Solicitation and Bid Package
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| R15PS00762_Amendment_0003.pdf | ||
| R15PS00762_Amendment_0003.pdf | ||
| R15PS00762_Amendment_0002.pdf | ||
| Sol_R15PS00762_Amd_000001.pdf | ||
| SECTION_B.pdf | ||
| Summary_of_Work_Section_01_11_00.pdf | ||
| Sol_R15PS00762.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Invitation for Bid
Solicitation No. R15PS00762
Middle Point Road Construction – Minimum Basic Access RAX Activity No. 1501
BELLE FOURCHE RESERVOIR
BELLE FOURCHE UNIT, SOUTH DAKOTA
U.S. Department of the Interior Bureau of Reclamation JUNE 2015
THIS PAGE INTENTIONALLY LEFT BLANK
Middle Point Road Construction
Belle Fourche Reservoir, South Dakota Solicitation R15PS00762
FOREWARD
MIDDLE POINT ROAD CONSTRUCTION
MINIMUM BASIC ACCESS
BELLE FOURCHE UNIT – SOUTH DAKOTA
FOREWORD
The work consists of gravel road construction for recreational access at the Belle Fourche Reservoir over or in proximity to an existing two-track road. This is a new road construction utilizing some of an existing two-track alignment. Work shall include construction of Middle Point Road, obliteration of undesignated two-tracks on Middle Point peninsula, and the construction of a parking area for Tequila Beach.
The work under this solicitation is located at Belle Fourche Reservoir and is approximately 8 miles east of the City of Belle Fourche in Butte County, South Dakota.
TELEPHONE INQUIRIES REGARDING THIS SOLICITATION SHOULD BE MADE TO:
Contractual Matters: Contracts Specialist Attention: Michael Birkland Billings, Montana Telephone: (406) 247-7646
FOR DATE AND PLACE OF BID OPENING, SEE "SOLICITATION, OFFER, AND
AWARD," STANDARD FORM 1442.
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS" (2009 EDITION) WHICH IS
APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT "WBR
1452.223-81 SAFETY AND HEALTH."
YOUR ATTENTION IS DIRECTED TO PART IV, SECITONL, INSTRUCTIONS,
CONSDITIONS AND NOTICES TO BIDDERS WHICH IN PART PROVIDES THAT
“ORAL EXPLANATIONS OR INSTRUCTIONS GIVEN BEFORE THE AWARD OF
THE CONTRACT WILL NOT BE BINDING.”
PRE-BID SITE VISIT: AN ORGANIZED SITE VISIT WILL BE HELD ON WEDNESDAY
JUNE 24, 2015 AT 10:00 AM. PROSPECTIVE BIDDERS ANTICIPATING TO ATTEND
THE WALK-THRU SHALL MEET AT THE INLET CANAL’S JEREMIASON FISHING
ACCESS PARKING OFF OF FISHERMAN’S ROAD LOCATED ON THE WEST SIDE OF
FOREWARD
BELLE FOURCHE RESERVOIR. PROSPECTIVE BIDDERS ARE STRONGLY
ENCOURAGED TO ATTEND THE PRE-BID MEETING AND VISIT THE SITE TO GAIN
FIRST-HAND KNOWLEDGE OF THE WORK REQUIREMENTS AND SITE
CONDITIONS. FAILURE OF THE PROSPECTIVE BIDDER TO INSPECT THE SITE
WILL NOT RELIEVE THE BIDDER FROM THE RESPONSIBILITY TO PROPERLY
ESTIMATE THE DIFFICULTY OR COST OF SUCCESSFULLY PERFORMING THE
WORK IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT.
CONTRACTORS INTERESTED IN THE PRE-BID SITE VISIT SHALL MAKE
ARRANGEMENTS BY CONTACTING GEORGE FINNEGAN OF THE RAPID CITY
FIELD OFFICE AT (605) 394-9757, Ext. 3002.
SAM: EFFECTIVE JULY 29, 2012, ANY CONTRACTOR INTERESTED IN DOING
BUSINESS WITH THE FEDERAL GOVERNMENT MUST REGISTER IN THE
SYSTEM FOR AWARD MANAGEMENT (SAM) DATABASE PRIOR TO AWARD OF
A CONTRACT OR AGREEMENT. SAM IS A FEDERAL GOVERNMENT OWNED
AND OPERATED FREE WEBSITE THAT CONSOLIDATES THE CENTRAL
CONTRACTOR REGISTRATION (CCR), THE ONLINE REPRESENTATIONS AND
CERTIFICATIONS APPLICATION (ORCA), AND THE EXCLUDED PARTIES LIST
SYSTEM (EPLS).
THE VENDOR'S DUNS & BRADSTREET NUMBER AND BANKING INFORMATION
ARE REQUIRED FOR REGISTRATION. CONTRACTORS MAY OBTAIN
INFORMATION ON REGISTRATION AND ANNUAL CONFIRMATION
EQUIREMENTS VIA THE SAM WEBSITE ACCESSED THROUGH
HTTPS://WWW.SAM.GOV/PORTAL/PUBLIC/SAM/ OR BY CONTACTING THE
FEDERAL SERVICE DESK AT 1-866-606-8220.
