Statement of Work

View the file

Other files

File Type Posted
Amendment_01_SF30.pdf PDF
2100101-B.pdf PDF
2310041-B.pdf PDF
RA133W-16-RQ-0931.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

“TOP HAT” I/O PANEL UPGRADE

Statement of Work

1.0 INTRODUCTION

1.1 Background

The National Weather Service (NWS) has 162 operational WSR-88D (Weather Surveillance Radar – 1988) sites deployed throughout the United States and at selected sites overseas. The WSR-88D is comprised of three systems. These are the Radar Data Acquisition (RDA), Radar Product Generator (RPG) and the various display units used to depict radar products. The requirement for this procurement updates the I/O panel associated with the Open Radar Data Acquisition (ORDA) processor cabinet.

1.2 Purpose

In effort to modernize the ORDA enclosure cabinet to accept new communication and power cables associated with recent planned upgrades a new I/O panel needs to be manufactured. This panel, called the “Top Hat”, part number 2310041-301 also has 6 (six) sub-panels, part numbers 2100101-101 through -106. The Radar Operations Center (ROC) will require the manufacture and delivery of one first article panel set which includes the main panel (Top Hat) and upon acceptance of the first article, the production of the main panel and sub-panels.

2.0 SCOPE OF WORK

A first article panel set will be required for testing and acceptance by NWS ROC. The first article will include part number 2310041-301 and sub-panels 2100101-101 through -106. Upon acceptance of the first article a production quantity will be required as stated in CLINs 0002 through 0008 below. Each panel will be constructed out of “Galveneel” Steel”, rivet nuts, and silk screen markings per the attached drawings to this Statement of Work (SOW).

2.1 Documentation and Attachments

Manufacturing documentation associated with each part is provided with this SOW as follows:

- Attachment 1: ROC Drawing 2310041-301, Sheets 1 and 2.

- Attachment 2: ROC Drawing 2100101-101 Through -106, Sheets 1 Through 5.

3.0 DELIVERABLES

Manufacture and deliver the below CLINs in accordance with drawings 2310041-301 and 2100101-101 through -106 (provided).

CLIN 0001 First Article, Deliver First, I/O (Top Hat) and Adapter ORDA Panels The vendor will manufacture a quantity of one each (1 EA) “First Article” of ROC part numbers 2310041-301 (Rev B) and Sub-panels, 2100101-101 through 2100101-106 and deliver to the ROC at the address and POC listed below no later than four weeks after contract award.

CLIN 0002 Production Panel, I/O, ORDA (TOP HAT) Upon acceptance of the first article, the vendor will manufacture a quantity of 227 each production units of ROC part number 2310041-301 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0003 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 237 each production units of ROC part number 2100101-101 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0004 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 62 each production units of ROC part number 2100101-102 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0005 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 237 each production units of ROC part number 2100101-103 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0006 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 853 each production units of ROC part number 2100101-104 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0007 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 46 each production units of ROC part number 2100101-105 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

CLIN 0008 Production Panel, ORDA Adapter

Upon acceptance of the first article, the vendor will manufacture a quantity of 46 each production units of ROC part number 2100101-106 (Rev B) and deliver to the ROC at the address and POC listed below no later than eight weeks after acceptance of “First Article” CLIN 0001.

3.1 Shipping and Delivery

All CLINs shall be delivered to:

NWS ROC NEXRAD

C/O Daniel Hoffman/RMT

1424 Halley Avenue

Norman, OK 73069

3.2 Delivery Schedule

CLIN 0001 - 30 days ARO

CLINs 0002 through 0008 - 45 days after Government acceptance of CLIN 0001.

4.0 COR & TECHNICAL POCs

COR: Daniel Hoffman, daniel.t.hoffman@noaa.gov, 405-573-3308.

Technical POC: Blair Baldridge, blair.baldridge@noaa.gov, 405-573-3424.