Sol_R16PS01133_Amd_000001_with_attachment.pdf

PDF 247 KB Posted

Attached to
OT-FORT COBB FIREBREAK CLRING&FNCING-WB
Solicitation number
R16PS01133
Issued by

About this file

The purpose of this amendment is to provide the following changes See attachment

View the file

Other files

File Type Posted
R16PS01133_Solicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

R16PS01133

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Billings MT 59101

R60

2021 4th Avenue North GP-5000 Acquisitions Great Plains Region Bureau of Reclamation

06/15/2016000001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/15/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is:

a. Provide a synopsis of the organized site visit that took place on June 23,2016.

b. Replace certain Specifications sections identified in the attachment. These changes are the result of questions submitted from the site visit.

c. Change Section J, Attachment Number 0001 to reflect clearing and fence erection will be by Common Laborer.

d. Last day to submit questions is July 11, 2016

e. See attachment for site visit questions with answers and specification changes incorporated in this amendment.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Paris Everson

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Fire Break Clearing and Fencing Fort Cobb Reservoir Washita Basin Project, Oklahoma R16PS01133 Amendment 0001.

Solicitation R16PS01133 Amendment 0001

Fire Break Clearing and Fencing Fort Cobb Reservoir, Washita Basin Project, Oklahoma

On June 23, 2016 a pre-bid site visit was held at Fort Cobb Reservoir, Oklahoma. Principle components of work include: (1) Surveying; (2) Demolition of existing fencing; (3) Mechanically clearing 20-foot wide firebreak; (4) Hand clearing 5-foot for fencing where mechanical clearing is not authorized; (5) Constructing new 5-strand barbed wire fence and gates; (6) Constructing steel corner posts and H-braces;

(7) Constructing steel post and cable fencing.

Below are the names of the contractors that attended the site visit: (Note: Company names are listed in no particular order.)

Timber Oklahoma BNJ Builders Finley Welding & Fencing L&J Construction Inc.

Washita Construction Beamer’s Cleaning

PWE

Bronze Oak Talon LPE Yankee Fencing Co.

Marlon Contracting T. McDonald Construction D H Dozer

At the conclusion of the site visit questions were submitted. Based on the questions the Government has amended the specifications (see changes). Questions with the corresponding answers are as follows:

Note: The following contractor questions were not captured verbatim, but are intended to capture the intent of the questions and discussions which occurred during the pre-bid site visit.

Will Reclamation provide landowner contact information for contractor to coordinate site access?

Reclamation will not provide landowner contact information as this is not required to complete the specified work. Section 01 14 12 – Work Restrictions, has been amended to reflect that all work performed under this contract is accessible via public roads or Federal lands.

Is work on weekends allowed?

Work hours are defined in Section 01 14 12 – Work Restrictions, as Monday through Friday, 7 am to 7

pm. The process for requesting additional work hours or work days is also outlined in this section.

Will there be any designated contractor staging areas?

Section 01 31 19 – Project Management and Coordination, has been amended to include provisions for a staging area.

PEverson Typewritten Text

Washita Basin Project, Oklahoma R16PS01133 Amendment 0001.

Will the Contractor need to coordinate with any overhead utilities?

Section 01 56 15 – Protection of Existing Utilities had been amended to include a note about the potential for overhead utilities to be present. The contractor is responsible for protection of overhead utilities.

Does the Government want all of the removed fencing t-posts regardless of their condition?

Section 01 56 20 – Demolition of Existing Fencing, has been amended to clarify Part 3.01-B to take reasonable care to prevent damage to existing fencing t-posts during removal and that all re-useable fencing t-posts shall remain the property of the United States.

Can the contractor coordinate with private land owners to move cattle instead of constructing temporary fencing?

Section 01 56 20 – Demolition of Existing Fencing, has been amended to clarify Part 3.02-A to provide temporary fence protection for adjacent lands as required to prevent livestock from straying from adjacent lands.

Which areas require survey work?

Survey requirements are defined in Section 01 71 20 – Surveying.

GPS survey work could be problematic under tree canopy.