PAYMENT REQUEST FOR THE ANTICIPATED CONTRACT MUST BE
SUBMITTED ELECTRONICALLLY THROUGH THE U.S. DEPARTMENT OF THE
TREASURY’S INTENET PAYMENT PLATFORM (IPP) SYSTEM. THE IPP WEBSITE
IS HTTPS://WWW.IPP.GOV. THE CONTRACTOR MUST USE THE IPP WEBSITE
TO REGISTER ACCESS AND USE IPP FOR SUBMITTING REQUEST FOR
PAYMENT. CONTRACTOR ASSISTANCE WITH ENROLLEMENT CAN BE
OBTAINED BY CONTACTING THE IPP PRODUCTION HELPDESK VIA E-MAIL
IPPGROUP@BOS.FRB.ORG OR PHONE (866) 973-3131. IF THE CONTRACTOR IS
UNABLE TO COMPLY WITH THE REQUIREMENT TO USE IPP FOR SUBMITTING
INVOICES FOR PAYMENT, THE CONTRACTOR MUST SUBMIT A WAIVER
REQUEST IN WRITING TO THE CONTRACTING OFFICER WITH ITS PROPOSAL
OR BID.
https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
Table of Contents - 1
TABLE OF CONTENTS
PART 1 – THE SCHEDULE
SECTION A – Solicitation, Offer, and Award Form (SF 1442)
SECTION B – Supplies or Services and Prices
SECTION C – Specification/Drawings/Maps
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 33 00 Submittals 01 35 10 Material Safety Data Sheets 01 35 20 Safety and Health 01 55 20 Traffic Control 01 57 30 Water Pollution Control 01 71 20 Surveying 01 74 10 Cleaning
DIVISION 31 - EARTHWORK
31 02 10 Water for Dust Abatement 31 14 10 Topsoil Stripping 31 14 20 Road Obliteration 31 23 02 Compacting Earth Materials 31 23 40 Roadway Embankments 31 23 41 Parking Surfaces 31 23 90 Disposal of Excavated Materials 31 27 32 Gravel Materials 32 92 20 Seeding and Soil Supplements 33 42 30 Corrugated Metal Pipe Culverts
APPENDIX A
Belle Fourche Reservoir Road Maintenance Map Belle Fourche Reservoir: Middle Point Road Plan, Profile and Details
SECTION D – Not Used
SECTION E – Inspection and Acceptance E.1 Material and Workmanship E.2 Inspection of Construction E.3 Warranty of Construction
SECTION F – Deliveries or Performance F.1 Commencement, Prosecution, and Completion of Work F.2 Suspension of Work
Table of Contents - 2
F.3 Variation in Quantity
SECTION G – Contract Administration Data G.1 Authorities and Delegations
G.2 Electronic Invoicing and Payment Requirements G.3 Contractor’s Administration Personnel G.4 Post Award Conference
SECTION H – Special Contract Requirements
H.1 Site Security H.2 Non-Discrimination Notice to U.S. Department of the Interior Contractors, Subcontractors, and Lessors
PART II – CONTRACT CLAUSES
SECTION I – Contract Clauses I.1 Clauses By Reference I.2 Commercial and Government Entity Code Maintenance
I.3 Incorporation by Reference of Representations and Certifications I.4 Order of Precedence –Sealed Bidding I.5 Minimum Wages Under Executive Order 13658 I.6 Estimate of Percentage of Recovered Material Content I.7 Buy American Act – Construction Materials I.8 Bid Guarantee I.9 Additional Bond Security I.10 Performance and Payment Bonds - Construction I.11 Payments Under Fixed-Price Construction Contracts I.12 Prompt Payment for Construction Contracts I.13 Schedules for Construction Contracts I.14 Specifications and Drawings for Construction I.15 Changes I.16 Authorized Deviations in Clauses I.17 Restriction on Endorsements I.18 Release of Claims I.19 Liability Insurance I.20 Safety and Health I.21 Protecting Federal Employees and the Public from Exposure to Tabacco Smoke in the Federal Workplace I.22 Certification of Representatives for Corporate Sureties I.23 Equipment Ownership and Operating Expense I.24 Payment for Mobilization and Preparatory Work I.25 Claims Accounting I.26 Other Contracts I.27 Preservation of Cultural Resources I.28 Security Requirements
Table of Contents - 3
I.29 Modification Proposals
PART III – DOCUMENTS, EXHIBITS, AND OTHER
SECTION J – List of Documents, Exhibits, and Other Attachments
1- Wage Determination 2- Standard Form 24 – Bid Bond
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – Representations, Certifications and Other Statements of Offerors K.1 Annual Representations and Certifications K.2 Commercial and Government Entity Code Reporting
SECTION L – Instructions, Conditions and Notices to Bidders L.1 System for Award Management L.2 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR PART 101-29 L.3 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition
Streamlining and Standardization Information system (ASSIST) L.4 Amendments to Invitations for Bids L.5 False Statements in Bids L.6 Submission of Bids L.7 Explanation to Prospective Bidders L.8 Late Submissions, Modifications, and Withdrawals of Bids L.9 Preparation of Bids-Construction L.10 Submission of Offers in the English Language
