RA-133W-18-RP-0028 WSR-88D SHELTER MAINTENANCE AND REPAIR
Attachment 2
Department of Commerce (DOC) National Oceanic and Atmospheric Administration (NOAA)
National Weather Service (NWS) Radar Operations Center (ROC)
STATEMENT OF WORK (SOW)
WSR-88D SHELTER MAINTENANCE
AND REPAIR
April 2018
Contents:
1. INTRODUCTION
2. BACKGROUND
3. SCOPE
4. GENERAL REQUIREMENTS
5. SPECIFIED MATERIALS
6. MAINTENANCE REGIONS
7. MAINTENANCE PROCEDURES
8. QUALITY ASSURANCE INSPECTION POINTS
9. FINAL INSPECTION
10. CONTRACT ADMINISTRATION
11. SCHEDULE
12. GENERAL INFORMATION
13. LIST OF APPENDICES
1. INTRODUCTION
The National Weather Service (NWS), National Oceanic and Atmospheric Administration (NOAA) within the Department of Commerce (DOC) manages the Next-Generation Weather Radar (NEXRAD) network high-resolution Weather Surveillance Radar – 88 Doppler (WSR-88D). The NEXRAD are operated by the National Weather Service (NWS), Federal Aviation Administration (FAA) and U. S. Air Force (USAF). NEXRAD detects weather events and is the primary detection system used by the NWS to support issuance of severe weather warnings, and is used by the FAA and USAF to support safety of flight operations.
Equipment required for operation of the NEXRAD radars is contained in three separate pre-cast concrete shelters at each site. The Government requires minor refurbishment of these shelters.
2. BACKGROUND
The NWS requires maintenance of pre-cast concrete radar shelters as part of the shelter maintenance and repair Service Life Extension Program (SLEP). The Program is comprised of up to 160 Doppler radars located within the United States, of which 143 are eligible for SLEP. Each radar site has three pre-cast concrete shelter enclosures, including a Radar Data Acquisition (RDA) Shelter, Generator (GEN) Shelter, and Transit Power and Maintenance Shelter (TPMS), which houses the electronic radar equipment. The shelters at each radar site require periodic maintenance and repairs to provide continued protection of sensitive radar equipment, and ensure longevity of individual shelter enclosures. These shelters have been in service for 11-15 years.
The construction of the three types of shelters are similar in that they are all constructed of concrete panels with exposed aggregate exterior walls and a concrete roof with a rubber protective coating on the roof exterior. All shelters have painted metal doors/frames, ventilation hoods, diesel fuel fill tubes, etc. The RDA and GEN Shelters have caulked joints between concrete panels, whereas the TPMS Shelter does not use caulking in these joints. Photographs of each type of shelter are included in Appendix A. Dimensions of each shelter are contained in Appendix B.
2.1 Shelter Pictures:
Figure 1: Aggregate wall and door Figure 2: Painted surfaces Figure 3: Shelter roof
3. SCOPE
The contractor shall provide all material and labor required to complete each maintenance task as described in this Statement of Work.
The procedures and materials to be used for each maintenance task are included with this SOW. All applicable maintenance procedures will be performed on each shelter.
4. GENERAL REQUIREMENTS
All maintenance shall be performed at the site of the equipment shelters (found in Appendix C). The contractor will provide all materials required to accomplish refurbishment of all shelters identified in the task order. The contractor will coordinate arrival and work accomplishment with identified NWS site personnel, and remove all waste materials resulting from the maintenance actions. The five maintenance tasks to be performed under this contract are: cleaning and replacing roof, cleaning and re-sealing aggregate surfaces, repainting metal surfaces, removing and replacing all exterior caulk in joints, and replacing steel doors as required.
Although the Contracting Officer’s Representative (COR) will be the primary Point of Contact (POC) when coordinating execution of task orders, the work site POC will coordinate site entry, inspections, final acceptance, etc.
