U.S. Department of the Interior Bureau of Reclamation PN Region May 2015
Solicitation No. R15PS00313
Hungry Horse Visitor Areas and Parking Lot Improvements Hungry Horse Project, Montana
This solicitation issued by Contracting Officer
Pacific Northwest Region Bureau of Reclamation
1150 North Curtis Road, Suite 100 Boise ID 83706-1234
Phone inquiries regarding this solicitation should be made to Contracting Officer
Telephone Number: (208) 378-5156
HUNGRY HORSE VISITOR AREAS AND PARKING LOT IMPROVEMENTS
HUNGRY HORSE PROJECT, MONTANA
FOREWORD
Work is located approximately 20 miles northeast of Kalispell, Montana, and 9 miles southeast of Columbia Falls, Montana, in Flathead County.
The principal components of the work to be performed under these specifications at Visitors Center Overlook include; removing and replacing the Visitors Center Overlook shelter roof, fascia, and metal decking, removing red lead paint from the Visitors Center Overlook shelter and repainting, constructing a van accessible parking space with curb ramp in front of the Visitors Center Overlook, furnishing and placing new electrical conduit from the Main Visitors Center to the Visitors Center Overlook, furnishing and placing a concrete walkway with curb between the Visitors Center Overlook and the Main Visitor Center, remove and replace existing chain link fencing between the Main Visitors Center and approximately 280 feet west of the Visitors Center Overlook ,.
At the Main Visitors Center, constructing a van accessible parking space with access aisle in front of the Visitors Center, removing existing concrete curb ramp in front of Visitors Center and replacing it with a new walkway, removing asphalt ramp and installing concrete stairs and handrails, improvements to parking area in front of Visitors Center, saw cutting parapet wall in back of Visitors Center and installing viewing window to be accessible to all visitors, improvements to parking area on the west side of the Visitors Center,.
At the Spillway Viewing Area include saw cutting the parapet wall in front of Spillway and installing viewing window to be accessible to all visitors, and constructing concrete walkway in front of parapet wall and constructing viewing pad overlooking spillway to be accessible to all visitors.
At South parking area include constructing an accessible walking, viewing, and picnic pad area adjacent to north side of parking area, constructing van accessible parking space with access aisle, saw cutting, removing, and disposing of existing asphalt, grading, installing base coarse, and hot mix asphalt paving for South Parking Area, furnishing and installing concrete slab at tight radius at the south abutment, and furnishing and installing storm drains. Furnishing and installing a 1500-gallon tank at the parking area.
Removing and replacing all street lighting in all parking areas.
A pre-bid site visit will be conducted in accordance with the Clause in Section L entitled “Site Visit - Construction.” Offerors are strongly urged to participate in the site visit. Failure by Offerors to inspect the site will not relieve them of the responsibility of properly estimating the difficulty or cost of successfully performing the work in accordance with the specifications and within the allowed time.
Attendees are to provide and wear safety boots, hard hats, and safety vests.
FOR DATE AND PLACE OF BID OPENING, SEE "SOLICITATION, OFFER, AND
AWARD," STANDARD FORM 1442, IMMEDIATELY FOLLOWING THE "TABLE OF
CONTENTS."
FOR INFORMATION REGARDING BUREAU OF RECLAMATION'S HANDBOOK ENTITLED
"RECLAMATION SAFETY AND HEALTH STANDARDS," (2009 EDITION) WHICH IS
APPLICABLE TO WORK UNDER THIS CONTRACT, SEE NOTICE IN PART II, SECTION I
ENTITLED "SAFETY AND HEALTH."