L.11 Submission of Offers in U.S. Currency L.12 Type of Contract L.13 Construction Wage Rate Requirements-Secondary Site of the Work L.14 Notice of Requirement for affirmative Action to Ensure Equal Employment Opportunity for Construction L.15 Notice of Buy American Requirement – Construction Materials L.16 Service of Protest L.17 Site Visit L.18 Authorized Deviations in Provisions L.19 Notice of Intent to Acquire Metric Products and Services L.20 Notice of Proposed Partnering L.21 Instruction for Mobilization and Preparatory Work Schedule Line item L.22 Authorized Workers Notice to Potential
SECTION M – Evaluation Factors for Award M.1 Contract Award M.1 Notice of World Trade Organization Government Procurement Agreement Evaluations
PART I – THE SCHEDULE
THIS PAGE INTENTIONALY LEFT BLANK
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040190605
Bureau of Reclamation Bureau of Reclamation Great Plains Region 2021 4th Ave North Regional Office Billings MT 59102 PO Box 36900
R60
Billings MT 59107
Michael Birkland (406)247-7646 x
06/19/2015
R15PS00762
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Project Title: Middle Point Road Construction, Belle Fourche Reservoir, South Dakota
Location of Work: Bureau of Reclamation's Belle Fourche Reservoir, South Dakota
Magnitude of Project: $500,000.00 to $1,000,000.00 This is 100% Set-Aside for small business. The North American Industry Classification system (NAICS) code is 237310. The Small Business Size Standard for
NAICS 237310 is $33.5M. Electronic submission of bids will not be allowed. Mailed and hand carried bids will be received at the office of the Bureau of Reclamation, Great Plains Regional Office, Attention Gerri Voto-Braun GP5000, 2021 4th Ave
North, Room 507, 5th Floor, Billings Montana 59101. Contractors shall allow time to pass through security.
TAX PAYER IDENTIFICATION NUMBER (TIN): _____________________________
DATA UNIVERSAL NUMBER SYSTEM (DUNS): _____________________________
COMMERCIAL AND GOVERNMENT ENTITY (CAGE): _____________________________
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 180 calendar days and complete it within ________________ ________________ calendar days after receiving
Paragraph F.1
07/21/2015
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Gerri Voto-Braun
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R15PS00762
00010 BELLE FOURCHE RESERVOIR MIDDLE POINT ROAD 1 AU $ _____________
CONSTRUCTION
Price Schedule A CLINS 1 Through 7
Price Schedule B CLINS 8 Through 9
Price Scheudle C CLINS 10 Through 11
(See the following continuation Pages)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Schedule B-1
CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES
MIDDLE POINT ROAD CONSTRUCTION
MINIMUM BASIC ACCESS
BELLE FOURCHE UNIT – SOUTH DAKOTA
B.1 BID SCHEDULE
(a) Offers will be considered for award on the following schedules, but no offer will be considered for award on only a part of a schedule.
(b) Contract award will be made on Schedule A, however, options from schedule B and C may be awarded at the option of the Government, based on available funding at time of award and the awardee notified.
(c) All offers are subject to the terms and conditions of this solicitation.
(d) The quantities in the schedule are estimated quantities for comparison of offers only and except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
(e) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for Contract Line Item Number (CLIN) 1.
SCHEDULE A – Middle Point Road Construction CLIN* Section Work or Materials Quantity and
Unit Unit Price
Amount
1) WBR
1452.23
2-81
Mobilization and Preparatory Work
For the lump sum of $
2) 31 23 40 Middle Point Roadway Embankment
1.6 Mile $ $
3) 31 27 32 Pit Run Material for Soft Spot Repair
6,000 Tons $ $
4) 33 42 30 Corrugated Metal Pipe (CMP) Culverts
300 LF $ $
5) 31 27 32 Limestone Gravel Surfacing on Middle Point Road
9,000 Tons $ $
6) 01 55 20 Road Signs 4 signs $ $
Schedule B-2
CLIN* Section Work or Materials Quantity and Unit
Unit Price
Amount
7) 32 92 20 Seed Middle Point Road Shoulders and Borrow Ditches.
5 acres $ $
*CLIN – Contract Line Item Number
TOTAL FOR SCHEDULE A $_________________
OPTION SCHEDULE B – Two-Track Obliteration
Unit Unit Price
Amount
8) 31 14 20 Obliterate Undesignated Two-Track Roads.
1 Mile $ $
9) 32 92 20 Seed Obliterated Road Areas.