Section 01 71 20 – Surveying, does not specify a survey method. Surveyor is responsible to provide accurate survey.

Will contractor be required to re-establish permanent land boundary benchmarks when they are missing or destroyed?

No. There are no requirements for this work included in Section 01 71 20 – Surveying.

Where do contractor’s costs for brush-hogging get captured?

Section 31 11 00 – Clearing, has been amended to include mowing or brush-hogging in Part 1.01-B-1 – Payment.

Do dead limbs piled in the clearing zone need to be removed?

Yes. This is covered under the definition of vegetation in Section 31 11 00 – Clearing, Part 1.02 – Definitions.

Will the park provide a biologist for conducting presence and absence surveys for nesting birds?

Section 31 11 00 – Clearing, Part 3.01-A has been amended to reflect that during the nesting season, the contractor’s biologist shall conduct the presence and absence surveys for nesting birds. Submittals and Qualifications for the biologist were also added to this section and to Section 01 33 00 – Submittals.

Requirements for a biological monitor were added to Part 1.01-B – Payment.

What are the vertical clearing requirements along the firebreaks?

Section 31 11 00 – Clearing, has been amended to clarify Part 3.01-C-1-d and Part 3.01-C-2-f to remove overhanging tree branches to a height of 10-feet by pruning.

What is the height requirement for brush-hogging?

Section 31 11 00 – Clearing, Part 3.01-C-1-h now includes a mowing or brush-hogging requirement of 6-inches or less.

Washita Basin Project, Oklahoma R16PS01133 Amendment 0001.

What happens if equipment creates ruts?

Section 31 11 00 – Clearing, Part 3.01-C-1-i has been amended to require that the cleared area finished surface shall be smooth and free of ruts and shall be suitable for future brush-hog maintenance by others.

Are there any trees located in the mechanical clearing areas which will not be removed?

Section 31 11 00 – Clearing, Part 3.01-C-1-j has been amended to require the contractor to coordinate and get approval from the COR prior to commencing mechanical clearing work. Preserve and protect trees designated by the COR.

Can mechanical methods be used for hand clearing requirements, and should the stumps be cut off flush with the ground?

Section 31 11 00 – Clearing, has been amended to include the following clarifying notes in Part 3.01-C-2:

-Hand clearing shall be performed using hand operated tools.

-Use of a chain saw is allowed.

-Cut off stumps flush with ground.

How stringent is the 4-inch maximum chip size requirement for disposal of vegetative material?

Section 31 11 00 – Clearing, has been amended to clarify Part 3.02-A-2 regarding the government’s intent for disposal of cleared material.

The contractors pointed out that we are requiring an “ironworker, structural” wage rate for the laborers who install barbed wire fence. This is an unreasonable requirement and should be classified as “common or general laborer”.

The Contracting Officer (CO) has changed the Department of Labor, Davis Bacon Wage Determination for General Decision Number: OK20150036; from Iron Worker, Structural to Laborer – Common or General. This applies to hand clearing and fence erection. It does not apply equipment operator or other labor categories.

CHANGES

Due to the questions submitted during the site visit, the government determined the following specifications are changed and replaced with the following sections attached in this amendment:

(Note: Changes will be reflected with a dark line on the left side of the sentence/paragraph/spec.)

Section 01 14 12 – Work Restrictions Section 01 31 19 – Project Management and Coordination Section 01 33 00 – Submittals Section 01 56 15 – Protection of Existing Utilities Section 01 56 20 – Demolition of Existing Fencing Section 31 11 00 – Clearing Section J – List of Documents, Exhibits and Other Attachments o Attachment Number 0001 Department of Labor General Decision Number : OK160036

The last day to submit questions to the Contract Officer is Monday, July 11, 2016 at 4:00 pm All other terms and conditions of this solicitation remain unchanged.

Bid Opening date and time remain unchanged as stated in the Standard Form 1442 block 13.

PEverson Typewritten Text

PEverson Typewritten Text

Document No.

R16PS01133 A0001

Document Title Fire Break Clearing and Fencing, Fort Cobb Reservoir, Ok

Work Restrictions

01 14 12 - 2

This page intentionally left blank.

