHING/EQUIPMENT PLANS TO BE CONSIDERED AS IN CONTRACT WORK TO BE

PROVIDED BY THE CONTRACTOR. ALL SYMBOLS LOCATED ON THE PLANS DENOTE EITHER

FURNITURE, EQUIPMENT, CASEWORK OR MILLWORK. WHERE A SYMBOL IS LOCATED ON

THE PLANS BUT IS NOT LABELED OR TAGGED TO A SCHEDULE, THE CONTRACTOR MUST

SEEK CLARIFICATION FROM THE OWNER OR ARCHITECT BEFORE PROCEEDING. FOR

PURPOSES OF BIDDING ONLY, IF CLARIFICATION CANNOT BE OBTAINED FROM THE OWNER

OR ARCHITECT THROUGH ADDENDUM PRIOR TO THE BID DATE, THE CONTRACTOR MUST