The exterior maintenance to be performed by the contractor on shelter enclosures is specified for each site location and each shelter at that location and may include:
• Cleaning and sealing of exterior aggregate wall surfaces
• Painting external trims and metal surfaces
• Remove/replace caulking on and around external walls and surfaces
• Remove/replace lockset/deadbolt on external steel doors
• Remove/replace steel exterior doors
• Painting external steel doors and frames
• Remove/replace external roofing surfaces
The procedures and materials to be used for each maintenance task are included with this SOW. All applicable maintenance procedures will be performed on each shelter as identified in the individual Task Orders.
5. SPECIFIED MATERIALS
Appendix D contains the list of materials specified for use in completing these maintenance tasks, along with product descriptions and Safety Data Sheets (SDS). The contractor shall not deviate from this list by substituting other products unless the deviation is approved by the COR in writing. The contractor shall arrive at each site with sufficient quantity of material to accomplish all maintenance tasks on all site equipment shelters.
6. MAINTENANCE REGIONS
The NWS Radar Operations Center (ROC) oversees five separate regions requiring shelter refurbishment:
Eastern, Western, Central, Southern, and Department of Defense (see Appendix C).
6.1 DIFFERING CONDITIONS
Due to variable weather conditions at individual sites within each region, the maintenance requirements may vary from site to site, or region to region.
Example a)
Many sites within the Eastern region currently have Rhino brand roofing covering the roofs of their shelters.
These sites may elect to either replace with a Rhino system, or choose the Conklin brand roofing system.
Example b)
Sites located in an environment that is caustic to standard steel doors may elect to replace them with stainless steel doors.
7. MAINTENANCE PROCEDURES
The NWS Radar Operations Center (ROC) developed maintenance procedures to be used by NWS personnel responsible for maintaining these equipment shelters. The procedure for each maintenance action is provided in Appendix E. The contractor shall follow these procedures while performing under this contract. Any deviations must be approved in writing by the COR.
8. QUALITY ASSURANCE INSPECTION POINTS
Proper preparation is critical to receiving a high quality result. For this reason, a number of inspection points are identified in this contract. One or more of these inspection points may be invoked for each task order at the discretion of the COR. The possible inspection points include the following:
Table 8.1 INSPECTION POINTS
Section and Title Description
8.1. Inspection of Material Prior to commencement of work, refurbishment materials will be inspected to ensure they coincide with those referenced in appendix D.
8.2. Inspection of Roof
Preparation
Prior to application of roof coating, the roof will be visually inspected for cleanliness.
8.3. Inspection of Aggregate
Preparation
Prior to application of aggregate sealant, the exterior walls will be visually inspected for cleanliness.
8.4. Inspection of Metal
Surface Preparation
Prior to the application of primer, all exterior metal surfaces will be inspected to ensure that all rust has been removed and all surfaces to be primed and painted are clean and have been appropriately scuffed to accept the primer.
8.5. Inspection of joints prior
to Re-Caulking
Prior to replacing caulk in exterior joints, the joints will be inspected to ensure all old caulk material has been removed, residual caulk material is removed from bonding areas on each side of the joint, joint area is clean, backer rod has been replaced and bond release tape is in place.
8.6. Inspection of Door and
Lockset
Ensure door, frame and lockset are installed per manufacturer’s instructions. Ensure door provides appropriate weather seal around all edges, and closes securely. Ensure lockset keyway matches existing keys, and is installed per manufacturer’s instruction.
9. FINAL INSPECTION
A mandatory final inspection and Government acceptance of work shall be conducted on the resulting condition of each shelter refurbished under a task order. This inspection shall be performed by a NWS site representative in the presence of the contractor. Items listed in Table 7.1 will be used to verify work performed at the site meets contractual obligations, and will be used to substantiate contractor invoicing. Any quality issues will be addressed and corrected at this time. The NWS representative shall also ensure that all resulting waste materials and debris are removed from the site by the contractor. The contractor is responsible for restoring the site to its original condition prior to submitting an invoice for payment.
10. CONTRACT ADMINISTRATION
The NWS COR is responsible for the overall scheduling of the project activity and selection of communication needs. Regular meetings between the Contractor and the NWS COR will be required to outline a work schedule and prioritize tasks. The Contractor is responsible for scheduling the work to be done each day, within the work schedule of the NWS staff. Contractor personnel are required to do the work independently, generating high quality results in a timely manner.
