AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE Page of Pages
2. AMENDMENT/MODIFICATION
3. EFFECTIVE DATE
07/21/2016
4. REQUISITION/PURCHASE NO.
0040279392/17840
5. PROJECT NO.
20-C0858
6. ISSUED BY CODE: 00020
Department of the Interior Bureau of Reclamation/Mid-Pacific Region Office 2800 Cottage Way Sacramento, California 95825-1898
7. ADMINISTERED BY CODE: 00020
Department of the Interior Bureau of Reclamation/Mid-Pacific Region Office 2800 Cottage Way Sacramento, California 95825-1898
8. NAME AND ADDRESS OF CONTRACTOR
X
9A. AMENDMENT OF SOLICITATION NO.
R16PS01169
9B. DATED (SEE ITEM 11)
07/21/2016
10A. MODIFICATION OF CONTRACT NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of offers () is extended (X) is not extended.
Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO. AS
DESCRIBED IN ITEM 14
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:
THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor ( ) is not, ( ) is required to sign and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)
The Solicitation cited in block 9A above, Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures is hereby amended.
Purpose: The purpose of this amendment is to incorporate various changes to the solicitation documents.
Description: This amendment hereby incorporates the following solicitation changes: (1) Incorporate revisions to SOW (2) Incorporate revision to Section A (3) Incorporate revision to Section F (4) Incorporate Section J, Attachment No. 6 (Questions and Answers).
The date and time for receipt of offers remains unchanged at July 28, 2016 at 1:00 p.m.
The contractor shall acknowledge all amendments to the solicitation, as required in Part 19 of the SF-1442.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (TYPE OR PRINT)
16A. NAME AND TITLE OF CONTRACTING OFFICER
Contracting Officer
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
ERIM CELIK
(Signature of Contracting Officer)
16C. DATE SIGNED
NSN 7540-01-152-807030-105 STANDARD FORM 30 (REV. 10-83)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
MICROSOFT WORD VERSION
Amenment No. 0002 Solicitation No. R16PS01169 jcabral Rectangle jcabral Rectangle jcabral Rectangle jcabral Rectangle
Folsom Dam M&I TCD Safety Measures SOW No. 20-C0858 Folsom Dam – Folsom Unit – Central Valley Project – California
Statement of Work - 1
STATEMENT OF WORK (SOW)
FOLSOM DAM MUNICIPAL AND INDUSTRIAL WATER SUPPLY
TEMPERATURE CONTROL DEVICE (TCD) SAFETY MEASURES
CENTRAL VALLEY PROJECT, CALIFORNIA
DEFINITIONS
A. COR: Contracting Officer Representative.
B. CCAO: Central California Area Office.
C. IWRC: Independent Wire Rope Core.
D. OGR: On-site Government Representative.
E. Reclamation: Bureau of Reclamation.
F. TCD: Temperature Control Device.
1.0 BACKGROUND
The Folsom Dam Temperature Control Device (TCD) is a three sided structure approximately 9.5’ wide by 9.0’ deep that covers the existing trash rack. This enclosure, referred to as the enclosure structure, is approximately 147’ high and is located upstream of the existing trash rack structure and extending from approximately elevation 300.00 feet up to 441.74 feet. Both sides of the enclosure structure are fabricated from structural steel plate reinforced with structural steel shapes. The front of the structure is open except for three gates. The three gates are each provided with their own set of guides enabling them to travel past each other. When fully extended, the gates almost cover the full height of the height of the enclosure structure. The gates are designed so that they operate in telescopic fashion. The upper gate referred to as the control gate is equipped with a lid that blocks flow over the top of the gate. By raising and lowering the window within the control gate, withdrawals from the reservoir can be from any elevation between 331.50 feet and 418.00 feet.
The control gate is raised and lowered by a wire rope hoist mounted on the hoist deck. The motorized hoist is sized so that the gates can be raised or lowered without stopping or reducing the flows through the structure. The hoist has a capacity of 90,000 pounds at a single speed of 4 feet per minute. The hoist is configured with a single hoist drum, with left and right handed grooves for two 1-5/8-inch diameter wire ropes. The ropes are positioned to drop off the drum directly above the gate connections when the gate is at its uppermost position, in order to minimize fleet angles.