Hungry Horse Visitor Areas and Parking Lot Improvements i
PART I THE SCHEDULE
SECTION A SOLICITATION/CONTRACT FORM ..................................................................... A-1
SECTION B SUPPLIES OR SERVICES AND PRICES/COSTS ...................................................B-1
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ........................... C-1
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 29 00 Payment Procedures 01 33 00 Submittals 01 35 10 Material Safety Data Sheets 01 35 20 Safety and Health 01 35 21 Removal From Work 01 35 30 Contractor’s Onsite Safety and Health Professional 01 42 10 Reference Standards 01 43 10 Quality Control Testing for Earthwork and Cast in Place Concrete 01 43 20 Contractor Quality Control For Materials Used In The Work 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 60 00 Product Requirements 01 71 20 Surveying 01 74 10 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 - EXISTING CONDITIONS
02 41 00 Demolition 02 42 00 Salvage 02 82 20 Removal and Disposal of Asbestos Containing Materials 02 83 30 Removal and Disposal of Coatings Containing Heavy Metals
DIVISION 03 - CONCRETE
ii
03 30 00 Cast-In-Place Concrete 03 40 00 Precast Concrete
DIVISION 04 –MASONRY
04 70 00 Manufactured Masonry
DIVISION 05 - METALS
05 50 00 Metal Fabrications 05 73 13 Aluminum Glass Panel Railing
DIVISION 06 – NOT USED
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50 Roof Materials Removal 07 54 23 Fully-Adhered TPO Roof System 07 92 00 Joint Protection
DIVISION 08 – NOT USED
DIVISION 09 - COATINGS
09 96 20 Coatings
DIVISION 10 - SPECIALTIES
10 14 00 Traffic Signs 10 14 53 Accessible Signs
DIVISION 11 – NOT USED
DIVISION 12 – FURNISHINGS
12 93 00 Site Furnishings
DIVISIONS 13 THROUGH 25 – NOT USED
DIVISION 26 - ELECTIRCAL
26 05 02 Basic Electrical Requirements 26 05 10 Insulated Conductors 26 05 20 Grounding and Bonding iii
26 05 29 Hangers and Supports 26 05 33 Conduits 26 05 60 Equipment Identification 26 27 16 Enclosures and Boxes 26 27 30 Wiring Devices 26 29 13 Starters, Contactors, and Safety Disconnects 26 55 00 Lighting
DIVISIONS 27 THROUGH 30 – NOT USED
DIVISION 31 - EARTHWORK
31 11 00 Clearing and Grubbing 31 23 02 Compacting Earth Materials 31 23 21 Earthwork for Structures 31 23 22 Conduit Pipe Trench Earthwork 31 23 23 Compacted Gravel Backfill 31 23 30 Excavate Pavement 31 23 39 Disposal of Excavated Materials
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 26 Pavement Grinding 32 05 19 Geotextile 32 11 23 Aggregate Base Courses 32 12 16 Hot Mix Asphalt (HMA) 32 12 36 Seal Coat 32 17 13 Wheel Stops 32 17 20 Pavement Markings 32 31 13 Chain Link Fence
DIVISION 33 - UTILITIES
33 11 14 Pipe to Precast Tank Fittings 33 41 10 Storm Drains and Grating
DIVISIONS 34 THROUGH 50 – NOT USED
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Photographs 51 00 20 Hazardous Materials Information 51 00 40 End of Month Elevations iv
DIVISION 52 - DRAWINGS
52 00 00 Drawings
SECTION D PACKAGING AND MARKING ................................................................................. D-1
SECTION E INSPECTION AND ACCEPTANCE ..........................................................................E-1 E.1. 52.236-5 MATERIAL AND WORKMANSHIP (APR 1984) ........................................ E-1 E.2. 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)...................................... E-1
E.3. 52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994) - ALTERNATE I
APR 1984) ....................................................................................................................... E-3
SECTION F DELIVERIES OR PERFORMANCE ......................................................................... F-1
F.1. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984) ......................................................................................................... F-1 F.2. 52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEPT 2000) ................... F-1 F.3. 52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984) ........................... F-1 F.4. 52.242-14 SUSPENSION OF WORK (APR 1984) ........................................................ F-1
SECTION G CONTRACT ADMINISTRATION DATA ................................................................ G-1
G.1. GOVERNMENT POINT OF CONTACT--BUREAU OF RECLAMATION--PN
REGION (OCT 2010) ..................................................................................................... G-1
G.2. 1452.201-70 AUTHORITIES AND DELEGATIONS--DEPARTMENT OF THE
INTERIOR (MAY 2010) ................................................................................................ G-1
G.3. ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS-INVOICE
PROCESSING PLATFORM (IPP) (APRIL 2013) ........................................................ G-2
SECTION H SPECIAL CONTRACT REQUIREMENTS ............................................................. H-1
H.1. AUTHORIZED WORKERS NOTICE TO POTENTIAL BUREAU OF
RECLAMATION CONTRACTORS (SEP 2002).......................................................... H-1
H.2. CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM
(JULY 2010) ................................................................................................................... H-2
PART II CONTRACT CLAUSES
SECTION I CONTRACT CLAUSES ................................................................................................ I-1 I.1. 52.202-1 DEFINITIONS (NOV 2013) ............................................................................. I-1 I.2. 52.203-3 GRATUITIES (APR 1984) ............................................................................... I-1 I.3. 52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)........................ I-2
I.4. 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE
GOVERNMENT (SEPT 2006)......................................................................................... I-2 I.5. 52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014) .......................................... I-2 v
