Amendment 01 - Questions Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2100101-B.pdf | ||
| 2310041-B.pdf | ||
| NWWG1300-16-01031_SOW_TOP_Hat_08Jul16.doc | DOC document | |
| RA133W-16-RQ-0931.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name and Title of Signer (Type or Print) 16A. Name and title of Contracting Officer (Type or Print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States of America
(Signature of Contracting Officer)
16C. Date Signed
(Signature of person authorized to sign)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITIONS UNUSABLE Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. Contract ID Code Page of Pages 1 2
2. Amendment/Modification No. 3. Effective Date 4. Requisition/Purchase Req. No. 5. Project No. (if applicable) 01 September 6, 2016 NWWG1300-16-01031
6. Issued By Code AJ730004 7. Administered By (If other than Item 6) Code
U.S. DEPT. OF COMMERCE - BOULDER LABS SEE BLOCK 6
ACQUISITION MANAGEMENT DIVISION SOU6
325 BROADWAY
BOULDER, CO 80305
8. Name and Address of Contractor (No., Street, County, and Zip Code) (X) 9A. Amendment of Solicitation No.
X
RA133W-16-RQ-0931
9B. Date (See Item 11) August 31, 2016 10A., Modification of Contract/Order No.
10B. Date (See Item 13)
Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended X is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDG- MENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting and Appropriation Data (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACT/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. This change order is issued pursuant to: (Specify authority) The changes set forth in item 14 are made in the Contract Order No. in item 10A.
B. The above numbered Contract/Order is modified to reflect the administrative changes (such as changes in paying office, appropriation date, etc.)
Set fourth item 14, pursuant to the authority of FAR 43.103 (b)
C. This supplemental agreement is entered into pursuant to authority of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, X is required to sign this document and return 1 copies to the issuing office.
14. Description of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to provide the attached responses to questions.
RA133W-16-RQ-0931
Amendment 01
QUESTION 1:
The Mtl’s are specified as 15 Ga & 17 Ga ASTM A 366 Steel Sheets, these are not available for this Mtl so I will quote using 14 Ga (.0747”) & 16 Ga (.0598”).
ANSWER:
The proposed change to 14 to 16 Gauge is acceptable.
QUESTION 2:
Ref Drawings & Statement of Work:
Drawings included in the Solicitation are 2100101-B & 2310041-B; Questions, are there Drawings for 2100101-101, -102, -103, -104, -105 & -106 &/or are they the same as 2100101-B;
Same for 2310041-B Drawing 2310041-301.
ANSWER:
Drawing 2310041-301 Rev B contains the main panel front and back (2 pages). Drawing 2100101 contains the sub panels that will be attached to the main panel. This drawing depicts dash numbers 101 through 106 (5 pages).
QUESTION 3:
Ref DRAWING 23100411:
Regarding 2310041, is the Tin Arc Spray on the inside wall and underside surfaces of the flanges? If so, we will probably have to spray this in the flat stage, and hope that the bending does not damage the Spray Coating.
The middle view on page one depicts the spray coating on the outside walls of the flanges and running down the sides? Or do they just want the entire inside surface of the panel coated?
ANSWER:
In the Scope of the Statement of Work (SOW) we stated that the requirement is for Galvannealed steel to replace the carbon steel on all of the drawings. The Tin Arc spray should no longer be necessary. The Galvannealed steel will ensure that we have good electrical connectivity throughout the cabinet. Please note: On the main panel (drawing 2310041) we also want to replace the clinch nuts with rivet nuts.
QUESTION 4:
Ref PARTS:2100101-B & 2310041-B:
Is the Spray Coating Tin as in Tin Can, or is it Titanium Nitride, which is a better conductor?
ANSWER:
In the Scope of the Statement of Work (SOW) we stated that the requirement is for Galvannealed steel to replace the carbon steel on all of the drawings. The Tin Arc spray should no longer be necessary. The Galvannealed steel will ensure that we have good electrical connectivity throughout the cabinet.
File details come from the government source that posted it. Updated .