The hoist is attached to the control gate by wire ropes, and a turnbuckle is provided on one side for adjustment of the rope tension. The existing wire ropes are constructed of galvanized steel strands with an Independent Wire Rope Core (IWRC) and are approximately 185’ in length each. The hoist deck is located at the top of the dam just below the roadway, at approximately elevation 477.00 feet. The top of this hoist deck is covered in steel grating that is fastened down with steel bolts and clips, with sections of grating able to be removed via crane to access the inside of the control structure and top of the control gate. The control structure is hung from steel corbels attached to the mass concrete of the dam.
Amendment No. 0002
Statement of Work - 2
During an inspection in December 2015 the wire ropes were found severely corroded and a subsequent rope inspection via a Reclamation climb team confirmed the components that warrant replacement. The TCD was installed and commissioned in 2003. The new rope shall be an in kind replacement, as well as other associated attaching hardware. In addition, Reclamation drawing 485-D-2327 shows a safety cage and ladder system to facilitate access to inspect and maintain the TCD structure/components including the wire ropes below the hoist platform. The cage and ladder system was never installed and otherwise is missing. Access below the hoist platform is unsafe for maintenance personnel unless personnel are climb team qualified. As such, only qualified climb team members can safely access or some other elaborate system such as scaffolding and or use of a crane can facilitate inspections below the hoist platform. Given the nexus with safety of CCAO staff, a safety cage and ladder system should be installed at the earliest possible date.
2.0 OBJECTIVES
• Replace wire ropes and connecting hardware from the control gate to drum.
• Supply and install safety access cage and ladder system.
• Confirm functionality of hoist and rope system.
• No spills/debris in Folsom Lake.
3.0 SCOPE
The Contractor that is awarded the job shall:
A. Safely rig control gate to facilitate removal of existing wire ropes.
B. Remove of and dispose of the old wire ropes and all connecting hardware including but not limited to turnbuckles and spelter sockets.
C. Install an in-kind replacement galvanized steel wire ropes and associated rated connecting hardware.
D. In coordination with Reclamation personnel, perform a functional test of hoist after installation of new wire ropes and connecting hardware.
E. Supply and install safety access cage and ladder system.
F. Repair any facilities damaged due to construction activities.
The Contractor shall propose their method for Reclamation’s approval to support the control gates in order to remove the tension on the ropes to facilitate the replacement of the wire ropes.
See Sections 6.21 and 6.22 below. All corroded and damaged components of the rope system shall be replaced. All rope connecting hardware shall be rated the same and new.
4.0 TYPE OF CONTRACT
The Government will award a firm fixed priced construction contract.
5.0 PERIOD OF PERFORMANCE
All work shall be complete within 120 calendar days after notice to proceed. Period of performance to include preparatory work, approval of submittals and all on-site work – replacement of wire ropes and installation of safety access cage and ladder system. All on-site work shall be completed within 30 days.
Statement of Work - 3
5.1 Recognized Holidays
No work shall occur during Federal holidays.
5.2 Hours of Operations
The Contractor is responsible for conducting business, between the hours of 0700 – 1700 Monday through Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
5.3 Place of Performance
The work under this contract will be performed at Folsom Dam located at 7794 Folsom Dam Road, Folsom, CA 95630.
5.4 Security
A. Contractor Security Requirements
The contract solicitation may delineate any applicable specific Contractor security requirements. As such, Contractor personnel performing work under this contract shall meet the security requirements at the time of award, and must maintain the level of security required for the life of the contract. The Contractor shall coordinate access for personnel, materials, and equipment with the COR/OGR prior to mobilization on site.
The COR/OGR will escort Contractor personnel as necessary and will be at the work site any time the Contractor is on site. The COR/OGR will need the names, company names, position of each individual and dates and times each individual is expected on site at least five business days prior to any work conducted onsite.
B. Site Security Less any preliminary activities, the Government anticipates about 2-3 weeks on site to complete the installation work. Because of this short duration, Contractor storage areas should not be required. Any material stored onsite shall be done at the risk of the Contractor. One lane of Folsom Dam Road shall remain open at all times, unless approved by the COR/OGR for a specific activity and duration.
The Contractor shall be responsible for safeguarding all government equipment, information and property provided for Contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.