3 acres $ $
TOTAL FOR SCHEDULE B $_________________
OPTION SCHEDULE C – Tequila Beach Parking Area Construction
Unit Unit Price
Amount
10) 31 23 41 Shape and Blade Tequila Beach Parking Area and Trails
1 Acre $ $
11) 31 27 32 Limestone Gravel Surfacing on Tequila Beach Parking Area
1,000 Tons $ $
TOTAL FOR SCHEDULE C $_________________
END OF SECTION
Belle Fourche Reservoir, South Dakota Solicitation No. R15PS00762
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. The work under this solicitation is located at Belle Fourche Reservoir and is approximately 8 miles east of the City of Belle Fourche in Butte County, South Dakota.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Middle Point Road Construction
1. Middle Point Roadway Embankment: Strip and salvage topsoil from the subgrade. Water, scarify and compact the subgrade. Cut, fill, shape, blade and compact Middle Point Road prism and ditches to the parameters shown in the drawings. Scarification shall remove all soft areas to depth as necessary and compacted to the road dimensions shown in the drawings. Topsoil salvaged shall be replaced on road shoulders and ditches. Prepare suitable seed bed on road shoulders and ditches.
2. Corrugated Metal Pipe Culverts: Install culverts. Earth shall be excavated and culverts installed at locations shown in the drawings. Earth excavated shall be stored for backfill if suitable. Culverts shall be bedded with gravel material as described in the drawing. Culverts shall receive backfill earth cover. Earth cover shall receive compaction and shaping to meet the design requirements.
3. Limestone Gravel Surfacing on Middle Point Road: Dress and compact limestone gravel material on the surface of the constructed Middle Point Road Embankment.
4. Road Signs: Install road signs as noted in the drawings.
5. Seed Middle Point Road Shoulders and Borrow Ditches.
B. Middle Point Undesignated Two-Track Obliteration
1. Scarify and remove undesignated two-tracks on the Middle Point Peninsula.
Grade to the surrounding contours. Prepare suitable seed bed.
2. Seed Obliterated Road Areas: Seed prepared seed bed surface.
Belle Fourche Reservoir, South Dakota Solicitation No. R15PS00762
01 11 00 - 2
C. Tequila Beach Parking Area Construction
1. Shape and Blade Tequila Beach Parking Area and Trails: Strip and salvage topsoil. Water, scarify, compact, shape and blade Tequila Beach Parking Area with slope to drain northward. Soft spots shall be removed. Topsoil salvaged shall be wasted onsite as directed. Reclamation shall stake the perimeter of the parking area prior to work being performed. Contractor shall shape two walking trails from the parking area down the north slope for beach access as designated in the field.
2. Limestone Gravel Surfacing on Tequila Beach Parking Area: Dress and compact limestone gravel material on surface of Tequila Beach Parking Area.
D. Work is to be scheduled between October 24, 2015 and April 30, 2016. In the event of severe or wet weather, the Contracting Officer and/or COR will have authority to suspend work until such time that, in their opinion work may resume, in order to minimize damage or rutting of the travel routes.
E. Contractor will be responsible to repair or restore any damage caused by their work to the surrounding property to the satisfaction of the Contracting Officer and/or COR.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition
Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
B. Quality Assurance: Inspection and tests performed by Government to ensure compliance with the terms of the contract.
C. Quality Control: Activities performed by Contractor to ensure work conforms to contract requirements.
D. Contractor Quality Testing: Specified tests to be performed by the Contractor.
1. The Government may use the test results for Quality Assurance.
2. The Contractor may use the test results as part of Contractor quality control.
01 11 00 - 3
a. The Government anticipates that these tests will be part of the Contractor’s quality control program, however the tests do not relieve the Contractor of providing adequate quality control measures in accordance with the clause at FAR 52.246-12, Inspection of Construction.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer
2. COR: Contracting Officer’s Representative
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
01 11 00 - 4
This page intentionally left blank.
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 PROJECT CONDITIONS
A. Government land available for Contractor use as a staging area for contractor will be permitted as approved by the Contracting Officer.
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by the CO.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment: Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
3.02 RESTORATION
A. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
B. After completion of work, scarify and grade Government land used for construction purposes and not required for completed installation so that surfaces blend with natural
Use of Site 01 14 10 - 2 terrain and are in a condition that will facilitate natural vegetation, provide proper drainage, and prevent erosion.
C. See Section 32 92 20 - Seeding.
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work requiring submittals.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittal Types, as listed in Table 01 33 00A – List of Submittals:
1. A – Approval:
a. Government will approve, conditionally approved subject to identified changes, or disapprove these submittals.
b. Approval submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction.
2. I – Informational:
a. The Government will acknowledge receipt of these submittals.
b. The Government may reject an Informational submittal when the submittal does not comply with the contract. The Contractor shall correct mistakes or deficiencies in rejected Informational submittals and resubmit.
c. Informational submittals are considered to be “shop drawings” within the terms of the clause at FAR 52.236-21, Specifications and Drawings for Construction, except that approval by the Government is not required.
1.03 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
01 33 00 - 2
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Provide space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches).
