Sol_R15PS00916_Amd_000001.pdf
PDF 1 MB Posted
- Attached to
- Geologic Investigations
- Solicitation number
- R15PS00916
About this file
R15PS00916
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_R15PS00916_Amd_000002.pdf | ||
| Sol_R15PS00916.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
R15PS00916
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Yakima WA 98901
R1C
1917 Marsh Roard Columbia-Cascades Area Office Pacific Northwest Region Bureau of Reclamation
Boise ID 83706-1234 1150 N. Curtis Road, Ste. 100
R10
Acquisition Management Division Regional Office Pacific Northwest Region Bureau of Reclamation
04/30/2015000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
04/30/2015
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to:
1. Extend the quote due date. The due date is changed from 5/15/2015 (1700 PT) to 6/12/2015
(1700 PT).
2. Revise the Statement of Work.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Paula D. Collins
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
5/15/15 6:15 PM
Performance Work Statement Borehole Geophysical Logging, Keechelus-to-Kachess Conveyance, WA
Seismology, Geomorphology, & Geophysics Group 85-833000 14 May 2015
1.0 INTRODUCTION:
1.1 Bureau of Reclamation (Reclamation): Reclamation is a water management agency within the U.S. Department of Interior with 600 dams in the 17 western states. Reclamation is the largest wholesaler of water in the country and second largest producer of hydroelectric power in the western US.
1.2 Reclamation Technical Service Center - Geophysics Group 85-833000 has a requirement for borehole geophysical logging in two boreholes along the proposed Keechelus-to-Kachess Conveyance tunnel, WA. See figure 1 for borehole locations. The general site vicinity is located approximately 30 miles west of Cle Elum, WA via I-90.
1.3 Contractor shall complete borehole geophysical logging in two boreholes as detailed below, consisting of a.) suspension or full-wave sonic logging, b.) optical televiewer, c.) acoustic televiewer, and d.) three component borehole dilatometer testing using SolExperts or 100% equivalent testing methods.
1.4 Previous solicitation R15PS00916 is modified here to reflect recent changes in scope of work for this requirement.
1.5 The engineering objective of this requirement is to obtain information along the proposed tunnel alignment regarding rock quality, including but not limited to:
areas of weak or potentially unstable rock;
fracture spacing, orientation, and aperture;
fracture openness, infilling, weathering, alteration, or cementation;
presence and locations of shear zones or faults;
other information that may aid in predicting ground behavior related to proposed tunnel excavation and support.
2.0 SCOPE:
2.1 The Contractor shall conduct the following borehole geophysical logs and testing as detailed in table 1 below. Receiving party shall be COR (see sec. 14 below).
Table 1 – Borehole geophysical & testing requirements Borehole Number Borehole diameter, nominal (in/mm) Logging Interval (feet below ground surface), planned
Log Types
A1-14-3 3.77 / 95.8 575-675 S, OT, AT, 3CD
A1-14-4 3.77 / 95.8 575-675 S, OT, AT, 3CD
Key to log types S – Suspension or Full-wave sonics OT – Optical televiewer AT – Acoustic televiewer 3CD – 3-component dilatometer – SolExperts or 100% equivalent
2.2 The boreholes listed above are planned to be drilled by Reclamation. The boreholes are planned to be fully cased, with logging conducted in nominal ten to twenty foot logging runs as the casing is pulled back. Casing will be pulled with a Reclamation drill rig.
For Suspension or Full-wave sonic logging, and for acoustic televiewers, the boreholes are planned to be water-filled as conditions allow.
For each borehole, five dilatometer test locations are anticipated, at depths to be determined on-site by Reclamation Geology staff.
Reclamation personnel will be on-site to assist with borehole water-filling and casing pulls.
2.3 Data Analysis .
In addition to the general requirements outlined in 1.5 and 2.1 above, requirements for specific log types are listed below in Table 2.
Table 2 – Data Analysis Requirements Log Type Data Analysis Requirements Display requirements Suspension or Full-wave Sonics
P-wave velocity S-wave velocity (where obtainable)
Log traces in WellCAD ver 4 or v.5 format;
Velocity logs Vp/Vs ratio log
Optical Televiewer Fracture location, orientation, aperture estimate, infilling, shearing or other condition.
Lower hemisphere pole plot.
Interpreted and uninterpreted log image panel displays in WellCAD v.4 or v.5 format.
Acoustic Televiewer (water-filled log intervals only)
Fracture location, orientation, aperture estimate, infilling, shearing or other condition.
Lower hemisphere pole plot.
Interpreted and uninterpreted log image panel displays in WellCAD v.4 or v.5 format.
3-Component Dilatometer Stress/strain analysis Strain ellipsoid display pressure / deformation curves in SolExperts Dilato-2 format.
2.4 Safety Plan
Contractor to submit safety plan adhering to Reclamation Safety and Health Standards
(http://www.usbr.gov/ssle/safety/RSHS/rshs.html) and relevant to working in conjunction with on-site drilling equipment, to Reclamation COR prior to start of work.
http://www.usbr.gov/ssle/safety/RSHS/rshs.html
Figure 1 -- Potential Keechelus to Kachess Conveyance, General Location
3.0 PERSONNEL QUALIFICATIONS:
The Contractor shall be able to document, upon request, experience with two or more similar projects within the last two years, which include experience in acquiring and interpreting all of the log types listed in tables 1-2 .