6.0 DELIVERABLES
The Contractor shall provide all labor, materials, equipment and permits necessary to complete the requirements outlined in this SOW and in Reclamation approved submittals. The Contractor shall
Statement of Work - 4 remove and properly dispose of all debris such as wood to facilitate the work. The items/deliverables that follow are effectively submittal/technical requirements to be provided/complied by the Contractor, and will require approval by the COR prior to any work starting on site. Provide as-built drawings, and material data on new designs/installations and include wire rope data in a tabbed O&M manual.
See Section F for O&M manual and all other submittal requirements.
6.1 Project Schedule
The Contractor shall provide a schedule showing the major elements of work and work breakdown structure that include submittals, preliminary site investigation, fabrication and lead time on materials, and the anticipated onsite work. Clearly show your approach regarding completion of all work and delineate the work associated with the wire ropes from the installation of the safety cage and ladder system, or overlap as applicable. Utilize MS Project, Primavera, or other industry standard program in developing schedule, but provide schedule in PDF format. Provide an updated schedule within 5 business days as requested by the COR/OGR.
6.2 Site Specific Safety Program and JHA
The Contractor shall submit a written safety program covering all aspects of the onsite activities associated with the proposed work/contract and signed by a Certified Safety Professional. Indicate/show plan to support gate to facilitate removal of the wire ropes. As applicable, indicate use of portable cranes necessary to perform the work. Provide a detailed scaffolding plan as applicable in performing any work on the face of Folsom Dam.
See Section 3 and Appendix B of Reclamation Safety and Health Standards (RSHS), 2014, (http:://www.usbr.gov/ssle/safety/RSHS/rshs.html) for detailed requirements. In addition, the Contractor shall submit Job Hazard Analyses (JHAs), and the Contractor shall conduct Joint JHA field meetings with Reclamation prior to the start of any onsite activities. See Sections 3 and 4 of the RSHS for specific requirements. No work shall proceed without an approved safety program and appropriate JHAs.
6.21 Design, Fabrication and Installation of Maintenance Pad Eyes The existing pad eye design in which the wire rope hardware attach to are shown on reference drawings 485-D-2334 and 2335. These reference drawings can be utilized as a guide to design and fabricate pad eyes adjacent to the existing to facilitate replacement of the wire ropes and hardware in the future. Drawing 485-D-2333 indicates that the total estimated weight of the gates (dead load) is about 40,800 pounds. The design shall facilitate the ability utilize typical rigging hardware to support the gate. The design shall be signed off by a Mechanical PE Registered in the State of California and include calculations and all details for materials, welding, Non-Destructive Testing (NDT) and installation requirements. All welding shall be accomplished by qualified welders per AWS standards. Provide NDT reports of pad eyes and a separate report as a result of welding the pad eye to the control gate.
6.22 Plan to Support Gates and Replacement of Wire Ropes
Provide detailed plan on supporting the existing load and replacement of the wire ropes.
Indicate equipment, manpower, size and set up of crane, duration, etc.
6.3 Product and Technical Data on New Wire Rope
The hoisting rope shall be of proper design and construction for crane service. The rated capacity load plus the load block weight divided by the number of parts of rope shall not
Statement of Work - 5 exceed 20 percent of the published breaking strength of the rope. Provide length of rope sufficient to permit the required lift, plus two dead wraps at the drum, plus length for anchoring to drum. Match existing rope diameter, strands, number of wires per strand, and lay. The rope shall have an independent wire rope core and shall be pre-lubricated using the manufacturer’s recommended lubricant and lubrication process for wire ropes on outdoor B30.7 Base Mounted Drum Hoists. Provide the following per Attachment C and field verify as necessary:
a. Two 1-5/8” diameter, 6x36WS, Round, Galvanized, EIPS, Right Regular Lay, Preformed, IWRC Steel Ropes. Include rope certificate(s) with submittal.
b. Rope system rated connecting hardware (galvanized) includes but is not limited to spelter sockets and turnbuckles.
6.3.A Wire Rope Installation
The Contractor shall:
A. Support the control gate to facilitate slacking of the wire ropes per Section 6.22.
Remove the existing ropes, and prior to installation of new ropes, clean drums, and any parts/surfaces that come in contact with rope shall be free of grease, dirt, and debris.
B. Inspect drum hoist in accordance with ASME B30.7. Reeve and terminate rope(s) in a manner identical to existing installations.