4. Draw to scale with neat lettering using drafting equipment or computer drafting equipment.
5. Final drawings:
a. AUTOCAD® format (.dwg) on CD-ROM disc.
b. Original D size (22 inches by 34 inches) plots.
c. Show as-built changes, including revision dates, made during installation.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
01 33 00 - 3
1. Sign and seal submittals by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
1.04 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. Only one attached submittal per transmittal letter.
3. RSN for attached submittal.
4. Responsible code.
5. Number of sets for RSN.
6. Identify submittal as initial or resubmittal.
E. All submittals shall be submitted for approval in accordance with Table 01 33 00A – List of Submittals.
F. Test results for Acceptance Testing submittals should be submitted no later than 3 calendar days after the test was performed. If the test(s) fail, then the results should be submitted within 4 hours.
1.05 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 14 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
01 33 00 - 4
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete approval submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Return of Submittals:
1. One set of submittals required for approval will be returned either approved, approved subject to identified changes, or not approved.
2. Submittals not approved:
a. Revise and resubmit for approval.
b. Show changes and revisions with revision date.
c. Describe reasons for significant changes in transmittal letter.
d. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise specified.
e. Requirements for initial submittals apply to resubmittals.
3. Do not change designs without approval of the CO after approval drawings, documentation, and technical data have been approved.
01 33 00 - 5
4. The Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they comply with the specifications.
b. Informational submittals that do not comply with the specifications may be returned for resubmittal or additional information may be requested.
1.06 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Contracting Officer, Bureau of Reclamation, Attention: GP-5000 Gerri Voto- Braun, PO Box 36900, Billings, MT 59107.
2. Contracting Officer’s Representative, Bureau of Reclamation, Attention:
DK-4000 (George Finnegan), 515 9th Street, Room 101, Rapid City, SD 57701.
B. Send a copy of each transmittal letter to offices listed above which are not sent the submittal.
C. Submittals required by the specifications, but not listed in Table 01 33 00A - List of Submittals:
1. Submit in accordance with this section.
2. Submit to Contracting Officer’s Representative, Bureau of Reclamation, Attention: DK-4000 (George Finnegan), 515 9th Street, Room 101, Rapid City, SD 57701, unless otherwise specified.
PART 2 PRODUCTS
Not Used
Belle Fourche Reservoir, South Dakota Solicitation No. R15PS00762
01 33 00 - 6
Table 01 33 00A. - List of Submittals
* Submittal types: A – Approval, I – Information
** CO indicates Contracting Officer and COR indicates Construction Officer’s Representative.
RSN Clause or Section Title
Submittals required Due date or Delivery Time Ty pe
Respo nsible Code
No. of sets to be sent to: **
CO COR
1 Performance and Payment Bonds- Construction 52.228-15
Performance and Payment Bonds
Within 10 Calendar days after award
A CO 1 0
2 Insurance-Work on a Government Installation (52.228-5)
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
1) Before issue of notice to proceed
2) Prior to Contractors commencing onsite work
A CO 1 0
3 Liability Insurance (1452.228-70)
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
A CO 1 0
4 Equal Opportunity (52.222-26)
Information required by Executive Order
112246 (SF-100)
Within 30 Calendar days following contract Award
I CO 1 0
5 Release of Claims (1452.204-70)
Release Claims (DI-137) against the United States
After Completion of the work and prior to final payment.
A CO 1 1
6 Site Security
GP-7
List of Employees
List of Vehicles and Equipment
At least 10 days prior to arriving on site.
A COR 0 1
7 Payroll Records (52.222-08)
Payroll Records for Prime Contractor, Subcontractors and all Employees
Weekly for each week of contractor performance
A COR 1 1
8 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certificate that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
I CO 1 1
Belle Fourche Reservoir, South Dakota Solicitation No. R15PS00762
01 33 00 - 7
Table 01 33 00A. - List of Submittals
* Submittal types: A – Approval, I – Information
** CO indicates Contracting Officer and COR indicates Construction Officer’s Representative.
RSN Clause or Section Title
Submittals required Due date or Delivery Time Ty pe
Respo nsible Code
No. of sets to be sent to: **
CO COR
9 Labor
Standards (52.222-11)
1) List of Subcontractors
2) Statement and Acknowledgement form for each subcontractor
1) List of all contractor and subcontractors employees working onsite
2) Within 14 days after award of any subcontract
A COR 1 1
10 Schedules for Construction Contracts (52.236-15)
Baseline schedule: Within 5 days before work commences on the contract
A COR 1 1
Black line prints
11 Schedules for Construction Contracts (52.236-15)
Updated schedule or schedules:
As deemed necessary by the
CO/COR.
A COR 1 1
Black line prints
01 35 10-1 Material Safety Data Sheets
Complete LHM and
MSDS
At least 21 days before jobsite delivery of hazardous material
I COR 0 1
01 35 10-2 Material Safety Data Sheets
Updated LHM and
MSDS
At least 21 days before jobsite delivery of hazardous material not previously listed
I COR 1 1
01 35 20-1 Safety and Health (WBR 1452.223-81)
Safety and Health Plan including CPR and First Aid Certifications
Submitted and accepted before commencing onsite work. See section 3 of RSHS.