Work Restrictions

01 14 12 - 1

SECTION 01 14 12

WORK RESTRICTIONS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 WORK RESTRICTIONS

A. Migratory Birds:

1. Nesting season: March 1 - August 31.

2. Work in accordance with Section 31 11 00 - Clearing.

B. Work hours:

1. Monday through Friday, 7 am to 7 pm.

2. Additional hours per COR approval. Request in writing and be approved 7 days in advance.

3. Additional days per COR approval. Request in writing and be approved 21 days in advance.

C. Allow public access to Fort Cobb State Park and Fort Cobb Wildlife Management Area (WMA) throughout construction.

1. Includes use of public roads and campground areas.

2. Maintain public use of roadways throughout park area and access to and from campgrounds during construction.

D. All work performed under this contract is accessible via public roads or Federal lands.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Clearing

31 11 00 - 4

Project Management and Coordination

01 31 19 - 1

SECTION 01 31 19

PROJECT MANAGEMENT AND COORDINATION

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in the price in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

1.03 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 31 19-1, Work Plan Summary.

1. Summary of upcoming work and traffic plans for next 60 days.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PROJECT COORDINATION

A. The following meetings are considered significant, but do not relieve Contractor from the responsibility of other meetings required outside this section.

B. Schedule Update Joint Review Meeting:

1. Meet weekly with COR to review work, progress made, difficulties in performing work, and resolution necessary to meet specifications requirements.

2. Meetings include review of construction program work and updating of progress reports.

Project Management and Coordination

01 31 19 - 2

C. Work Plan Summary:

1. Prepare written monthly summary of work plans. Provide summary to COR at least 7 days before the start of the month

D. After survey and clearing has been completed, Contractor shall stake locations for new fencing, H-Braces, Corner Braces, Gates, and Post and Cable Fencing in accordance with Section 32 31 30 – Barbed Wire Fencing, Steel Post and Cable Fencing, and Gates. Once staking is complete, Contractor shall contact COR a minimum of seven days prior to starting fence construction to schedule an on-site meeting to review all fence locations.

Contractor shall not construct new fencing prior to receiving written approval from COR.

3.02 STAGING AREAS

A. Reclamation will make available an un-secured location approximately 50-feet by 50-feet in size for staging of materials and equipment near the southwest end of Fort Cobb Dam.

B. Contractor may store materials and equipment within cleared firebreaks.

C. United States shall not be liable for damage to or theft of contractor materials or equipment.

Submittals

01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement units: US Customary Units

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Reserve 3- by 3-inch space next to title block for review stamps.

01 33 00 - 2

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Government Format drawings:

a. Prepare drawings designated as “Government Format” in the specifications as follows:

1) Title block and sheet format:

a) As shown on Drawing 40-D-7102.

b) Government will provide specific title block information to be used.

2) Drawing format:

a) AUTOCAD, Version 2007 or later.

b) In accordance with NIBS NCS.

3) Size: D-size (22-inch by 34-inch) as defined by ASME Y14.1.

4) Government will provide an electronic AutoCAD template.

6. Final drawings:

a. Drawing format: AUTOCAD, Version 2007 or later.

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

c. Electronic files: On CD or DVD discs.

d. Original plots: D size (22 inches by 34 inches).

e. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

01 33 00 - 3

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

F. Samples and Color Selection Submittals:

1. Label with complete manufacturer's product and color identification.

2. Include type and quantity of materials specified in the referenced section in each “set” of samples.

3. Samples: Representative of product to be installed. Xerographic sheets for color selection are not acceptable.

4. Color chips: Sample paint chips. Ink color reproductions are not acceptable.

5. Label each sample, sample kit, set of color chips, or color chart with contract number and title.

6. The Government will select architectural color and pattern after product approval.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for each attached submittal.

3. Responsible code.

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

01 33 00 - 4

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause. Adjustment will be subject to terms of the clause at FAR 52.242-17, Government Delay of Work.

01 33 00 - 5

C. Submittal response:

1. Response letter will indicate whether submittal is approved, approved subject to identified changes, or not approved.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of CO after drawings, documentation, and technical data have been approved.