I.6. 52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS
FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) ........................................... I-4
I.7. 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014) .................................................................................................. I-5
I.8. 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN
FEDERAL TRANSACTIONS (OCT 2010) .................................................................... I-6
I.9. 52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND
REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER
RIGHTS (APR 2014) ...................................................................................................... I-10
I.10. 52.203-99 PROHIBITION ON CONTRACTING WITH ENTITIES THAT
REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS
(MAR 2015) .................................................................................................................... I-11
I.11. 1452.203-70 RESTRICTION ON ENDORSEMENTS--DEPARTMENT OF THE
INTERIOR (JUL 1996) .................................................................................................. I-11
I.12. 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER
FIBER CONTENT PAPER (MAY 2011) ...................................................................... I-11
I.13. 52.204-7 SYSTEM FOR AWARD MANAGEMENT (JUL 2013) ............................... I-12
I.14. 52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR
PERSONNEL (JAN 2011) ............................................................................................. I-14
I.15. 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER
SUBCONTRACT AWARDS (JUL 2013) ..................................................................... I-14
I.16. 52.204-12 DATA UNIVERSAL NUMBERING SYSTEM NUMBER
MAINTENANCE (DEC 2012)....................................................................................... I-18
I.17. 52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE. (JUL
2013) ............................................................................................................................... I-18
I.18. 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS
AND CERTIFICATIONS (DEC 2014) .......................................................................... I-20
I.19. 1452.204-70 RELEASE OF CLAIMS -- DEPARTMENT OF THE INTERIOR
(JUL 1996) ...................................................................................................................... I-20
I.20. 52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN
SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED,
OR PROPOSED FOR DEBARMENT (AUG 2013)...................................................... I-21
I.21. 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION
REGARDING RESPONSIBILITY MATTERS (JUL 2013) ......................................... I-22
I.22. 52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED
DOMESTIC CORPORATIONS (DEC 2014) ................................................................ I-23
I.23. 52.214-26 AUDIT AND RECORDS--SEALED BIDDING (OCT 2010) ..................... I-23
I.24. 52.214-27 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR
PRICING DATA--MODIFICATIONS--SEALED BIDDING (AUG 2011) ................. I-24
I.25. 52.214-28 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA
MODIFICATIONS SEALED BIDDING (OCT 2010) .................................................. I-26 I.26. 52.214-29 ORDER OF PRECEDENCE-SEALED BIDDING (JAN 1986) .................. I-27 vi
I.27. 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2014) ............ I-27 I.28. 52.219-14 LIMITATIONS ON SUBCONTRACTING (NOV 2011) ............................ I-29
I.29. 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM
REREPRESENTATION (JUL 2013) ............................................................................. I-30
I.30. 52.219-29 NOTICE OF SET-ASIDE FOR ECONOMICALLY
DISADVANTAGED WOMEN-OWNED SMALL BUSINESS CONCERNS
(JUL 2013) ...................................................................................................................... I-31
I.31. 52.222-3 CONVICT LABOR (JUNE 2003) .................................................................. I-33
I.32. 52.222-4 CONTRACT WORK HOURS AND SAFETY
STANDARDS -OVERTIME COMPENSATION (MAY 2014) ................................... I-34
I.33. 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014) ............ I-35
I.34. 52.222-7 WITHHOLDING OF FUNDS (MAY 2014) .................................................. I-38 I.35. 52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014) ..................................... I-38 I.36. 52.222-9 APPRENTICES AND TRAINEES (JULY 2005) .......................................... I-40
I.37. 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB
1988) ............................................................................................................................... I-41 I.38. 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) ....................... I-41 I.39. 52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014) ................... I-43
I.40. 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE
REQUIREMENTS AND RELATED REGULATIONS (MAY 2014) .......................... I-43
I.41. 52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988) .............. I-43 I.42. 52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014) .................................... I-43 I.43. 52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015).................. I-44 I.44. 52.222-26 EQUAL OPPORTUNITY (APR 2015) ........................................................ I-44
I.45. 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR
CONSTRUCTION (APR 2015) ..................................................................................... I-47 I.46. 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUL 2014) ........................... I-52
