Amendment 001 Fire Break Clearing and Fencing, Fort Cobb Reservoir, OK
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
R17PS01176
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59101
R60
2021 4th Ave. North
GP-5000
Great Plains Region Bureau of Reclamation
08/01/2017001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/01/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
IGF::OT::IGF::
Fire Break Clearing and Fencing, Fort Cobb Reservoir, Washita Basin Project, Oklahoma See Page 2 for changes incorporated in this solicitation.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Paris Everson
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Fire Break Clearing and Fencing Amendment 001 Fort Cobb Reservoir Washita Basin Project, Oklahoma R17PS01176
DESCRIPTION OF CHANGES: page 2of 4 Receipt of Bids: The hour and date for receipt of bids remains unchanged.
SITE VISIT: The following individuals attended the organized site visit on August 10, 2017.
CONTRACTOR QUESTIONS AND RECLAMATION RESPONSES page 3 of 4 Note: The following contractor questions were not captured verbatim, but are intended to capture the intent of the questions and discussions which occurred during the pre-bid site visit.
Question 1:
Does Reclamation have contact information for landowners adjacent to the specified work?
Reclamation Response:
Reclamation does have this information and can provide it to the selected contractor after award.
Question 2:
Will the Contractor need to coordinate with any overhead utilities?
Reclamation Response:
Section 01 56 15 – Protection of Existing Utilities states that the contractor is responsible for protection of overhead utilities.
Question 3:
How much debris disposal is anticipated under CLIN 4 – Demolition?
Reclamation Response:
Delineated area of debris disposal is identified on Drawing 853-514-1091. Contractor shall be responsible for visiting the site to thoroughly familiarize himself/herself with the conditions of the existing site as specified in Section 02 22 00 – Demolition. It is estimated that this volume could be approximately one dump truck load.
Question 4:
What are the concrete requirements when setting posts?
Reclamation Response:
Drawings 853-514-1100 through 853-514-1103 direct hole size and depth for the various posts to be installed under this contract as well as the minimum breaking strength for concrete. Section 32 31 30 – Fencing and Gates, Part 3.02 A directs requirements for concrete placement. Part 3.02 B requires a minimum of seven (7) days cure time before attaching fencing, cable, or gates to H-braces, corner posts, or posts.
Question 5:
If boundary dispute issues arise after surveying which require Reclamation to utilize its 90 day review period described in the Work Descriptions section, can the period of performance be adjusted? Is the contractor responsible for performing biological monitor presence/absence surveys if the period of performance adjustment causes clearing work to occur within the migratory bird nesting season that would otherwise not have?
Reclamation Response:
The period of performance can be adjusted at the discretion of the contracting officer. The contractor is responsible for any costs associated with requirements for a biological monitor per Section 31 11 00 - Clearing.
Question 6:
Is brush-hogging considered to be an activity which would require a biological monitor if performed during the nesting season?
Reclamation Response:
Brush-hogging is not considered to be part of clearing and therefore does not require a biological monitor. Per Section 31 11 00 – Clearing; Brush-hogging is to be performed prior to final inspection as a means to verify to the COR that the cleared and finished surface is suitable for future brush-hog maintenance by others, as well as to allow adequate inspection.
Question 7: page 4 of 4 Are there any areas which cannot be accessed by tracked equipment due to wet or muddy conditions?
Reclamation Response:
Part IV, Section L-19 states that offerors are urged and expected to inspect the site where the work will be performed. It is not anticipated that any areas will be inaccessible.
Last hour and time to submit questions is: 1200 hours MDT on August 23, 2017
File details come from the government source that posted it. Updated .