U.S. Department of the Interior Bureau of Reclamation Great Plains Region May 2015
Request For Proposal Solicitation No. R15PS00693
Enders Dam Spillway Gates and Outlet Works Gate Chamber Metalwork Recoating
Enders Unit Frenchman-Cambridge Division Pick-Sloan Missouri Basin Program Nebraska
U.S. Department of the Interior Bureau of Reclamation Great Plains Region May 2015
This page intentionally left blank i
ENDERS DAM
SPILLWAY GATES AND OUTLET WORKS GATE CHAMBER
METALWORK RECOATING
Pick-Sloan Missouri Basin Program
Nebraska
FOREWORD
Work is located at Enders Dam, in Chase County, Nebraska, approximately 3.5 miles southeast of Enders, Nebraska.
Work under these specifications is located at the dam spillway radial gates and includes sediment and animal droppings removal and cleaning, collection and analysis for heavy metals in work area locations, removal of existing coating systems and application of new coating systems to the gates, hoist motors, gearboxes, and drive shaft bearing pedestals, installation of bird barriers at trunnion anchor bolt block-outs, installation of bird spikes at gate locations, installation of rodent barriers at gate drain holes and grouting form tie holes in face of the spillway structure walls.
Additional work will be conducted at the adjacent outlet works gate chamber and includes cleaning, sample collection and analysis for heavy metals, removal of existing coating systems and application of new coating to the handrails, 8-inch bypass piping, 6-inch ventilation piping, ¼-inch air vent piping, slide gate hydraulic hoist, bonnet cover and hydraulic piping and gate hanger assembly.
TELEPHONE INQUIRIES REGARDING THIS SOLICITATION SHOULD BE MADE TO:
Contractual Matters: Gerri Voto-Braun Contracting Officer Billings, Montana Telephone: (406) 247-7809 gvotobraun@usbr.gov
FOR DATE AND PLACE PROPOSALS ARE DUE, SEE “SOLICITATION, OFFER, AND
AWARD," STANDARD FORM 1442, IMMEDIATELY FOLLOWING THE TABLE OF
CONTENTS.
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S PUBLICATION
"RECLAMATION SAFETY AND HEALTH STANDARDS," (2009 EDITION) WHICH IS
APPLICABLE TO WORK UNDER THIS CONTRACT, SEE CLAUSE AT "WBR
1452.223-81 SAFETY AND HEALTH."
PRE-BID SITE VISIT: AN ORGANIZED SITE VISIT HAS BEEN SCHEDULED FOR
JUNE 11, 2015 AT 11:00 AM. INTERESTED CONTRACTORS SHALL MAKE
ARRANGEMENTS IN ATTENDING THE SITE VISIT BY CONTACTING MR. JOHN
FOREMAN AT 970-962-4327 OR VIA E-MIAL AT JFOREMAN@USBR.GOV. SEE
PARAGRAPH L.16 FOR DIRECTIONS. ATTENDEES ARE TO PROVIDE AND WEAR
SAFETY BOOTS, HARD HATS AND SAFETY VESTS. PROSPECTIVE
CONTRACTORS ARE STRONGLY ENCOURAGED TO ATTEND THE PRE-BID SITE
ii
VISIT TO GAIN A BETTER UNDERSTANDING OF THE WORK REQUIREMENTS
AND SITE CONDITIONS.
SAM: EFFECTIVE JULY 29, 2012, ANY CONTRACTOR INTERESTED IN DOING
BUSINESS WITH THE GOVERNMENT MUST REGISTER IN THE SYSTEM FOR
AWARD MANAGEMENT (SAM) DATABASE PRIOR TO AWARD OF A CONTRACT
OR AGREEMENT. SAM IS A FEDERAL GOVERNMENT OWNED AND OPERATED
FREE WEBSITE THAT CONSOLIDATES THE CENTRAL CONTRACTOR
REGISTRATION (CCR), THE ONLINE REPRESENTATIONS AND CERTIFICATIONS
APPLICATION (ORCA), AND THE EXCLUDED PARTIES LIST SYSTEM (EPLS).