C. Allow proper set-in of the rope and associated equipment.
D. Ensure new ropes come pre-lubed with a penetrating oil. Utilize environmentally friendly lubricants: “Wirelife Low Tox Penetrating Lubricant (2011)” or equivalent as approved can be used to ensure penetration to the inner part of the rope. The pre-lubed ropes shall be “sealed” the entire length with “Earthwise EAL Wire Rope Grease (3353)” or equivalent as approved.
E. Properly dispose of old wire rope and any excess materials.
Statement of Work - 6
6.4 Product, Technical Data and Shop Drawings for Safety Access and Ladder System The Contractor shall supply and install a safety access cage and ladder system per reference drawings in Attachment B. The safety access cage and ladder system to be provided starts at above the hoist deck (El. 477 feet) and continues downward to El. 461 feet to El. 444 feet and to the concrete landing at El. 428 feet. These reference drawings are a guide, but can be utilized to develop shop drawings for approval. The Contractor shall verify field conditions as necessary in developing shop drawings. Work includes but is not limited to installation of ladders, platforms, platform guardrails, platform grating, and guardrails on the concrete bulkhead gate platform for a complete system in providing safe access to areas below the TCD hoist platform. The Contractor shall remove and properly dispose of all debris such as wood to facilitate the work. See Attachment A and F for submittal requirements.
Note: Drawings included in Attachment B were designed to obsolete design codes. New design codes are to be used as indicated in Section 8.0 of this SOW. All installed items associated with safety access ladder and platform systems shall meet all applicable design codes for structural applications in California.
6.5 Water Pollution Control and Spill Prevention
See Attachment D for requirements.
6.6 Repair of Site to Pre-Construction Conditions
After completion of work, restore and repair all areas where construction activities negatively impacted the facilities. Contractor to perform a site assessment prior to mobilization to verify initial conditions. All restoration and repair activities at are the cost of the Contractor. Contractor to submit repair methods to the Government prior to implementation.
7.0 GOVERNMENT FURNISHED PROPERTY
See applicable information under 5.4 Security above. The Contractor shall be given an adequate work area, and parking shall be allowed on site as coordinated through the COR/OGR and upon approval of all submittals. Therefore, the TCD control gate and system will be turned over to the Contractor for repairs as outlined in this SOW and as coordinated and approved by the Government.
7.1 Services
At mobilization, the Government will operate the TCD through its full range of operation with all parties present. The contractor shall note and record the high and low digital and mechanical elevation readouts and match these readings as a result replacing the wire ropes.
Any other pertinent existing conditions/parameters shall be noted by the Government and the Contractor at that time to ensure the TCD is returned to a same and fully operational state when the TCD is handed back to the Government. Existing Government cranes will not be available for use by the Contractor or Government personnel. Therefore, the Contractor shall provide any cranes required and provide qualified crane operators and riggers, with
Statement of Work - 7 certifications provided to the COR at least five days before any planned operations.
Reclamation personnel may observe rigging and similar operations to ensure safety, and protection of equipment. Although, it is the intent of Reclamation to hand off the TCD to the contractor until substantial completion, Reclamation reserves the right to operate the TCD on behalf of the Contractor because of potential safety concerns, or operations that Reclamation may be much more familiar with thereby limiting any potential issues. The Contractor shall be expected to provide all qualified personnel, ladders, equipment, materials, etc. to facilitate completion of the work.
7.2 Facilities
The Government will provide an accommodating work area as indicated in Section 7.0 above.
7.3 Utilities
There will be no restroom facilities available at Folsom Dam. Assume that no potable water is available. 120VAC power may be available, but may not be at a location convenient to the Contractor. Extension cords and alike shall be provided by the Contractor.
7.4 Project Restrictions/Limitations
The work herein requires the Folsom Dam water elevation to be below 428 feet as shown on drawing 485-D-2327. Typically, the reservoir draws down below this elevation in late summer and this continues through the fall. Therefore, it is anticipated that the work could occur from August through December. Unusual early rains or lack thereof could affect the aforementioned work window.