I.47. 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES
(JUL 2014) ...................................................................................................................... I-52 I.48. 52.222-37 EMPLOYMENT REPORTS VETERANS (JUL 2014) ............................... I-53
I.49. 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE
NATIONAL LABOR RELATIONS ACT (DEC 2010) ................................................ I-54 I.50. 52.222-50 COMBATING TRAFFICKING IN PERSONS (MAR 2015) ...................... I-55 I.51. 52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (AUG 2013)................. I-62
I.52. 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC
2014) ............................................................................................................................... I-65
I.53. 52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL
SAFETY DATA (JAN 1997) ALTERNATE I (JUL 1995) ........................................... I-70
I.54. 52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW
INFORMATION (MAY 2011)....................................................................................... I-71 I.55. 52.223-6 DRUG-FREE WORKPLACE (MAY 2001) ................................................... I-72 vii
I.56. 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT
MESSAGING WHILE DRIVING (AUG 2011) ............................................................ I-74
I.57. WBR 1452.223-80 ASBESTOS-FREE WARRANTY--BUREAU OF
RECLAMATION (OCT 1992) ....................................................................................... I-75
I.58. WBR 1452.223-81 SAFETY AND HEALTH -- BUREAU OF RECLAMATION
(MAY 2010).................................................................................................................... I-75
I.59. WBR 1452.223-82 PROTECTING FEDERAL EMPLOYEES AND THE
PUBLIC FROM EXPOSURE TO TOBACCO SMOKE IN THE FEDERAL
WORKPLACE–BUREAU OF RECLAMATION (DEC 2009) .................................... I-76
I.60. 52.225-9 BUY AMERICAN-CONSTRUCTION MATERIALS (MAY 2014) ............ I-76
I.61. 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUNE
2008) ............................................................................................................................... I-79 I.62. 52.227-1 AUTHORIZATION AND CONSENT (DEC 2007) ...................................... I-80
I.63. 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND
COPYRIGHT INFRINGEMENT (DEC 2007) .............................................................. I-80
I.64. 52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC
2007) ............................................................................................................................... I-81 I.65. 52.227-17 RIGHTS IN DATA - SPECIAL WORKS (DEC 2007) ................................ I-81 I.66. 52.228-1 BID GUARANTEE (SEP 1996) ..................................................................... I-82 I.67. 52.228-2 ADDITIONAL BOND SECURITY (OCT 1997) ........................................... I-83
I.68. 52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION
(JAN 1997)...................................................................................................................... I-83 I.69. 52.228-11 PLEDGE OF ASSETS (JAN 2012) .............................................................. I-84
I.70. 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS
(MAY 2014).................................................................................................................... I-84 I.71. 52.228-14 IRREVOCABLE LETTER OF CREDIT (DEC 1999) ................................. I-85
I.72. 52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION
(OCT 2010) ..................................................................................................................... I-88
I.73. 1452.228-70 LIABILITY INSURANCE-DEPARTMENT OF THE INTERIOR
(JUL 1996) ...................................................................................................................... I-89
I.74. WBR 1452.228-84 CERTIFICATION OF REPRESENTATIVES FOR
CORPORATE SURETIES--BUREAU OF RECLAMATION (SEP 1996) .................. I-90
I.75. 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) .............................. I-90
I.76. WBR 1452.231-81 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE
-- BUREAU OF RECLAMATION (JUL 1998) ............................................................. I-91
I.77. 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION
CONTRACTS (MAY 2014) ........................................................................................... I-94 I.78. 52.232-17 INTEREST (MAY 2014) .............................................................................. I-97 I.79. 52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014) ................................................. I-98
I.80. 52.232-27 PROMPT PAY FOR CONSTRUCTION CONTRACTS (MAY 2014) ....... I-98
I.81. 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER-SYSTEM FOR
AWARD MANAGEMENT (JUL 2013) ...................................................................... I-107 viii
I.82. 52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS
(JUN 2013).................................................................................................................... I-108
I.83. 52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL
BUSINESS SUBCONTRACTORS (DEC 2013) ......................................................... I-109
I.84. 52.233-1 DISPUTES (MAY 2014) ALTERNATE I (DEC 1991) ............................... I-109 I.85. 52.233-3 PROTEST AFTER AWARD (AUG 1996) ................................................... I-111
I.86. 52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT
2004) ............................................................................................................................. I-112 I.87. 52.236-2 DIFFERING SITE CONDITIONS (APR 1984) ........................................... I-112