THE VENDOR’S DUNS AND BRADSTREET NUMBER AND BANKING
INFORMATION ARE REQUIRED FOR REGISTRATION. CONTRACTORS MAY
OBTAIN INFORMATION ON REGISTRATION AND ANNUAL CONFIRMATION
REQUIREMENTS VIA THE SAM WEBSITE ACCESSES THROUGH
HTTPS://WWW.SAM.GOV/PORTAL/PUBLIC/SAM/ OR BY THE FEDERAL SERVICE
DESK AT 1-866-606-8220.
PAYMENT REQUESTS FOR THE ANTICIPATED CONTRACT MUST BE
SUBMITTED ELECTRONICALLY THROUGH THE U.S. DEPARTMENT OF THE
TREASURY’S INTERNET PAYMENT PLATFORM (IPP) SYSTEM. THE IPP
WEBSITE IS HTTPS://WWW.IPP.GOV. THE CONTRACTOR MUST USE THE IPP
WEBSITE TO REGISTER ACCESS AND USE IPP FOR SUBMITTING REQUESTS
FOR PAYMENT. CONTRACTOR ASSISTANCE WITH ENROLLMENT CAN BE
OBTAINED BY CONTACTING THE IPP PRODUCTION HELPDESK VIA E-MAIL
IPPGROUP@BOS.FRB.ORG OR PHONE (866) 973-3131. IF THE CONTRACTOR IS
UNABLE TO COMPLY WITH THE REQUIREMENT TO USE IPP FOR SUBMITTING
INVOICES FOR PAYMENT, THE CONTRACTOR MUST SUBMIT A WAIVER
REQUEST IN WRITING TO THE CONTRACTING OFFICER WITH ITS PROPOSAL
OR BID.
i
TABLE OF CONTENTS
PART 1 – THE SCHEDULE
SECTION A – Solicitation, Offer and Award, Standard Form 1442
SECTION B – Schedule
SECTION C - Descriptions/ Specifications
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 20 Radial Gate Operation 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety and Health Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 20 Existing Fences 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 60 Protected Species 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 - EXISTING CONDITIONS
02 34 50 Bird and Rodent Barriers 02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
DIVISION 03 - CONCRETE
03 62 20 Grouting Mortar for Spillway Structure Walls
DIVISION 04 – NOT USED
DIVISION 05 – METALS
05 00 05 Miscellaneous Metalwork
DIVISION 06 – NOT USED
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 92 10 Sealants
DIVISION 08 – NOT USED
DIVISION 09 - FINISHES
09 96 20 Coatings
DIVISION 10 through DIVISION 50 – NOT USED
DIVISION 51 – INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 02 83 Existing Coatings Analysis ii
51 09 96 Photograph Log
DIVISION 52 – DRAWINGS
52 00 00 Drawings
DIVISION 53 – NOT USED
APPENDIX A
Enders Dam Spillway Gates and Outlet Works Gate Chamber Metalwork Recoating Existing Coatings Analysis
APPENDIX B
Enders Dam Spillway Gates and Outlet Works Gate Chamber Metalwork Recoating Photgraph Log
SECTION D – Not Used
SECTION E – Inspection and Acceptance Material and Workmanship ............................................................................................................. E-1 Inspection of Construction .............................................................................................................. E-1 Warranty of Construction ................................................................................................................ E-2
SECTION F – Deliveries or Performance Commencement, Prosecution and Completion of Work .................................................................. F-1 Variation in Estimated Quantity ....................................................................................................... F-1 Suspension of Work ......................................................................................................................... F-1
SECTION G -- Contract Administration Data Authorities and Delegations ............................................................................................................ G-1 Contractor’s Administration Personnel ........................................................................................... G-1 Electronic Invoicing and Payment Requirements – Internet Payment Platform ............................. G-2 PostAward Conference .................................................................................................................... G-2
SECTION H -- Special Contract Requirements Non-Discrimination Notice to U.S. Department of the Interior Contractors, Subcontractors, and Lessors (Dec1999) .......................................................................................... H-1 Contractor Performance Assessment Reporting System ................................................................. H-1 Site Security .................................................................................................................................... H-2
PART II – CONTRACT CLAUSES
SECTION I -- Contract Clauses Clauses Incorporated by Reference .................................................................................................. I-1 Restrictions on Endorsements .......................................................................................................... I-3 Release of Claims ............................................................................................................................. I-3 Examination of Records by the Department of the Interior .............................................................. I-3 Liability Insurance ............................................................................................................................ I-3 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements (Deviations) ...................................................................................................................................... I-4 Commercial and Governmental Entity Code Maintenance .............................................................. I-4 Incorporation by Reference of Representations and Certifications .................................................. I-5 Order of Precedence – Uniform Contract Format ............................................................................ I-5 Establishing a Minimum Wage for Contractors (Deviation) ............................................................ I-5 Buy American Act – Construction Materials ................................................................................... I-8 Bid Guarantee ................................................................................................................................. I-11 Performance and Payment Bonds ................................................................................................... I-11 Payments Under Fixed-Price Construction Contracts .................................................................... I-12 Prompt Payment for Construction Contracts .................................................................................. I-14 iii
