Solicitation No. R15PS00695 Attachment B – Continuation of Price Schedule
Solicitation No. R15PS00695, Flow Meter upgrades at Flaming Gorge, Fontenelle, and Glen Canyon Dams
Continuation of Price Schedule
(a) Offers will be considered for award on the following price schedule, but no offer will be considered for award on only a part of the price schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Definitions:
(1) CLIN‐Contract Line Item Number
PRICE SCHEDULE
| CLIN |
| Description |
| Unit of Measure |
| Units |
| Unit Price |
| Total Price |
Glen Canyon Power Plant
| 11 |
| Furnish and install flowmeter systems in the bypass (hollow jet) tubes at Glen Canyon Power Plant |
| Each |
| 4 |
| 12 |
| Commission bypass tube flowmeter systems at Glen Canyon Power Plant |
| Lump Sum |
| 1 |
| 21 |
| Furnish Replacement Flowmeter Consoles for Penstocks at Glen Canyon Power Plant |
| Each |
| 9 |
| 22 |
| Furnish replacement network controller for flow meters at Glen Canyon Power Plant |
| Each |
| 1 |
| 23 |
| Commission replaced penstock flowmeter components at Glen Canyon Power Plant and train operators |
| Lump Sum |
| 1 |
Flaming Gorge Power Plant
| 31 |
| Furnish and install flowmeter systems in the bypass (hollow jet) tubes at Flaming Gorge Power Plant |
| Each |
| 2 |
| 32 |
| Commission bypass tube flowmeter systems at Flaming Gorge Power Plant |
| Lump Sum |
| 1 |
| 41 |
| Furnish Replacement Flowmeter Consoles for Penstocks at Flaming Gorge Power Plant |
| Each |
| 3 |
| 42 |
| Furnish replacement network controller for flow meters at Flaming Gorge Power Plant |
| Each |
| 1 |
| 43 |
| Commission replaced penstock flowmeter components at Flaming Gorge Power Plant and train operators |
| Lump Sum |
| 1 |
Fontenelle Power Plant
| 51 |
| Furnish Replacement Flowmeter Consoles for Penstocks at Fontenelle Power Plant |
| Each |
| 1 |
| 52 |
| Commission replaced penstock flowmeter components at Fontenelle Power Plant and train operators |
| Lump Sum |
| 1 |
File details come from the government source that posted it. Updated .