I.88. 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE
WORK (APR 1984) ...................................................................................................... I-112 I.89. 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984) ................. I-113 I.90. 52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991) ................................... I-113 I.91. 52.236-8 OTHER CONTRACTS (APR 1984) ............................................................. I-113
I.92. 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES,
EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984) ........................... I-113 I.93. 52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984) ............................. I-114 I.94. 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) ......... I-114 I.95. 52.236-12 CLEANING UP (APR 1984) ...................................................................... I-115
I.96. 52.236-13 ACCIDENT PREVENTION (NOV 1991) - ALTERNATE I (NOV
1991) ............................................................................................................................. I-115
I.97. 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984) ........ I-116
I.98. 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB
1997)- ALTERNATE I (APR 1984)............................................................................. I-117 I.99. 52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995) ................................ I-118
I.100. WBR 1452.236-84 PRESERVATION OF CULTURAL RESOURCES –
BUREAU OF RECLAMATION (FEB 2000) .............................................................. I-118
I.101. WBR 1452.237-80 SECURITY REQUIREMENTS – BUREAU OF
RECLAMATION – ALTERNATE III (FEBRUARY 2011) ....................................... I-120 I.102. 52.242-13 BANKRUPTCY (JUL 1995)....................................................................... I-128 I.103. 52.243-4 CHANGES (JUNE 2007) .............................................................................. I-128
I.104. WBR 1452.243-80 MODIFICATION PROPOSALS -- BUREAU OF
RECLAMATION (DEC 2001) ALTERNATE III (JUL 1998) .................................... I-129 I.105. 52.244-2 SUBCONTRACTS (OCT 2010) ................................................................... I-130 I.106. 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (APR 2015) ................. I-133
I.107. 52.248-3 VALUE ENGINEERING—CONSTRUCTION (OCT 2010) -
ALTERNATE I (APR 1984) ........................................................................................ I-134
I.108. 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT
(FIXED-PRICE) (APR 2012)-ALTERNATE I (SEP 1996) ........................................ I-137 I.109. 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)................... I-141 I.110. 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984) ........................ I-142 I.111. 52.253-1 COMPUTER GENERATED FORMS (JAN 1991) ...................................... I-142 ix
PART III LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J LIST OF ATTACHMENTS ......................................................................................... J-1
PART IV REPRESENTATIONS AND INSTRUCTIONS
SECTION K REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS
OF OFFERORS OR RESPONDENTS ....................................................................... K-1
K.1. 52.203-98, PROHIBITION ON CONTRACTING WITH ENTITIES THAT
REQUIRE CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS—
REPRESENTATION (FEB 2015) - DEVIATION ........................................................ K-1
K.2. 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (DEC
2014) ............................................................................................................................... K-1
K.3. 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL
2013) ............................................................................................................................... K-5
SECTION L INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR
RESPONDENTS ............................................................................................................L-1
L.1. 52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE
REPORTING (NOV 2014) .............................................................................................. L-1
L.2. 52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE
MAINTENANCE (NOV 2014) ....................................................................................... L-2
L.3. 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA
INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND
COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) ............. L-3
L.4. 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA
INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND
COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) .................................................. L-3
L.5. 52.211-6 BRAND NAME OR EQUAL (AUG 1999) (DEVIATION) ........................... L-3
L.6. WBR 1452.211-80 NOTICE OF INTENT TO ACQUIRE METRIC PRODUCTS
AND SERVICES - BUREAU OF RECLAMATION (MAR 1993) ............................... L-4 L.7. 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 1989) ...................... L-5 L.8. 52.214-4 FALSE STATEMENTS IN BIDS (APR 1984) ............................................... L-5 L.9. 52.214-5 SUBMISSION OF BIDS (MAR 1997) ............................................................ L-5 L.10. 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984) ...................... L-6
L.11. 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS
OF BIDS (NOV 1999) ..................................................................................................... L-6 L.12. 52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984) ...................... L-7