8.0 APPLICABLE PUBLICATIONS/STANDARDS/CODES
• Aluminum Association (AA) o AA ADM-105-2005 - Aluminum Design Manual
• American Institute of Steel Construction (AISC) o AISC 360-10 – Specifications for Steel Structural Buildings
• American Concrete Institute (ACI) o ACI 355.4-11, Qualification of Post-Installed Adhesive Anchors in Concrete and Commentary o ACI 318-11, Building Code Requirements for Structural Concrete and
Commentary
• American National Standards Institute (ANSI) o ANSI A 14.3-2002 - Fixed Ladders - Safety Requirements
• American Society of Mechanical Engineers (ASME) o ASME B30.7 – Base Mounted Drum Hoists o ASME B18.2.1-1996(2005) - Square and Hex Bolts and Screws, Inch Series
• American Society of Civil Engineers (ASCE) o ASCE 7-10, Minimum Design Loads for Buildings and Other Structures
• American Welding Society, Inc. (AWS)
• ASTM International (ASTM) o For all material proposed to be used. List all ASTM designations on shop drawing approval submittal and as-built drawings. Submit manufacturer
Statement of Work - 8 specification sheets for each item proposed indicating it meets ASTM designation, as applicable.
• Bureau of Reclamation (USBR) o USBR M-47 Guide to Concrete Repair, 2015.
• Code of Federal Regulations (CFR) o 40 CFR, Part 112 Oil Pollution Prevention o 29 CFR 1910 – Occupational Safety and Health Standards
• Federal Specifications (FS) o FS RR-W-410F - Wire Rope and Strand o FS RR-S-550D(1) - Sockets, Wire Rope
• International Coder Council (ICC) o IBC-15, 2015 International Building Code
• National Association of Architectural Metal Mfrs. (NAAMM)
• Public Law o Sections 311, 402, and 404 Clean Water Act (Public Law 92-500, as amended)
9.0 TASKS
The various tasks and technical requirements are outlined above and include, but are not limited to the Scope and Deliverables sections of this SOW. The Contractor shall provide all labor, materials, equipment and permits necessary to complete the requirements outlined herein and in Reclamation approved submittals. The Contractor shall be responsible to field verify measurements and any data, reports or reference drawings provided by Reclamation in completing all submittals requirements and achieving the objectives of this project. The Contractor shall be responsible for any damage to Reclamation facilities/equipment, and will pay for damages at their expense.
The Contractor shall comply with all applicable Federal, State and Local laws and regulations. The ladder and platform designs shall meet the aforementioned applicable publications/standards/codes per structural applications designed and sealed by a California Professional Engineer.
10.0 CONTRACTOR PERFORMANCE ASSESSMENT
The COR will be the primary individual to monitor and/or assess the Contractor’s work, and will report any deficiencies to the CO as appropriate. The COR is responsible to ensure that all technical requirements of the contract and this SOW are met. As such, the COR may be asked to provide input to the CO regarding the Contractor’s performance during the course of the contract, and during the close-out phase in which the Contractor may receive a final evaluation of their work.
11.0 ATTACHMENTS
A. Safety Access Cage and Ladder System Metalwork Specifications.
Statement of Work - 9
B. Reference Drawings:
485-D-2318 – TCD Structural Steel Hoist Platform Details 485-D-2319 – Guardrail Miscellaneous Metalwork 485-D-2320 – Grating Miscellaneous Metalwork 485-D-2321 – TCD Structural Steel Guides 485-D-2323 – Ladders and Cages 485-D-2324 – Miscellaneous Platform Metalwork 485-D-2327 - TCD General Installation/Overview 485-D-2328 - Enclosure Structure – Installation and Details 485-D-2333 - Gates – Installation, Assembly and Operation 485-D-2334 – Lower Gate – Control Gate Details 485-D-2335 – Control Gate Details 485-D-2340 – Control Gate Hoist General Arrangement 40-D-7102 – Drawings Border, Sample Title Block, and Signature Lines