Changes .......................................................................................................................................... I-20 Change Order Accounting .............................................................................................................. I-21 Authorized Deviations in Clauses .................................................................................................. I-21 Asbestos-Free Warranty ................................................................................................................. I-21 Safety and Health ........................................................................................................................... I-21 Protesting Federal Employees and the Public from Exposure to Tobacco and Smoke in the Federal Workplace ................................................................................................... I-22 Certification of Representatives for Corporate Sureties ................................................................. I-22 Equipment Ownership and Operating Expense .............................................................................. I-23 Limitation of Funds ........................................................................................................................ I-24 Payment for Mobilization and Preparatory Work .......................................................................... I-25 Claims Accounting ......................................................................................................................... I-27 Preservation of Cultural Resources ................................................................................................ I-27 Security Requirements – Alternate III ............................................................................................ I-28 Modification Proposals – Alternate IV ........................................................................................... I-35
PART III – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J – DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
Attachment No. 1 General Decision NE150048, dated March 20, 2015 Attachment No. 2 Standard Form 24, Bid Bond Attachment No. 3 Past Performance Questionnaire (Evaluation Factor 4)
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K -- Representations, Certifications and Other Statements of Offerors Annual Representations and Certifications ..................................................................................... K-1 Information Regarding Responsibility Matters ............................................................................... K-3
SECTION L -- Instructions, Conditions and Notices to Bidders Authorized Workers Notice to Potential Bureau of Reclamation Contractors ................................ L-1 Use and Disclosure of Proposal Information ................................................................................... L-2 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements – Representations ........................................................................................................ L-3 System for Award Management ...................................................................................................... L-3 Commercial and Government Entity Code Reporting ..................................................................... L-5 Availability of Specifications Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions, FPMR art 101-29 .......................................................................... L-6 Availability of Specifications, Standards, and Data Item Descriptions Listed in the Acquisition
Streamlining and Standardization Information System (ASSIST) .................................................. L-6 Submission of Offers in the English Language ............................................................................... L-6
Submission of Offers in U.S. Currency ........................................................................................... L-6 Instructions to Offerors – Competitive Acquisition ........................................................................ L-6 Type of Contract ............................................................................................................................ L-10 Contract Wage Rate Requirements - Secondary Site of Work ...................................................... L-10 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction ........................................................................................................ L-10 Notice of Buy American Act Requirement – Construction Materials ........................................... L-11 Service of Protest – Department of the Interior (Deviation) ......................................................... L-12 Site Visit (Construction)- Alternate I ........................................................................................... L-12 Preparation of Proposals ................................................................................................................ L-13 Authorized Deviations in Provisions ............................................................................................. L-13 Notice of Intent to Acquire Metric Products and Services ............................................................ L-13 Source Evaluation and Selection Procedures ................................................................................ L-14 General Proposal Instructions........................................................................................................ L-16 iv