A COR 1 1
01 35 20-2 Safety and Health (WBR 1452.223-81)
Monthly Accident Report
First day of each month. See paragraph 3.8 of RSHS.
I COR 1 1
01 55 20-1 Traffic Control Traffic Control Plan At least 15 days before affecting public traffic
A COR 1 1
01 55 20-2 Traffic Control Certification of Sign and Post
At least 21 days prior to start of installation.
A COR 0 1
01 33 00 - 8
Table 01 33 00A. - List of Submittals
* Submittal types: A – Approval, I – Information
** CO indicates Contracting Officer and COR indicates Construction Officer’s Representative.
RSN Clause or Section Title
Submittals required Due date or Delivery Time Ty pe
Respo nsible Code
No. of sets to be sent to: **
CO COR
01 57 30-1 Water Pollution
Control Pollution Prevention Plan
At least 28 days before start of onsite construction work
A COR 0 1
01 57 30-2 Water Pollution Control
Spill Prevention, Control and Countermeasure Plan
(SPCC)
At least 28 days before delivery or storage of oil
A COR 0 1
01 71 20-1 Surveying Resume At least 10 days prior to surveying on site.
A COR 0 1
01 71 20-2 Surveying Accuracy Check Results At least 10 days prior to surveying on site.
A COR 0 1
01 71 20-3 Surveying Completed and Reduced Survey Notes
Prior to final payment. A COR 0 1
01 71 20-4 Surveying Original Field Survey Books or Electronic Data
Prior to final payment. A COR 0 1
01 71 20-5 Surveying Quantity Survey Notes and Computations
As needed for pay requests. A COR 0 1
01 71 20-6 Surveying Workday’s Survey Notes
Within 3 calendar days of Request by Government
A COR 0 1
01 74 10-1 Cleaning Waste Production and Disposal Records
Within 5 days Upon Completion of Site Clean Up and Disposal of All Waste Materials
A COR 1 1
01 33 00 - 9
Table 01 33 00A. - List of Submittals
* Submittal types: A – Approval, I – Information
** CO indicates Contracting Officer and COR indicates Construction Officer’s Representative.
RSN Clause or Section Title
Submittals required Due date or Delivery Time Ty pe
Respo nsible Code
No. of sets to be sent to: **
CO COR
01 74 10-2 Cleaning Hazardous Wastes
Manifest Within 5 days of discovery of Hazardous Waste
I COR 1 1
01 74 10-3 Cleaning Test Results on Unknown Wastes
Within 5 days of Hazardous Waste Manifest
I COR 1 1
31 23 02-1 Compacting Earth Materials
Certified Testing Lab for Earth Compaction
At least 15 days prior to testing
A COR 0 1
31 23 02-2 Compacting Earth Materials
Test Results Earth Compaction
No later than 3 calendar days after test was performed, unless tests fail, then within 4 hours of deficiency
A COR 0 1
31 27 32-1 Gravel Materials
NHPA Certification of Aggregate Source – Limestone Gravel Surfacing
At least 21 days prior to start of placement.
A COR 1 1
31 27 32-2 Gravel Materials
Gravel Material Gradation
At least 21 days prior to start of placement.
A COR 0 1
31 27 32-3 Gravel Materials
Gravel Material Weigh Tickets
Within 2 work days of material delivery.
A COR 0 1
31 27 32-4 Gravel Materials
NHPA Certification of Aggregate Source – Pit Run Material
At least 21 days prior to start of placement.
A COR 1 1
31 27 32-5 Gravel Materials
Pit Run Material Gradation
At least 21 days prior to start of placement.
A COR 0 1
31 27 32-6 Gravel Materials
Pit Run Material Weigh Tickets
Within 2 work days of material delivery.
A COR 0 1
32 92 20-1 Seeding and Soil Supplements
Certifications At least 14 days prior to seed and supplement delivery.
A COR 0 1
33 42 30-1 Corrugated Metal Pipe Culverts
Manufacturer’s Product Specifications and Data
At least 14 days prior to seed and supplement delivery.
A COR 0 1
33 42 30-2 Corrugated Metal Pipe Culverts
NHPA Certification of Aggregate Source – Select Material
At least 21 days prior to start of placement.
A COR 1 1
33 42 30-3 Corrugated Metal Pipe Culverts
Select Material Gradation
At least 21 days prior to start of placement.
01 33 00 - 10
Table 01 33 00A. - List of Submittals
* Submittal types: A – Approval, I – Information
** CO indicates Contracting Officer and COR indicates Construction Officer’s Representative.
RSN Clause or Section Title
Submittals required Due date or Delivery Time Ty pe
Respo nsible Code
No. of sets to be sent to: **
CO COR
33 42 30-4 Corrugated
Metal Pipe Culverts
Select Material Weigh Tickets
Within 2 work days of material delivery.