L.13. 52.214-19 CONTRACT AWARD-SEALED BIDDING--CONSTRUCTION
(AUG 1996) ..................................................................................................................... L-7
L.14. 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR
1991) ................................................................................................................................ L-8 L.15. 52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991) .................. L-8 x
L.16. FACSIMILE ACKNOWLEDGMENT OF AMENDMENTS, MODIFICATIONS
TO OFFERS, AND WITHDRAWALS OF OFFERS-BUREAU OF
RECLAMATION--PN REGION (APR 2007) ................................................................ L-8
L.17. 52.216-1 TYPE OF CONTRACT (APR 1984) ............................................................... L-9
L.18. 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY
SITE OF THE WORK (MAY 2014) ............................................................................... L-9
L.19. 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO
ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION
(FEB 1999)....................................................................................................................... L-9
L.20. NON-DISCRIMINATION NOTICE TO U.S. DEPARTMENT OF THE
INTERIOR CONTRACTORS, SUBCONTRACTORS, AND LESSORS --
BUREAU OF RECLAMATION -- PN REGION (JAN 2000) ..................................... L-11
L.21. 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—
CONSTRUCTION MATERIALS (MAY 2014) ........................................................... L-11
L.22. 52.233-2 SERVICE OF PROTEST – DEPARTMENT OF THE INTERIOR
(SEPT 2006) (DEVIATION) ......................................................................................... L-12
L.23. 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB
1995) .............................................................................................................................. L-12
L.24. 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984) ................... L-13
SECTION M EVALUATION FACTORS FOR AWARD .............................................................. M-1
M.1. WBR 1452.225-82 NOTICE OF WORLD TRADE ORGANIZATION
GOVERNMENT PROCUREMENT AGREEMENT EVALUATIONS--
BUREAU OF RECLAMATION (MAY 2005) .............................................................. M-1
M.2. PRICE REASONABLENESS DETERMINATION (MAY 2010) ................................ M-1
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Pacific Northwest Region
Regional Office Acquisition Management Division
R10
1150 N. Curtis Road, Ste. 100
Boise ID 83706-1234
Bureau of Reclamation
Attn: Contracting Officer, PN-3726 1150 N. Curtis Road, Suite 100 Boise, ID 83706-1234
Susan Kramer 208-378-5156 x
05/13/2015
R15PS00313
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
HUNGRY HORSE VISITOR AREAS AND PARKING LOT IMPROVEMENTS, HUNGRY HORSE PROJECT,
MONTANA
THIS SOLICITATION IS SET-ASIDE FOR ECONOMICALLY DISADVANTAGED WOMEN-OWNED SMALL
BUSINESS CONCERNS
THE ESTIMATED PRICE RANGE OF THE WORK IS $1,000,000 TO $5,000,000
NOTE: The period of performance in Block 11 below is estimated. Due to system limitations a contract completion date cannot be entered in this field. The actual required contract completion date is August 1, 2016, as stated in Clause F.1. of the solicitation. In addition, onsite work cannot begin until April 1, 2016, as stated in Clause F.1. of the solicitation.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 365 calendar days and complete it within ________________ ________________ calendar days after receiving
Clause F.1.
06/24/2015
NSN 7540-01-155-3212
x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Pacific Northwest Region
Regional Office Acquisition Management Division
R10
1150 N. Curtis Road, Ste. 100
Boise ID 83706-1234
Susan E. Kramer
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R15PS00313
SECTION B
(a) Offers will be considered for award on the following schedule, but no offer will be considered for award on only a part of the schedule.
(b) All offers are subject to the terms and conditions of this solicitation.
(c) The quantity in CLIN 00020 is estimated for comparison of bids only, and except as provided in contract clause 52.211-18, Variation in
Estimated Quantity, no claim shall be made against the Government for overruns or underruns.
(d) Definitions:
(1) CLIN - Contract Line Item Number
(2) AU - Activity Unit (equals Lump Sum)
(3) CD - Cubic Yard
FOB: Destination
00010 Hungry Horse Visitor Areas and Parking Lot 1 AU
Improvements
00020 Excavating asphalt surface (specification section 213 CD
31 23 30)
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
C-1
SECTION C DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
DIVISION 01 - GENERAL REQUIREMENTS
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located approximately 20 miles northeast of Kalispell, Montana, and 9 miles southeast of Columbia Falls, Montana, in Flathead County.
1.02 PRINCIPAL COMPONENTS OF WORK
A. The principal components of work to be performed include the following:
1. Visitors Center Overlook Area:
a. Removing the Visitors Center Overlook roof, and furnishing and installing a new Visitors Center Overlook roof, to include:
1) Reroute existing conduits, remove and replace lighting, and remove and replace light pole bases.
2) Removing existing fascia and gutter and furnishing and installing new fascia and gutters.
3) Removing existing roof and ceiling metal decking and furnishing and installing new metal roof and ceiling metal decking.
4) Removing existing red lead paint and preparing and repainting the existing steel frame
5) Furnishing and installing new tapered insulation, a new cover board, a new roof, new flashing and a new gutter.
b. Constructing a van accessible parking space in front of the Visitors Center Overlook, to include:
1) Saw cutting, removing, and disposing of existing asphalt and concrete curbing.