C. Existing Wire Rope Certificate, Spelter Socket and Turnbuckle Data.
D. Water Pollution Control and Spill Prevention Specifications.
E. Photos.
F. Submittal Requirements
END OF SECTION
Solicitation No. R16PS01169 Specifications No. 20-C0858
F-1
SECTION F - DELIVERIES OR PERFORMANCE
Clause Title Date
52.242-14 Suspension of Work APR 1984
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK
APR 1984
The Contractor shall be required to
(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than 120 calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION SEP 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,700 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
Amenment No. 0002
Specifications No. 20-C0858
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
Attachment Number List of Documents, Exhibits, and other Attachments
1 General Decision Number: CA160009 CA9 dated 07/08/2016
2 Subcontracting Percentages Worksheet
3 Offeror Responsibility Information
4 Section G - RAC 15-13 Invoicing Documents
5 Sign in Sheet and Agenda
6 Questions and Answers
Amendment 2: Clarifications, Questions and Answers Folsom Dam Municipal and Industrial Temperature Control Device Safety Measures
Solicitation No. R16PS01169
Questions and Answers
1. The project only allows for 90 calendar days after the notice to proceed for completion. We have concerns that this is inadequate for the following reasons:
a. The time required to get personnel screened through the security clearance vetting process consumes contract days. This will need to be done before we can access the site to survey it for the design of the new ladder and inspection of the existing conditions. How long does this really take?
A Reclamation Representative will escort the Contractor personnel to facilitate access to the site.
b. The time required to prepare engineered design for the new ladder and platform system, Government review and comment, potential revised engineered design, another Government review, material procurement, fabrication, galvanizing and installation.
We acknowledge the Contractor’s concern. The contract performance period is revised from 90 days to 120 days.
c. There may be a potentially long lead time to procure the cable. We are getting mixed responses on whether the cable is even available and no commitments from anyone at this point.
We acknowledge the Contractor’s concern and understand that a manufacturer may need to manufacture a special run for this project. The contract performance period is revised from 90 days to 120 days.
We agree with the Government that the 90 calendar days allowed is more than adequate for the actual, onsite construction but believe the time is inadequate for the preparatory work.
Will the Government provide additional contract days for the preparatory and off site work?
We acknowledge the Contractor’s concern. The contract performance period is revised from 90 days to 120 days.
2. Can the cable be from a foreign source because it may be difficult or impossible to procure domestically based on our preliminary outreach? We have not be able to get a commitment from any supplier at this point.
Domestic manufacturers have the capability and shall be utilized per Buy American Act requirements.
3. A right hand lay only cable is specified. Please confirm that you do not need a left hand lay cable on the opposite end of the drum.
Both wire ropes are Right Regular Lay (RRL). The lay of the wire ropes is shown in the above photographs.
4. The specifications state to replace all attachment hardware. Is this to include the attachment components to the drum that has not been exposed to the water and should be in good condition?
Yes.
5. Since there is no railing on the lower inspection platform, will a permanent hand rail, fall protection anchor point(s) or other devices need to be designed and installed?
Install railings on concrete landing (elevation 428’) as depicted on drawing 485-D-2327 and per Attachment A Specifications. Remove existing rusted rail as shown in Photograph 6 of Attachment E.
6. In the statement of work, paragraph 5.4B, Site Security, requires that one lane on the dam road be open at all times except as approved by the Government. A crane will be needed to facilitate construction on the project, the entire road will be needed for the crane set up. Will the Government commit prior to the bid for the road to be blocked by a crane for specified days and/or times?
The Government will allow the road to be blocked for specific activities and durations including but not limited to crane setup and operation as approved by the COR. The Contractor shall return one lane of Folsom Dam open at the end of each shift.
7. If determined necessary, will the Government be willing to relocate the existing gantry crane to allow more operational room for a crane?
The Government will accommodate relocating the existing Gantry Crane for specific activities and durations as approved by the COR.
8. Are there limitations to drilling and anchoring into the dam?
Drilling into the dam face shall not exceed 12”. Anchors into the concrete dam shall be epoxy type. Include anchor design details and installation methods as part of RSN A-1, Ladder and Platform Safety Approval Drawings and Data.
Clarifications
1. Period of Performance: The Period of Performance to include preparatory work, approval of submittals and all on-site work is revised from 90 days to 120 days. All on-site work shall be completed within 30 days. See the revised Statement of Work with changes in bold italics.
2. The additional captioned photographs below depict the M&IE TCD Hoist wire ropes attached to the drum.
Additional Photograph 1: The photograph depicts 1-5/8” wire ropes clamped to the drum at the TCD’s upmost position.
Additional Photograph 2: The photograph depicts the wire ropes with 5+ wraps remaining on the drum after the control gate is lowered to its lowest position.
Additional Photograph 3: The photograph depicts a counter readout of 334.5’ when the control gate is at the lowest elevation. At mobilization, the Government will operate the TCD hoist through its full range of operation. The contractor shall note and record the high and low digital and mechanical elevation readouts and match these readings as a result of replacing the wire ropes.