Travel is required as part of the contract, and the will be done at the Contractor’s own risk and expense.
10.1. GOVERNMENT CONTACT INFORMATION
NOAA customer contact information is located in Appendix C.
11. SCHEDULE
11.1. PERIOD OF PERFORMANCE
The period of performance of each individual task order will be undetermined at the time the order is issued.
The appointed COR will be responsible for coordinating the sequence of execution of each task order under this contract. The quantity of task orders awarded as a result of this contract will depend upon availability of funds and resultant cost of services.
11.2. IMPLEMENTATION SCHEDULE
Execution of shelter refurbishments shall begin NLT 30 calendar days after contract award. Each shelter refurbishment will be coordinated with the assigned COR or his/her designated Government representative, to determine site availability, accessibility, and scheduling.
The contractor shall develop a site work schedule detailing work to be performed at each site and dates for completion, sufficient to support evaluation of progress made toward completion at each site requiring shelter refurbishment.
11.3. MINIMUM CREW SIZE
Many radar sites are located in remote areas. For safety purposes, a minimum crew size of 2 persons must be used in performing tasks under this contract.
11.4. ON-SITE COORDINATION
During the week prior to crews arriving at each radar site, the contractor shall participate in a pre-arrival meeting, along with Contracting Officer’s Representative, or other Government personnel from the ROC, personnel from the radar site, and the Contracting Officer (if required). The purpose of this meeting is to ensure that radar operations are not unnecessarily impacted and that the refurbishment contractors are not unnecessarily delayed in completing their tasks. While painting vent hoods and air conditioners, it will be necessary to shut down the TPMS and RDA equipment. This evolution must be planned and scheduled upon arrival of the work crew on site. Equipment downtime must be minimized and may be affected by weather conditions in the area.
Topics to be discussed:
• Introduction of key personnel along with contact information
• Arrival date, time, and location to meet with site POC
• Availability of site facilities (e.g. water, electric, restrooms, etc.)
• Intended schedule of activities
• Inquiries regarding any severe weather (high winds, lightning, etc.) expected on, or shortly after the start date
11.5. IN-BRIEF
On the day of arrival, prior to any work commencing, contractor personnel supervising contractor activities will meet with senior Government site-maintenance personnel to ensure there are no changes in circumstances since the pre-arrival conference.
12. GENERAL INFORMATION
12.1. NON-PERSONNEL SERVICES
With exception to safety and security issues, the Government will not control, direct, or supervise Contractor employees during the performance of this contract. Contractor employees performing services under this order shall be controlled, directed, and supervised at all times by management personnel of the Contractor.
Contractor management shall ensure that employees properly comply with the performance work standards outlined in the PWS. Contractor employees shall perform their duties independent of, and without the need for supervision by, any Government official. The tasks, duties, and responsibilities set forth in the Contract may not be interpreted or implemented in any manner that results in any Contractor employee creating or modifying Federal policy, obligating the appropriated funds of the US Government, overseeing the work of Federal employees, providing direct personal services to any Federal employee, or otherwise violating the prohibitions set forth in Parts 7.5 and 37.1 of the Federal Acquisition Regulation (FAR). The Government will control access to the facility and will perform the inspection and acceptance of the completed work.
12.2. HOURS OF OPERATION
The duration of the Contractor’s performance period is based on an estimated regular labor hours for the time period as specified in the task order. During this part-time/full-time task order, the Contractor shall work/shall work up to 40 hours per week during the normal operating hours of the facility, which are a standard eight (8) hours per day, five (5) days per week. Work schedules should include working within the core hours of the Center, which are from 9:00 a.m. to 3:30 p.m. An alternate work schedule may be requested and approved by the NWS Project Leader, provided the Contractor’s work hours do not total more than 40 hours per week/40 hours per week.