2) Excavating and placing concrete pavement for accessible parking.
3) Excavating and placing concrete for curb ramp.
4) Furnishing and placing van accessible signage and post.
5) Placing access aisle stripes, parking stripes and accessibility pavement markings.
6) Furnishing and placing precast concrete wheel stop.
c. Furnishing and placing new electrical conduit from the Main Visitors
Center to the Visitors Center Overlook, to include:
01 11 00 - 2
1) Removing, and disposing of existing conduit.
2) Furnishing and installing conduit runs and conductors.
3) Backfilling areas disturbed by excavation for electrical conduit.
d. Furnishing and placing a concrete walkway with curb between the Visitors Center Overlook and the Main Visitor’s Center which includes:
1) Saw cutting, removing, and disposing of existing asphalt and concrete curb.
2) Excavating for concrete for walkway/curb and gutter.
3) Grading for concrete walkway/curb.
4) Placing concrete for walkway/curb.
e. Removing existing chain link fencing between Visitors Center Overlook and Main Visitor’s Center and replace with new chain link fence. Work includes:
1) Removing and disposing of existing chain link fence.
2) Furnishing and installing new chain link fence. Fence to be mounted to outside of walkway.
3) Removing and replacing street lights and post between Visitor’s Center Overlook and Main Visitor’s Center.
f. Removing existing chain link fence between Visitors Center Overlook to approximately 280 feet west of the Visitors Center Overlook.
1) Removing and disposing of existing chain link fence.
2) Furnishing and installing new chain link fence. Fence to be mounted in ground as shown in typical section drawing 40-D- 6268.
3) Remove and replace street light just west of the Visitor Center Overlook.
2. Main Visitor’s Center Area:
a. Constructing a van accessible parking space with access aisle in front of the Main Visitors Center, which includes:
1) Saw cutting, removing, and disposing of existing asphalt parking area.
2) Excavating and placing concrete pavement for accessible parking area.
3) Furnishing and placing van accessible signage and post.
01 11 00 - 3
4) Placing access aisle stripes and accessibility pavement markings.
5) Furnishing and placing precast concrete wheel stop.
b. Removing existing concrete curb ramp in front of main Visitor’s Center and replacing it with a new concrete walkway which includes:
1) Saw cutting, removing, and disposing of existing concrete curb ramp.
2) Excavating and placing concrete pavement for new walkway.
c. Removing existing asphalt curb ramp east of Main Visitor’s Center and replacing with concrete stairs:
1) Saw cutting, removing, and disposing of existing asphalt curb ramp.
2) Removing and disposing of existing handrail.
3) Excavating and placing concrete pavement for new stairs.
4) Installing topsoil, landscape fabric, and rock.
5) Furnishing and installing handrails for stairs.
d. Improvements to parking area in front of Main Visitor’s Center which includes:
1) Saw cutting, removing, and disposing of portions of existing curb and gutters as shown on drawings.
2) Excavating and placing concrete curb and gutters.
3) Furnishing and placing grating for catch basin.
4) Clean asphalt parking area, apply seal coats and stripe parking spaces.
e. Removing existing portions of existing concrete slab and replace with new concrete slab as shown on drawings. Approximately 940 square feet:
1) Saw cutting, removing, and disposing of existing 5” concrete slab with reinforced wire fabric.
2) Furnish and replace with reinforced concrete pad. New pad to meet ADA-ABAAG slope standards and joints between new and
01 11 00 - 4 existing concrete walkways and pad shall be less than ¼” in height and less than ½” in width.
f. Saw cutting parapet wall in back of Main Visitor’s Center and installing viewing window to be accessible to all visitors. Work includes:
1) Saw cutting, removing, and disposing of portions of existing concrete parapet wall.
2) Furnishing and installing aluminum glass panel railing with clear tempered glass.
g. Improvements to parking area on the west side of the Main Visitor’s Center which includes:
1) Saw cutting concrete for catch basin, furnishing and installing drain grating.
h. Saw cutting parapet wall in front of spillway and installing viewing window to be accessible to all visitors, and saw cutting concrete walkway in front of parapet and constructing viewing area overlooking spillway to be accessible to all visitors Work includes:
1) Saw cutting, removing, and disposing of portions of existing concrete parapet wall.
2) Furnishing and installing aluminum glass panel railing with clear tempered glass.
3) Saw cutting, removing, and disposing of portions of existing walkway.
4) Excavating and placing concrete view pad.