4.0 GOVERNMENT FURNISHED EQUIPMENT & MATERIALS:
4.1 Boreholes. See Table 1 and figure 1 for locations and logging intervals.
4.2 Water to fill boreholes. Note that some boreholes may not be able to be completely filled in high water-take conditions, though the logging interval is anticipated to be deep enough to be water-filled.
5.0 REGULATIONS / POLICIES:
Current active Reclamation contracting policy. Current valid proof of insurance per sec. 10.0.
6.0 TRAVEL:
6.1 Two round trips are anticipated for mobilization/demobilization and on site work.
Each round trip from the Contractor’s site to the work site is anticipated to take one day with no overnight travel.
6.2 On site work: Eight [8] days total on-site are planned to complete logging at the two boreholes. Nine [9] nights of overnight travel are planned for the on-site work.
7.0 GOVERNMENT VEHICLES:
No Government-owned vehicle use is required or approved. Reclamation shall supply drill rig and water truck equipment.
8.0 SECURITY:
Contractor shall comply with current Reclamation Safety, Security, & Law Enforcement guidelines.
9.0 TRAINING:
Contractor shall have adequate experience with the required testing methods, therefore no training is anticipated.
10.0 INSURANCE:
Contractor shall hold minimum current valid insurance to cover any damage to property or equipment.
11.0 DELIVERABLES:
11.1 Contractor shall perform borehole geophysical logging as detailed in sec. 2 and tables 1-2 above. Receiving party shall be COR, (see below). Contractor shall transport all necessary equipment and supplies (excepting drill rig and water truck, which shall be supplied).
Reclamation on site personnel shall be available to operate Reclamation drill equipment to pull casings and provide borehole water.
11.2 Data analysis. Contractor shall perform data analysis and presentation as detailed in sec 2.3 and table 2.
11.3 Report. Contractor shall perform work as required in sec. 11.1-11.2 above, and submit a draft report detailing data acquisition and interpretation procedures for the log types listed in tables 1-2. See sec. 15 for schedules. Reclamation shall review contractor’s draft, supply return comments, and contractor shall submit final report addressing Reclamation comments.
12.0 PERFORMANCE REQUIREMENTS SUMMARY:
The Contractor service requirements are summarized into performance objectives listed in Table 2 below. The performance goal briefly describes the minimum acceptable levels of service for this requirement.
Table 2 -- Performance Requirements
SEC. PERFORMANCE
OBJECTIVE
PERFORMANCE GOAL METHOD OF
SURVEILLANCE
1.3, 10.0 Submit copies of previous experience, and insurance coverages with bid.
Compliance of Contractor Review by CS, CO, TLGP.
2.4 Submit safety plan with bid. Compliance of Contractor Review by CS, COR.
2.0 Deliver supplies and storage
magazines.
Within 90 days of contract award, notifying Contracting Officer’s Representative (COR) 7 days in advance for on site inspection.
Inspection by COR.
2.2, 3.0, 8.0, 9.0, 11.0, 15.0
Adherence to BOR requested procedures. Adherence to BATFE and WA-state permit requirements.
Compliance of Contractor Review by COR.
2.0 Pickup of unused supplies and
storage magazines.
At survey completion. Inspection by COR.
13.0 Identification of Contractor Employees: All contract personnel are required to identify themselves as contractors. Whether attending meetings, or working in other situations where their contractor status is not obvious to third parties, they must make their status known to avoid creating an impression that they are Government employees.
14.0 POINTS OF CONTACT:
Contracting Officer (CO) Paula Collins
POB 25007, MS-84-27810
Denver, CO 80225 509-575-5848 x____ pcollins@usbr.gov
Contract Specialist (CS) Marisol Bastiani
POB 25007, MS-84-27810
Denver, CO 80225 509-575-5848 x267 mbastiani@usbr.gov
CO’s Representative (COR) Mike Gilliam
POB 25007, MS 85-833000
Denver, CO 80225 303-445-3806 mgilliam@usbr.gov
CO’s Repr [alternate] (COR) John Earle
POB 25007, MS 85-832000
Denver, CO 80225 303-445-3152 jearle@usbr.gov
Technical Lead Geophysics
(TLGP)
Rich Markiewicz
POB 25007, MS 85-833000
Denver, CO 80225 303-445-3167 rmarkiewicz@usbr.gov
Technical Lead Geology
(TLG)
Bryan Simpson
POB 25007, MS 85-832000
Denver, CO 80225 303-445-3094 bksimpson@usbr.gov
15.0 Performance Period / Schedules
Contractor shall coordinate with COR after contract award and conduct borehole geophysical logging services in conjunction with COR, TLG, & TLGP.
Anticipated schedule, subject to change upon notification to contractor in writing by Reclamation.
Table __ - Milestones and Schedule Milestone Planned date of completion Remarks Boreholes completed and ready for logging
3-Aug-2015 Coordinate with TLG, COR for exact dates.
Televiewer logging completed
6-Aug-2015
Dilatometer testing completed
11-Aug-2015
Draft report submitted by Contractor
11-Sep-2015 One electronic and one hardcopy
Comments supplied by Reclamation
18-Sep-2015 One electronic copy.
Final report submitted by Contractor
2-Oct-2015 One electronic and four hardcopies.
The on-site work is anticipated to take about 8 days. Weather conditions, National Forest fire-danger restrictions, Labor Day or other holiday delays, or other adverse conditions may affect this schedule. Normal work schedule is Mon-Sat 7:30a-5:30p.