Technical Proposal Instructions .................................................................................................... L-17 Pricing Proposal Instructions ......................................................................................................... L-18 Notice of Proposed Partnering ....................................................................................................... L-19 Instruction for Mobilization and Preparatory Work Schedule Line Item ...................................... L-19
SECTION M – Evaluation Factors for Award Evaluation Factors for Award – Quality Predominance ................................................................. M-1 Notice of World Trade Organization Government Procurement Agreement Evaluations ............. M-4
PART I – THE SCHEDULE
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040197617
Bureau of Reclamation
Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Bureau of Reclamation
Attention: Gerri Voto-Braun (GP-5000) 2021 4th Avenue North Billings, MT 59101
Gerri Voto-Braun 406-247-7809
1x 05/25/2015
R15PS00693
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Enders Dam Spillway Gates and Outlet Works Gate Chamber Metalwork Recoating, Enders
Unit, Frenchman-Cambridge Division, Pick-Sloan Missouri Basin Program, Nebraska
The work is located at Enders Dam, approximately 3.5 miles southeast of Enders, Nebraska in Chase County
The estimated price range for this project is $500,000 to $1,000,000
The North American Industrial Classisfication Code is 238320
The Small Business Size Standard is $15 Million
Taxpayer Identification Number: ________________________________
Data Universal Numbering System: _______________________________
Commercial and Government Entity Code: _________________________
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 240 calendar days and complete it within ________________ ________________ calendar days after receiving
Pragraph F.1
06/26/2015
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF 4
Bureau of Reclamation Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Gerri Voto-Braun
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R15PS00693
00010 Enders Dam Spillway Gates and Outlet Works Gate
Chamber Metalwork Recoating 1 AU $_______________
Price Schedule CLINS 1 through 16
(See the following continuation pages)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Enders Dam Spillway Gates and Outlet Works Gate Chamber Metalwork Recoating Specification No. 60-C0652
Schedule
B - 1
CONTINUATION OF SECTION B – SUPPLIES OR SERVICES AND PRICES
ENDERS DAM
SPILLWAY GATES AND OUTLET WORKS GATE CHAMBER
METALWORK RECOATING
Pick-Sloan Missouri Basin Program
Frenchman-Cambridge Division
B.1 SCHEDULE
(a) Offers will be considered for award on the following schedule, but no offer will be considered for award on only a part of the schedule.
(b) All offers are subject to the terms and conditions of this solicitation.
(c) The quantities in the schedule are estimated quantities for comparison of offers only, and except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number
SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
1 WBR
1452.232-81
Mobilization and Preparatory Work
For the lump sum of $
2 01 55 20 Traffic Control For the lump sum of $
3 02 34 50 Bird Barriers For the lump sum of $
4 02 34 50 Bird Spikes 216 each $ $
5 02 34 50 Rodent Barriers 48 each $ $
6 02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
For the lump sum of $
7 03 62 20 Grouting Mortar at Spillway Structure Side Walls
100 each $ $
Schedule
B - 2
SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
8 05 00 05 Glass-Reinforced Epoxy Isolation
576 each $ $
9 07 92 10 Sealant 1,500 lf $ $
10 09 96 20 Spillway Gate Spot Recoating Repairs – Structural Steel Crevices and Connections
240 ft2 $ $
11 09 96 20 Spillway Gate Spot Recoating Repairs – Interior and Exterior Spillway Gate, Lower Section
1,750 ft2 $ $
12 09 96 20 Trunnion Anchor Assembly 850 ft2 $ $
13 09 96 20 Spillway Gate Hoist Equipment – Spot Repair
20 ft2 $ $
14 09 96 20 Spillway Gate Hoist Equipment – Topcoat Coating
300 ft2 $ $
15 09 96 20 Outlet Works Gate Chamber Structures – Spot Repair
30 ft2 $
16 09 96 20 Outlet Works Gate Chamber Structures – Topcoat Coating
210 ft2 $ $
TOTAL FOR SCHEDULE $_________________
END OF SCHEDULE
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located at Enders Dam, in Chase County, Nebraska, approximately 1.5 miles south of Enders, Nebraska. Refer to Figure 1, Site Map, for project location.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Work under these specifications is located at the dam spillway radial gates and includes sediment and animal droppings removal and cleaning, collection and analysis for heavy metals in work area locations, removal of existing coating systems and application of new coating systems to the gates, hoist motors, gearboxes, and drive shaft bearing pedestals, installation of bird barriers at trunnion anchor bolt block-outs, installation of bird spikes at gate locations, installation of rodent barriers at gate drain holes and grouting form tie holes in face of the spillway structure walls.