1.07 TRANSMITTAL

A. Addresses for codes receiving paper copy submittals listed in Table 01 33 00A - List of Submittals:

1. CO: Bureau of Reclamation, Attention GP-5000, PO Box 36900, Billings MT 59107-6900. Physical address: 2021 4th Avenue North, Billings MT 59101.

2. COR: Bureau of Reclamation, Attention OK-McCrackin. Physical address:

5924 NW 2nd Street Suite 200, Oklahoma City, OK 73127-6514.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

01 33 00 - 6

Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, COR indicates Contracting Officer Representative.

RSN

Clause or

Section Title

Submittals required

Due date or delivery time

Respon-sible code

Sets to be sent to: **

CO COR

1 Performance and Payment Bonds - Construction 52.228-15

Performance and Payment Bonds

Within 10 calendar days after award

CO 1 paper 0

2 Insurance-Work on a Government Installation 1452.228-70

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing onsite work

CO 1 paper

1 paper

3 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1 paper 0

4 Equal Opportunity 52.222-26

Information required by Executive Order

112246 (SF-100)

Within 30 days following award

CO 1 paper 0

5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10

Certification that executive compensation and subcontract awards were reported

Within 10 days of each report being submitted

CO 1 paper 0

6 Release of Claims 1452.204-70

Release of Claims (DI-137) against the Government

After completion of the work and prior to final payment

CO 1 paper 0

7 Labor Standards Data 52.222-11

1) List of subcontractors

2) Statement and acknowledgement Form (SF-1413) for each subcontract

Within 14 days after award of contract

COR 1 paper

1 paper

9 Payrolls and Basic Records 52.222-08

Copies of all payrolls

Weekly for each week of contract performance

COR 1 paper 2 paper

10 Site Security

GP-7

List of contractor and subcontractor employees

At least 10 days prior to arriving at worksite

COR 0 2 paper

11 Site Security

GP-7

List of vehicles and equipment to be brought onsite

At least 10 days prior to arriving at worksite

COR 0 2 paper

01 33 00 - 7

RSN

Clause or

Section Title

Submittals required

Due date or delivery time

Respon-sible code

Sets to be sent to: **

CO COR

12 Schedules for Construction Contracts (52.236-15)

Practicable schedule:

Blackline prints

Submitted 14 days before commencing onsite work.

COR 1paper 1paper

01 31 19-1 Project Management and Coordination

Work Plan Summary 7 days prior to the start of each month

COR 0 1 paper

01 35 10-1 Safety Data Sheets

Complete LHM and

SDS

At least 14 days before jobsite delivery of hazardous material

COR 0 1 paper

01 35 10-2 Safety Data Sheets

Updated LHM and

SDS

At least 14 days before jobsite delivery of hazardous material not previously listed

COR 1 paper 1 paper

01 35 20-1 Safety and Health

Safety Program Submitted and accepted before commencing onsite work. See Section 3 of RSHS

COR 0 1 paper

01 35 20-2 Safety and Health

Monthly Accident Summary Report

Monthly COR 0 1 paper

01 35 30-1 Contractor’s Onsite Safety and Health Personnel

Resume At least 14 days prior to employment

COR 0 1 paper

01 35 30-2 Contractor’s Onsite Safety and Health Personnel

Safety Inspection Reports

At least once each week COR 0 1 paper

01 55-20-1 Traffic Control Traffic Control Plan

At least 14 days before affecting public traffic

COR 0 1 paper

01 56 10-1 Protection of Existing Installations

Plan for Protecting Existing Installations

At least 14 days Before starting onsite work

COR 0 1 paper

01 57 20-1 Environmental Controls

Fire Prevention Plan At least 14 days before start of onsite construction work

COR 0 1 paper

01 57 30-1 Water Pollution Control

Water Quality Managment Plan

At least 14 days before start of onsite construction work

COR 0 1 paper

01 57 30-2 Water Pollution Control

Stormwater Pollution Prevention Plan

At least 14 days before start of onsite construction work

COR 0 1 paper

01 57 30-3 Water Pollution Control

Spill Prevention Control and Countermeasure (SPCC) Plan

At least 14 days before delivery or storage of oil

COR 0 1 paper

01 33 00 - 8

RSN

Clause or

Section Title

Submittals required

Due date or delivery time

Respon-sible code

Sets to be sent to: **

CO COR

01 71 20-1 Surveying Surveying Plan At least 14 days before beginning survey work

