Questions _ RFP 2025_09 Walker County Mowing.pdf
PDF 58 KB Posted
- Solicitation number
- PE-74600-NONST-2026-000000015
- Issued by
- Wilcox County, Georgia
About this file
This document is a questions and answers file for RFP 2025-09, a Walker County mowing, litter pick-up, and weed control contractor solicitation. The project requires four cutting cycles per year with seven weeks allowed to complete each cycle, with a preferred start date of April. The scope of work includes mowing services, litter removal before and after mowing operations, Johnson grass spraying three times per year, and weed eating around signs, phone pedestals, fire hydrants, and guardrails during each cycle. Approximately 60% of roads will require boom mower equipment for trimming woodlines and overhead growth to maintain a 15-foot clearance from the roadway. The contractor must maintain cutting consistency across all cycles, trim behind and in front of guardrails, and maintain areas behind mailboxes and other road obstacles.
The contractor is responsible for all trash disposal, including obtaining a fee waiver at the landfill for dumping accumulated litter, as the county will not provide a dumpster. Spot picking of litter must occur after initial mowing passes to address debris left during the original collection. The contractor must maintain uniform cuts and clear all limbs, growth, and obstructions from woodlines, fence rows, and overhead areas throughout the contract term to ensure roadway safety and accessibility.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 2025_009 Cancelled.docx | DOCX document | |
| RFP 2025_09_3 Walker County Mowing_ Litter Pi.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP 2025-09 Walker County Mowing, Litter Pick-up and Weed Control
Contractor questions and answers.
1.How many cuts per year 3 or 4? 4 rounds per year
2. How many times to spray each year to target Johnson Grass? 3 times per year
3. How many days do you allow to complete a cycle? 7 Weeks per cycle
4. Will there be a dumpster provided for litter? No, the contractor will be responsible for disposal for all of the trash accumulated.
5. Does the county have a preference for the month in which we should start? If so, which month is preferred? Yes, preference is to start in the month of April.
6. Does litter need to be picked up before and after mowing or just before mowers come through the areas? Before and after needs to be spot picked for the stuff that is left during the original pick up.
7. Do the limbs on woodlines need trimmed and if so, how high? Yes, contractor is to maintain a good trim around 15 feet high off of the road with boom mower trimming.
8. Will there be a fee waiver available at the landfill for them to dump the litter? Yes, that can be arranged.
9. Do we need to mow behind guardrails or just in the front of them? Behind and in front of guardrails is to be maintained as well as behind mailboxes and other road obstacles.
10. What percentage of roads will require Boom mowers? Approximately 60%
11. Will we need to cut back every cycle or start with a one pass cycle and each cycle cut further back? Contractor will need to maintain a good cut back every cycle and keep it uniform with no limbs or growth from woodlines, fence rows, and overhead in obstruction of the roadway.
12. What all needs to be weedeated and maintained around? All signs, phone pedestals, fire hydrants, and guardrails need to be weedeated every cycle.