Additional work will be conducted at the adjacent outlet works gate chamber and includes cleaning, sample collection and analysis for heavy metals, removal of existing coating systems and application of new coating to the handrails, 8-inch bypass piping, 6-inch ventilation piping, ¼-inch air vent piping, slide gate hydraulic hoist, bonnet cover and hydraulic piping and gate hanger assembly.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition
Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer
2. COR: Contracting Officer’s Representative
01 11 00 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
01 11 00 - 3
FIGURE 1 – SITE MAP
END OF SECTION
Enders Dam Spillway
NE State Hwy. 61
To Enders, NE
To Benkelman, NE
Outlet Works Access
Building
Access Road to US Hwy. 6
Enders Reservoir
Spillway
N
01 11 00 - 4
This page intentionally left blank.
Use of Site
01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and
Vehicles to Prevent the Spread of Invasive Species
(Technical memorandum No. 86-68220-07-05)
2010 Edition
Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Areas for processing, storing, and disposing of waste materials from construction operations.
6) Temporary fences.
b. Describe methods to preserve, protect, and repair if damaged, vegetation
(such as trees, shrubs, and grass) and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not http://www.usbr.gov/mussels/prevention
01 14 10 - 2 interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during the construction stage or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
B. Location, construction, operation, maintenance, and removal of construction facilities on
Government land will be subject to approval of the COR.
C. Housing for construction personnel will not be permitted on Government land.
D. The bridge over Enders Dam is Nebraska State Highway 61. Refer to Section 01 55 20 –
Traffic Control.
E. A clear, 15-foot unobstructed path along the access roads to the outlet works must be maintained to allow for emergency access to the spillway.
F. Reclamation will not lower the water level should the reservoir rise to the sill elevation, Elev. 3097.00. The last time the reservoir pool water was on the gates was May, 2000.
The reservoir pool elevation is currently (June 2014) about 14 ft below the sill and due to water demands provided to specified Nebraska irrigation districts, the water elevation is not anticipated to rise to the sill during the construction period of this project.
G. Accessing the spillway floor can be made on foot. However, placing equipment, materials, scaffolding, man lifts, etc. will require crane operations. A crane can access the spillway floor from State Highway 61 bridge over the spillway or by the downstream north spillway wall adjacent to Outlet Works Access Building. Refer to Figure 1 Site
Map, Section 01 11 00 – Summary of Work.
PART 2 PRODUCTS
01 14 10 - 3
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.
3. The COR will inspect construction equipment following procedures described in
USBR Cleaning Manual before allowing the equipment onsite.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition. These areas would include, but not limited to, any staging, storage, parking or surface work areas.
B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
C. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
D. Reseed disturbed areas in accordance with Section 32 92 20 – Seeding and Soil
Supplements.
01 14 10 - 4
Radial Gate Operation
01 14 20-1
SECTION 01 14 20
RADIAL GATE OPERATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include cost in prices offered in the schedule for work requiring operation of the radial gates.
1.02 PROJECT CONDITIONS
A. Government-owned hoists will be required to open and close the radial gates.
B. Government will provide operator. Operation of radial gates by Contractor personnel is not permitted.
C. Contractor shall coordinate the opening and closing of the radial gates with the
Contracting Officer’s Representative (COR). Provide the COR 24-hours notice of required opening/closing/repositioning of radial gates to ensure Government operator is available to operate.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Radial Gate Operation
01 14 20-2
Submittals
01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedules for other items of work.
1.02 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
C. Submittals: Considered “shop drawings” within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.
1.03 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Provide space next to title block for review stamps.
3. Size: D size (22 inches by 34 inches).
4. Draw to scale with neat lettering using drafting equipment or computer drafting equipment.
1. Final drawings:
a. Drawing format: AUTOCAD, Version 2007 or later.
01 33 00 - 2
b. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
c. Electronic files: On CD or DVD discs.
d. Original plots: D size (22 inches by 34 inches).
e. Government will provide an electronic AutoCAD template.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
1.04 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit sets specified in “Sets to be sent:” columns in Table 01 33 00A - List of Submittals.
1. Electronic submittals:
a. In Portable Document Format (PDF).
b. Include RSN transmittal letter.
c. Do not include Personally Identifiable Information (PII) in electronic submittals.
2. Submit electronic submittals via email or CD/DVD based on size:
a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra large. E-mailing of electronic
01 33 00 - 3 submittals exceeding 10 MB should only occur after transmittal of larger size e-mail has been verified.
b. Address e-mail of electronic submittals less than extra large size to:
1) sha-GPR-CONSTSVCS@usbr.gov
c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on CD or DVD.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 28 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. Each submittal shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.