COR 0 1 paper

01 71 20-2 Surveying Resume At least 14 days before beginning survey work;

At least 14 days before personnel change

COR 0 1 paper

31 11 00-1 Clearing and Grubbing

Qualifications Within 21 days after receipt of Notice to Proceed

COR 0 1 paper

32 31 30-1 Wire Fence Barbed Wire Product Literature

At least 14 days before commencing onsite construction work

COR 0 1 paper

32 31 30-2 Wire Fence T Post Product Literature

At least 14 days before commencing onsite construction work

COR 0 1 paper

32 31 30-3 Wire Fence 2 3/8 inch J55/N80 Pipe Product Literature

At least 14 days before commencing onsite construction work

COR 0 1 paper

32 31 30-4 Wire Fence 4 inch J55/N80 Pipe Product Literature

At least 14 days before commencing onsite construction work

COR 0 1 paper

32 31 30-5 Wire Fence Manufacturer’s Specification for Gate

At least 14 days before commencing onsite construction work

COR 0 1 paper

Protection of Existing Utilities

01 56 15 - 1

SECTION 01 56 15

PROTECTION OF EXISTING UTILITIES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the schedule for other items of work.

1.02 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS Reclamation Safety and Health Standards.

Available on the Internet at:

http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

1.03 PROJECT CONDITIONS

A. Drawings included in these specifications do not show existing utilities.

B. Obtain location of buried conduit, pipe, cable, ground mat, and other buried items before excavating.

C. Overhead utilities are present in some locations of this project. Contractor is responsible for protection of overhead utilities.

D. Contact “Call Okie” for utility locates via telephone:

1. OKIE 811.

2. 800-522-6543.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 INTERFERENCE WITH OPERATION OR MAINTENANCE

A. Do not interfere with operation or maintenance service on utilities, existing on date offers are received.

Protection of Existing Utilities

01 56 15 - 2

1. Provide for access to utilities in a manner satisfactory to owners and operators and the Government.

B. Provide required temporary structures; make necessary repairs, replacements, or similar operations; and furnish indemnity or other bonds.

Demolition of Existing Fences

01 56 20 - 1

SECTION 01 56 20

DEMOLITION OF EXISTING FENCING

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Measurement: Linear feet of barbed wire fence and post and cable fence removed.

1. Includes all associated installations such as H-braces, corner posts, fence stays, and all other ancillary materials.

B. Payment: Linear foot price offered in the price schedule.

PART 2 PRODUCTS

2.01 Not Used

PART 3 EXECUTION

3.01 FENCE REMOVAL

A. Remove existing fences on government property where new fence is to be constructed as shown on drawings.

1. When removing fence along county roads, ensure that fence location is marked and preserved such that new fencing can be constructed in the same location.

2. When removing fence where Reclamation property abuts private property, the property boundary shall be surveyed prior to removal of the fencing. Do not remove any fencing located on private property.

B. Contractor shall take reasonable care to prevent damage to existing fencing t-posts during removal. All re-useable fencing t-posts shall remain the property of the United States and shall be delivered to a location within the Fort Cobb Project boundary as designated by the COR.

C. All other removed fencing materials shall become the property of the Contractor and shall be removed from Federal property and disposed of in accordance with applicable state and local statutes.

3.02 TEMPORARY FENCES

A. Where fences are removed along the Federal property boundary, provide temporary fence protection for adjacent lands as required to prevent livestock from straying from adjacent lands.

Demolition of Existing Fences

01 56 20 - 2

B. Remove temporary fences and protection as a part of cleanup operations prior to final acceptance of completed work.

31 11 00 - 1

SECTION 31 11 00

CLEARING

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Measurement:

1. Mechanical Clearing: Linear feet of 20-foot wide mechanical clearing.

2. Hand Clearing: Linear feet of 5-foot wide hand clearing.

B. Payment:

1. Mechanical Clearing: Price per linear foot offered in Price Schedule. Includes:

a. Biological Monitor, if required.

b. Mowing or Brush-hogging.