Material Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
MATERIAL SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials
B. MSDS: Material Safety Data Sheet.
1.03 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:
1. Materials delivered to the Government.
2. Materials incorporated into the work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. RSN 01 35 10-1, Complete LHM and MSDS:
a. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
2. RSN 01 35 10-2, Updated LHM and MSDS:
a. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and MSDS before receipt of updated LHM and MSDS by the Contracting Officer’s Representative.
Material Safety Data Sheets
01 35 10 - 2
PART 2 PRODUCTS
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Safety and Health Standards
1. Bureau of Reclamation (USBR)
a. RSHS-2009 Reclamation Safety and Health Standards
1) Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2) The October 2009 revision of the RSHS supersedes previous versions. For construction and other contracts that require a safety clause, the RSHS version that was in effect when the contract was signed would govern, unless there is a mutual agreement by the contracting parties to adopt this revised version. If there is a significant change that would affect the work being performed for a specific project, a modification may be explored with the contractor.
2. OSHA General Industry and Construction Standards
a. Available at www.osha.gov
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. RSN 01 35 20-1, Safety and Health Plan:
a. Written safety program in accordance with Section 3 and Appendix B of
USBR RSHS.
1) The Contractor shall provide a site specific written Safety Plan that is acceptable to Reclamation as listed on Table 01 33 00A. The program shall be consistent with the outline and content of the Reclamation Safety and Health Standard (RSHS), 2009 revision, Section 3 and Appendix B and include the program materials required by the Occupation Safety and Health standards (OSHA) for the work conducted. Due to the nature of the work the Written Plan shall include as a minimum; Hazard Communication, Personal Protective Equipment, Hearing Conservation.
http://www.osha.gov/
01 35 20 - 2
2) The written plan shall contain detailed information on the training, safe work practices, personal protective equipment and engineering controls to be used onsite to control hazard.
3) The Contractor shall be responsible for insuring that Subcontractors comply with the requirements set forth in this specification, the regulatory standards and the industry standards incorporated by reference in the RSHS and OSHA standards.
Where there is conflict between the standards, the more stringent or restrictive shall be utilized.
4) Medical Facilities Plan:
a) Describe facilities for providing medical attention for injured or disabled employees.
b) Employee’s qualifications to render CPR and First Aid.
Arrange for dependable ambulance service in accordance with USBR RSHS paragraph 5.4.
5) Resume of Contractor’s Onsite Safety Representative:
a) They must be capable of identifying existing and predictable hazards in the surround or working conditions which are unsanitary, hazardous or dangerous to employees, inspectors and the public. They must be qualified by possession of a recognized degree, certification, and/or professional standing, or by extensive knowledge, training and experience has successfully demonstrated the ability to solve or resolve work related safety and health problems. They must communicate effectively safety plans and activities with the Contract Officer’s Representative. Should the Contractor’s safety effort be considered inadequate, the Contract Officer has the option to require the Contractor to employ a qualified Safety Professional.
2. RSN 01 35 20-2, Monthly Accident Report:
a. Form 7-2218 or other acceptable form in accordance with paragraph 3.7 and 3.8 of USBR RSHS.
1.04 PROJECT CONDITIONS
A. Comply with RSHS.
B. Do not begin work on site until health and safety plans and certificates have been submitted, approved and implemented on site.
C. Provide and maintain a work environment and procedures that will:
1. Safeguard the public and Government's personnel exposed to Contractor operations and activities.
01 35 20 - 3
2. Avoid interruptions of site operations and delays in project completion dates.
3. Control costs in contract performance.
D. Do not require persons employed in performance of this contract, including subcontracts, to work under conditions which are unsanitary, hazardous, or dangerous to the employee’s health or safety.
E. Provide appropriate safety barricades and signs.
F. Maintain accurate record of and report to the CO the following occurrences during performance of this contract:
1. Death.
2. Occupational disease.
3. Traumatic injury to employees or the public.
4. Property damage in excess of $2,500.
G. Contractor must comply specifically with all of the requirements contained in USBR RSHS Section 3-Contractor Requirements.
H. The Contractor shall be responsible for insuring that subcontractors comply with the requirements set forth in this specification and all regulatory standards.
01 35 20 - 4
Traffic Control
01 55 20 - 1
SECTION 01 55 20
TRAFFIC CONTROL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Temporary Traffic Control
1. Cost: Include in prices offered in the schedule for other items of work.
B. Road Signs
1. Measurement:
a. Units of installed signs.
2. Payment:
a. Payment will be made at the unit price in the Bid Schedule for each sign installed.
1) This shall include all material, labor and installation costs for the signs, posts, concrete footer and mounting hardware.
1.02 REFERENCE STANDARDS
A. Federal Highway Administration, Department of Transportation
1. MUTCD, Part 6 Part 6, Temporary Traffic Control, MUTCD 2009, Manual on Uniform Traffic Control Devices, 2009 Edition, August 31, 2009 (http://mutcd.fhwa.dot.gov/)
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. RSN 01 55 20-1, Traffic Control Plan.
2. RSN 01 55 20-2, Certification of Sign and Post
a. Full product compliance with product requirements.