1.05 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
01 33 00 - 4
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
1. A response letter from the COR for each submittal will be sent to the Contractor indicating if the submittal is either approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.
1.06 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.
2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
01 33 00 - 5
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title Submittals required
Due date or delivery time
Respon-sible code
Sets to be sent: **
CO COR
1 Performance and Payment Bonds – Construction 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1 0
2 Insurance-work on a Government Installation 52.228-05
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work
CO
CO
3 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1 0
4 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award
CO 1 0
5 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1 0
6 Site Security
GP-7
Employee Information Initially at least 21 days before beginning onsite work; at least 21 days before additional employees arrive on-site
COR 0 1
7 Site Security
GP-7
Vehicle Information At least 21 days before beginning on-site work
COR 0 1
9 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1
10 Payrolls and Basic Records 52.222-08
Copies of all payrolls Weekly for each week of contract performance
COR 1 1
01 33 00 - 6
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title Submittals required code
Sets to be sent: **
CO COR
11 Schedules for Construction Contracts 52.236-15
Practicable Schedule Within 5 days after work commences on the contract or another period of time as determined by CO
COR 1 paper 1 paper + 1 electronic
12 Schedules for Construction Contracts 52.236-15
Updated Schedule showing actual progress
Monthly or as directed by the CO
COR 1 paper 1 paper + 1 electronic
13 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1 0
Division 1 – General 01 14 10-1 Use of Site Land Use and
Landscape Rehabilitation Plan
At least 28 days before use of Government land
COR 0 1 paper + 1 electronic
01 35 10-1 Safety Data Sheets
Complete LHM and
SDS
At least 14 days before jobsite delivery of hazardous material
COR 0 1 paper + 1 electronic
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 14 days before jobsite delivery of hazardous material not previously listed
COR 0 1 paper + 1 electronic
01 35 20-1 Safety and Health Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS
COR 0 1 paper + 1 electronic
01 35 20-2 Safety and Health Monthly Accident Summary Report
First day of each month. See paragraph
3.8 of RSHS
COR 0 1 paper + 1 electronic
01 35 20-3 Safety and Health Respirator User Documentation
At least 14 days before arriving at worksite
COR 0 2 paper
01 35 20-4 Safety and Health Crane Training Certificates
At least 14 days before arriving at worksite
COR 0 2 paper
01 35 20-5 Safety and Health Other Training Certificates
At least 14 days before arriving at worksite
COR 0 2 paper
01 35 30-1 Contractor’s Onsite Safety and Health Personnel
Qualifications At least 20 days before beginning onsite work
COR 0 2 paper
01 35 30-2 Contractor’s Onsite Safety and Health Personnel
CIH Inspection Reports
At least once each month
COR 0 1 paper + 1 electronic
01 35 30-3 Contractor’s Onsite Safety and Health Personnel
Safety Inspection Reports
At least once each week
COR 0 1 paper + 1 electronic
01 55 20-1 Traffic Control Traffic Control Plan At least 35 days before affecting public traffic
COR 0 1 paper + 1 electronic
01 33 00 - 7
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title Submittals required code
Sets to be sent: **
CO COR
01 56 10-1 Protection of Existing Installations
Plan for Protecting Existing Installations
At least 28 days before starting onsite work
COR 0 1 paper + 1 electronic
01 57 20-1 Environmental Controls
Copy of Applicable Air Quality Permit
At least 30 days before starting onsite construction
COR 0 1 paper
1 electronic 01 57 30-1 Water Pollution
Control Water Management Plan
At least 28 days before commencing onsite construction work
COR 0 1 paper + 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention Control and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil
COR 0 1 paper + 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
At least 21 days before beginning onsite work
COR 0 1 paper + 1 electronic
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
COR 0 1 paper + 1 electronic
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 21 days before beginning environmental assessment
COR 0 2 paper
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
COR 0 1 paper + 1 electronic
01 78 30-1 Project Record Documents
Warranties Within 10 days of completion of work
COR 0 2 paper
1 electronic Division 2 – Existing Conditions 02 34 50-1 Bird and Rodent
Barriers Manufacturer’s Literature
At least 20 days before starting onsite construction
COR 0 1 paper
1 electronic 02 34 50-2 Bird and Rodent
Barriers “Or Equal” Products At least 20 days before starting onsite construction
COR 0 2 paper
1 electronic 02 34 50-3 Bird and Rodent
Barriers Typical Layout of Bird Barriers
At least 20 days before starting onsite construction
COR 0 2 paper
1 electronic 02 83 30-1 Removal and
Disposal of Coatings Containing Heavy Metals
Documentation Submitted before commencing onsite work.