5) Furnishing and installing handrails around viewing pad.
j. Remove and replace soffit lighting on outside of Visitor’s Center.
4. Top of Dam:
a. Furnishing and installing pavement markings on roadway crossing the dam.
5South Parking and Reservoir Overlook Area:
a. Constructing a van accessible parking space in front of the north side of parking Area. Work includes:
1) Furnishing and placing van accessible signage and post.
01 11 00 - 5
2) Placing access aisle stripes and accessibility pavement markings.
3) Furnishing and placing precast concrete wheel stop.
b. Constructing an accessible viewing and picnic pad area adjacent to north side of parking area. Work includes:
1) Earthwork for, and furnishing and placing a concrete picnic pad and viewing pad.
2) Earthwork for, and furnishing and placing a concrete walkway 5-foot wide, 4-inch thick cast-in-place concrete walkway.
3) Saw cutting, removing, and disposing of existing asphalt.
4) Furnishing and placing metal handrails.
5) Furnishing and installing concrete curb ramp to meet ADA- ABAAG standards.
6) Furnishing and installing picnic table to meet current ADA- ABAAAG standards.
7) Furnishing and installing handrails and guard rails.
8) Placing striping for 17 standard parking stalls.
c. Saw cutting, removing, and disposing of existing asphalt, rock excavation and compacted gravel backfill, furnish and install a 1500 gallon septic tank, grading and installing base coarse, and asphaltic concrete pavement for South Parking Area.
1) Slope as shown on drawings.
2) New 2-inch Hot Mix Asphalt (HMA).
3) New 1 ½-inch HMA overlay.
d. Furnish and place new concrete slab at tight turning radius of the south abutment.
e. Furnish and install storm drains as shown on drawings.
4. Removing and replacing all street lighting in all parking areas.
5. Installing No Parking signs.
01 11 00 - 6
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, the words “shall be” are included by inference where a colon (:) is used within the sentence or phrase.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time the solicitation was issued.
B. Quality Assurance: Inspection and tests performed by Government to ensure compliance with the terms of the contract.
C. Quality Control: Activities performed by Contractor to ensure work conforms to contract requirements.
D. Contractor Quality Testing: Specified tests to be performed by the Contractor.
1. The Government may use the test results for Quality Assurance.
2. The Contractor may use the test results as part of Contractor quality control.
a. The Government anticipates that these tests will be part of the Contractor’s quality control program; however the tests do not relieve the Contractor of providing adequate quality control measures in accordance with the clause at FAR 52.246-12, “Inspection of Construction.”
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer
2. COR: Contracting Officer’s Representative
3. CM: Contract Modification
PART 2 PRODUCTS
Not Used
01 11 00 - 7
PART 3 EXECUTION
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 COST
A. Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. USBR Cleaning Manual Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2010 Edition - Available online at: http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals:
1. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
a. For each Contractor use site on Government land.
1) Show use location and extent of impact. Uses include but are not limited to the following:
a) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
b) Parking areas, temporary roads, and haul routes.
c) Utilities including air, power, and water lines; fire hydrants;
and compressor station.
d) First-aid and medical facilities.
e) Areas for processing, storing, and disposing of waste materials from construction operations.
f) Temporary fences.
2) Describe methods to preserve, protect, and repair if damaged, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not interfere with the work required under this http://www.usbr.gov/mussels/prevention
01 14 10 - 2 contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
3) Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
4) Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
b. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. Government land as shown on drawings may be used for required construction facilities.
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by the COR.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment: Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
B. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in USBR Cleaning Manual.
C. The COR will inspect construction equipment following procedures described in USBR Cleaning Manual before allowing the equipment onsite.
01 14 10 - 3
3.02 RESTORATION
A. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
Payment Procedures
01 29 00 - 1
SECTION 01 29 00
PAYMENT PROCEDURES
PART 1 GENERAL
1.01 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals:
1. RSN 01 29 00-1, Schedule of Values.
2. RSN 01 29 00-2, Application for Payment.
1.02 SCHEDULE OF VALUES
A. Prepare a separate Schedule of Values for each schedule of the Work under the Contract.
B. Upon request of COR, provide documentation to support the accuracy of the Schedule of values.
C. Lump Sum Work:
1. Reflect specified allowances and alternates, as applicable.
2. List bonds and insurance premiums, mobilization, demobilization, preliminary and detailed progress schedule preparation, equipment testing, facility startup, and contract closeout separately.
D. An unbalanced or front-end loaded schedule will not be acceptable.
E. Summation of the complete Schedule of Values…