2. Hand Clearing: Price per linear foot offered in the Price Schedule. Includes:

a. Biological Monitor, if required.

1.02 DEFINITIONS

A. Vegetation: Trees, shrubs, brush, stumps, exposed roots, down timber, branches, grass, and weeds.

1.03 SUBMITTALS

A. If clearing during nesting season, as defined in Section 01 57 60 - Protected Species, submit in accordance with the requirements of Section 01 33 00 - Submittals.

1. RSN 31 11 00-1, Qualifications.

a. Resume.

b. Official transcripts.

1.04 QUALIFICATIONS

A. Biologist:

1. Bachelor’s Degree from an accredited U.S. university in:

a. Biology or,

b. Wildlife Biology, terrestrial.

2. Experience: 2 years’ experience in performing presence and absence surveys.

31 11 00 - 2

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 CLEARING

A. During nesting season as defined in Section 01 57 60 - Protected Species.

1. Contractor’s biologist shall conduct presence and absence surveys for nesting birds 3 to 5 days prior to clearing.

a. Perform work in accordance with Section 01 57 60 - Protected Species.

b. Notify COR immediately when migratory nesting birds are identified.

B. Survey Federal property boundaries before clearing. Stay within Federal property boundaries when clearing.

C. Clear rights-of-way for Fire Break and Fencing as shown on the drawings:

1. Mechanical Clearing:

a. Width of clearing shall be 20-feet to establish a Fire Break.

b. When clearing along county roads, clearing shall begin 2-feet in front of the existing fence line (i.e., road side of fence), and extend 20-feet into Reclamation property (18-feet behind existing fence line) unless otherwise shown on drawings.

c. When clearing along areas where Reclamation property abuts private property, clearing shall begin at property line and extend 20-feet into Reclamation property.

d. Remove tree branches overhanging the 20-foot firebreak to a height of 10-feet by pruning branches back to the nearest branch crotch outside of the 20-foot firebreak.

e. Clearing shall not be performed using equipment which will up-root trees.

f. Use of a drum chopper is allowed.

g. Cut off or grind stumps a minimum of 3-inches below the ground surface to minimize regrowth.

h. Cleared area shall be mowed or brush-hogged to a height of 6-inches or less prior to constructing fence.

i. Cleared area finished surface shall be smooth and free of ruts and shall be suitable for future brush-hog maintenance by others.

31 11 00 - 3

j. Mechanical clearing shall be coordinated with and approved by the COR prior to commencing work. Preserve and protect trees designated by the

COR.

2. Hand Clearing:

a. Hand clearing shall be performed at locations designated on drawings to minimize disturbance to existing vegetation and prevent erosion.

b. Hand clearing shall be performed using hand operated tools.

c. Use of a chain saw is allowed.

d. Width of hand clearing shall be a maximum of 5-feet with a minimum of 2-feet on each side of the fence to be constructed.

e. Cut off stumps flush with ground.

f. Remove tree branches overhanging the 5-foot clear zone to a height of 10-feet by pruning branches back to the nearest branch crotch outside of the 5-foot clear zone.

g. Hand clearing shall be coordinated with and approved by the COR prior to commencing work. Preserve and protect trees designated by the COR.

3.02 DISPOSAL OF CLEARED MATERIAL

A. Dispose of vegetative material:

1. Remove from Federal property and dispose of in accordance with applicable state and local statutes, and/or

2. Shred trees into mulch with individual pieces having a maximum 24-inch longest dimension and a maximum 2-inch shortest dimension. Use shredded mulch material on cleared areas to prevent erosion by spreading mulch uniformly to restore disturbed areas as determined by COR, and/or

3. Tree trunks larger than 24 inches diameter at breast height (DBH) can be cut into eight foot sections and scattered a minimum of 25 feet from the edge of the firebreak clearing on Federal property.

31 11 00 - 5