COR 0 1 paper
1 electronic
01 33 00 - 8
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title Submittals required code
Sets to be sent: **
CO COR
02 83 30-2 Removal and Disposal of Coatings Containing Heavy Metals
Qualifications Submitted and accepted before commencing onsite work.
COR 0 2 paper
02 83 30-3 Removal and Disposal of Coatings Containing Heavy Metals
Written Compliance Program for Worker Protection
Within 24 hours of receipt from the lab.
COR 0 1 paper + 1 electronic
02 83 30-4 Removal and Disposal of Coatings Containing Heavy Metals
Plans At least 30 days before beginning onsite work.
COR 0 1 paper + 1 electronic
02 83 30-5 Removal and Disposal of Coatings Containing Heavy Metals
Heavy Metal Exposure Certifications and Test Results
Within 2 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-6 Removal and Disposal of Coatings Containing Heavy Metals
Preconstruction Test Results
Within 2 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-7 Removal and Disposal of Coatings Containing Heavy Metals
Working Level Test Results
Within 14 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-8 Removal and Disposal of Coatings Containing Heavy Metals
Post-Construction Test Results
Within 7 days after tests are completed
COR 0 1 paper + 1 electronic
02 83 30-9 Removal and Disposal of Coatings Containing Heavy Metals
Certificate of Disposal Within 7 days after disposal.
COR 0 1 paper + 1 electronic
Division 3 – Concrete 03 62 20-1 Grouting Mortar for Spillway Structure Walls
Packaged Nonshrink Grout Data
At least 14 days prior to construction.
COR 0 1 paper
1 electronic Division 5 – Metals 05 00 05-1 Miscellaneous
Metalwork Welding Procedures and Welder Certifications
At least 20 days before starting onsite construction
COR 0 1 paper
01 33 00 - 9
Table 01 33 00A. - List of Submittals ** CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title Submittals required code
Sets to be sent: **
CO COR
05 00 05-2 Miscellaneous Metalwork
Approval Data At least 20 days before starting onsite construction
COR 0 1 paper
1 electronic 05 00 05-3 Miscellaneous
Metalwork “Or Equal” Products At least 20 days before starting onsite construction
COR 0 1 paper
1 electronic Division 7 – Thermal and Moisture Protection 07 92 10-1 Sealants Approval Data At least 20 days before starting onsite construction
COR 0 1 paper
1 electronic 07 92 10-2 Sealants “Or Equal” Products At least 20 days before starting onsite construction
COR 0 1 paper
1 electronic Division 9 – Finishes 09 96 20-1 Coatings Approval Data At least 20 days before beginning on-site work.
COR 0 1 paper
1 electronic
09 96 20-2 Coatings Final Approval Data At least 14 days before application.
COR 0 1 paper
1 electronic 09 96 20-3 Coatings Certifications At least 20 days before beginning on-site work.
COR 0 1 paper
1 electronic
09 96 20-4 Coatings Documentation At least 20 days before beginning on-site work.
COR 0 1 paper
1 electronic 09 96 20-5 Coatings Contractor Quality
Testing Data for “Shop or Field Applied” Coatings
At least 20 days before beginning on-site work.
COR 0 1 paper
01 33 00 - 10
Safety Data Sheets
01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous
Material Identifications and Material Safety Data - Alternate 1.
1.03 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data -
Alternate 1, includes:
1. Materials delivered to the Government.
2. Materials incorporated into the work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material
Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and SDS before receipt of updated LHM and SDS by
Contracting Offices Representative.
Safety Data Sheets
01 35 10 - 2
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Safety and Health
01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include the cost of complying with this section in the prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards
a. Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2. FIST 1-1 (2012) Hazardous Energy Control Program
a. Available on the Internet at:
www.usbr.gov/power/data/fist_pub.html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910…