The Contractor is not authorized to perform duties under this task order on days when the facility/campus is closed, i.e. ., Government Furlough, inclement weather, power outages, legal and federal holidays, etc. ., unless otherwise noted. These will be considered non- working (non- pay) days. In the event of Federal dismissal or facility closure during normal work hours, the Contractor will be notified directly by the NOAA COR or Project Leader to depart from the facility/campus grounds. Should the facility be closed during off- hours, the Contractor will be provided information regarding the site's status to be able to make an informed decision on reporting for work on time or a delayed time period, or non- work status and notifying both the Contractor' s point of contact as well as the NOAA COR or Project Leader.
12.3. GOVERNMENT FURNISHED EQUIPMENT
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities, except as otherwise specified.
12.4. SAFETY AND ENVIRONMENTAL REQUIREMENTS
The Contractor and shall comply with all applicable Federal, State, and Local law and regulations pertaining to safety and environmental requirements.
The Contractor shall be able to provide to the COR, or the designated Government representative, the Safety Data Sheets (SDS) for all chemical products prior to materials being brought on site. These products include, but not limited to solvents, cleaners, paints, caulk, and roof coatings.
The Contractor shall comply with the following:
1. All products shall be kept in original container with legible label.
2. If the product is placed in smaller container for use, the smaller container shall be marked legible stating the product it contains.
3. There shall not be any chemical product mixed together unless intended by the chemical manufacture.
Contractor shall perform all tasks in a safe manor, and take all necessary precautions to mitigate risks. The Contractor shall:
1. Provide appropriate safety barricades, signs, and signals.
2. Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 (OSHA Regulations
Standards for Safety and Health Regulations for Construction) and 29 CFR Part 1910 (OSHA Regulations Standards for Occupational Safety and Health Standards).
3. The Contractor shall dispose of all waste material/products off site in accordance of Federal, State, and Local law and regulations at Contractors expense. The Contractor shall remove all unused materials/products, to include waste, which were either supplied or purchased by the Contractor in the performance of the task order.
4. The contractor is responsible for the clean-up and remediation of any chemical/ compound spills.
5. Upon arrival, the Contractor and/or employee shall sign in on the security log sheet when entering the property.
13. LIST OF APPENDICES
Appendix A - Shelter Pictures Appendix B - Dimensional Quantities for Calculating Material Requirements Appendix C - Site Locations with POC’s Appendix D - Materials Appendix E - Exterior Building Maintenance and Repair Procedures
| 1. INTRODUCTION |
| 2. BACKGROUND |
| 2.1 Shelter Pictures: |
| 3. SCOPE |
| 4. GENERAL REQUIREMENTS |
| 5. SPECIFIED MATERIALS |
| 6. MAINTENANCE REGIONS |
| 6.1 DIFFERING CONDITIONS |
| 7. MAINTENANCE PROCEDURES |
| 8. QUALITY ASSURANCE INSPECTION POINTS |
| Table 8.1 INSPECTION POINTS |
| 8.1. Inspection of Material |
| 8.2. Inspection of Roof Preparation |
| 8.3. Inspection of Aggregate Preparation |
| 8.4. Inspection of Metal Surface Preparation |
| 8.5. Inspection of joints prior to Re-Caulking |
| 8.6. Inspection of Door and Lockset |
| 9. FINAL INSPECTION |
| 10. CONTRACT ADMINISTRATION |
| 1. |
| 2. |
| 3. |
| 4. |
| 5. |
| 6. |
| 7. |
| 8. |
| 9. |
| 1. |
| 2. |
| 3. |
| 4. |
| 5. |
| 6. |
| 7. |
| 8. |
| 9. |
| 10.1. GOVERNMENT CONTACT INFORMATION |
| 11. SCHEDULE |
| 11.1. PERIOD OF PERFORMANCE |
| 11.2. IMPLEMENTATION SCHEDULE |
| 11.3. MINIMUM CREW SIZE |
| 11.4. ON-SITE COORDINATION |
| 11.5. IN-BRIEF |
| 12. GENERAL INFORMATION |
| 12.1. NON-PERSONNEL SERVICES |
| 12.2. HOURS OF OPERATION |
| 12.3. GOVERNMENT FURNISHED EQUIPMENT |
| 12.4. SAFETY AND ENVIRONMENTAL REQUIREMENTS |
| 13. LIST OF APPENDICES |
File details come from the government source that posted it.