PART 2 PRODUCTS
2.01 SIGNS
A. Sign backing material. Flat sheet aluminum meeting ASTM B-209 alloy 6061-T6, or 5052-H38 with mill finish. Minimum 0.08-inch thickness.
B. Facing materials and finishes. Scotchlite or approved equal.
Traffic Control
01 55 20 - 2
2.02 POSTS AND HARDWARE
A. Tubular galvanized steel posts. AASHTO- M-111 270 Grade 36, and M-232.
B. Hardware: bolts, nuts, u-bots, washers, etc. shall be galvanized steel meeting ASTM A- 153.
PART 3 EXECUTION
3.01 TRAFFIC CONTROL
A. Meet requirements of MUTCD, Part 6. See Reference Standards above.
B. The contractor will be allowed to close the roads and parking area designated for construction to the public during the road construction project of Middle Point Rd and Tequila Beach Parking. Middle Point Road will NOT be closed to thru traffic until July 7th.
C. Conduct construction operations to minimize obstruction and inconvenience to public traffic.
D. Access will be maintained for government personnel as needed.
E. Provide cones, delineators, concrete safety barriers, barricades, flasher lights, danger signals, signs, and other temporary traffic control devices as required to protect work and public safety.
F. Provide signs, illumination, and traffic signals as required to prevent accidents and damage or injury to passing traffic 24 hours a day seven days a week both night and day.
G. Do not begin work along public or private roads until proper traffic control devices for warning, channeling, and protecting motorists are in place in accordance with approved traffic control plan.
H. Protect roads closed to traffic with effective barricades and warning signs. Illuminate barricades and obstructions in driving areas from sunset to sunrise.
I. Remove traffic control devices when no longer needed.
J. Public misconduct and/or trespassing in construction area will be communicated to Reclamation Inspector and or COR within 24 hours of observance.
3.02 SIGN INSTALLATION
A. Meet requirements of MUTCD. See Reference Standards above.
B. The signs shall be installed at the locations indicated on the drawings.
Water Pollution Control
01 57 30 - 1
SECTION 01 57 30
WATER POLLUTION CONTROL
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards
B. Code of Federal Regulations (CFR)
1. 40 CFR, Part 112 Oil Pollution Prevention
C. Public Law
1. Sections 311, 402, and 404 Clean Water Act (Public Law 92-500, as amended)
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. RSN 01 57 30-1. Pollution Prevention Plan:
a. As required by the stormwater permit for discharges from construction sites.
1) Compliant with South Dakota DENR SWPPP guidelines.
a) http://denr.sd.gov/des/sw/SWPPPRequirements.aspx
2. RSN 01 57 30-2, Spill Prevention, Control, and Countermeasure (SPCC) Plan:
a. Submit when SPCC Plan is required in accordance with 40 CFR, Part 112.
1) SPCC Plan is required where release of oil and oil products could reasonably be expected to enter into or upon navigable waters of the United States or adjoining shorelines in quantities that may be harmful (40 CFR, Part 110), and aggregate on site oil storage capacity is over 1,320 gallons. Only containers with capacity of 55 gallons and greater are included in determining on site aggregate storage capacity.
01 57 30 - 2
b. Reviewed and certified by a registered professional engineer in accordance with 40 CFR, Part 112, as required by Section 311 of the Clean Water Act (Public Law 92-500 as amended).
1.04 REGULATORY REQUIREMENTS
A. Construction Safety Standards:
1. Comply with sanitation and potable water requirements of Section 7 of RSHS.
B. Laws, Regulations, and Permits:
1. Perform construction operations to comply, and ensure subcontractors comply, with:
a. Applicable Federal, State, and local laws, orders, regulations, and Water Quality Standards concerning control and abatement of water pollution;
and terms and conditions of applicable permits issued by permit issuing authority.
b. If conflict occurs between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.
C. Contractor Violations:
1. If noncompliance should occur, immediately (verbally) report noncompliance to the CO. Submit specific written information within 2 days.
2. Violation of applicable Federal, State, or local laws, orders, regulations, or Water Quality Standards may result in the CO stopping site activity until compliance is ensured.
3. The Contractor shall not be entitled to extension of time, claim for damage, or additional compensation by reason of such a work stoppage.
4. Corrective measures required to bring activities into compliance shall be at the Contractor's expense.
1.05 REQUIRED PERMITS
A. Stormwater Discharge Permit Associated With a Construction Site:
1. Notice of Intent (NOI):
a. Both the Bureau of Reclamation and the Contractor shall sign the NOI to obtain coverage under a stormwater general permit to control stormwater discharges from the construction site as required under Section 402 of the Clean Water Act (Public Law 92-500, as amended).
2. Pollution Prevention Plan:
01 57 30 - 3
a. The Contractor shall prepare a Pollution Prevention Plan as required by the permit.
b. Comply with terms and conditions to obtain and maintain this stormwater discharge permit.
3. Monitoring:
a. Provide monitoring, if necessary, to achieve compliance with applicable Water Quality Standards.