About this file

This is a Questions & Answers Addendum issued by the Florida Fish and Wildlife Conservation Commission (FWC) Procurement Office in response to Solicitation No. FWC 25/26-90 for a Tosohatchee WMA Chemical Storage Building. The addendum addresses three key inquiries from prospective bidders regarding project feasibility and scope clarification. In response to concerns about meeting the original June 15, 2026 completion deadline, FWC has extended the target completion date to August 28, 2026, while still accepting bids with revised timelines. The scope of work includes furnishing and delivering the chemical storage structure with placement at the site; however, electrical connections to power sources will be arranged separately by FWC and are not the responsibility of the contractor. The sealed bid submission deadline remains 3:00 PM Eastern Time on Thursday, April 9, 2026, with public bid opening on the same date. Bid protests must be filed within the timeframe specified in Section 120.57(3), Florida Statutes, with the Purchasing Office located at 1875 Orange Avenue East, Tallahassee, Florida 32311-6160.

FWC clarified that no specific manufacturer or product serves as the basis for design; instead, bidders must submit proposals for buildings that meet or exceed the outlined specifications, ratings, and certifications developed in accordance with herbicide storage requirements and applicable local, state, and federal codes and regulations. The addendum does not disclose pricing information, set-asides, or incumbent vendor details. Bidders should note that the typical lead time for such structures is approximately 24 weeks, comprising 2-4 weeks for custom drawing creation and 18-20 weeks for production, with FWC's acceptance of the extended August 28, 2026 completion date intended to accommodate this manufacturing timeline.

View the file

Other files

File Type Posted
FWC.25.26.90 ITB Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Fish and Wildlife Conservation Commission

Commissioners

Rodney Barreto

Chairman

Coral Gables

Steven Hudson

Vice Chairman

Fort Lauderdale

Preston Farrior

Tampa

Joshua Kellam

Palm Beach Gardens

Gary Lester

Oxford

Albert Maury

Coral Gables

Sonya Rood

St. Augustine

Office of the

Executive Director

Roger A. Young

Executive Director

Charles “Rett” Boyd

Assistant Executive Director

George Warthen

Chief Conservation Officer

Jessica Crawford

Chief of Staff

850-487-3796

850-921-5786 FAX

Managing fish and wildlife resources for their long-term well-being and the benefit of people.

620 South Meridian Street

Tallahassee, Florida

32399-1600

Voice: 850-488-4676

Hearing/speech-impaired:

800-955-8771 (T)

800-955-8770 (V)

MyFWC.com

DATE: APRIL 2, 2026

ADDENDUM NO.: 1

BID NO.: FWC 25/26-90

BID TITLE: TOSOHATCHEE WMA - CHEMICAL STORAGE BUILDING

UPDATE: QUESTIONS & ANSWERS

The enclosed addendum has been issued for consideration in the preparation of your response to the Florida Fish and Wildlife Conservation Commission’s

(FWC) Solicitation No. FWC 25/26-90, “Tosohatchee WMA - Chemical Storage

Building”.

All responses to the subject solicitation must be received no later than 3:00

PM (ET) on Thursday, April 9, 2026.

A response received after the exact time specified will not be considered.

Failure to file a protest within the time prescribed in Section 120.57(3), Florida Statutes (F.S.), or failure to post the bond or other security required by law within the time allowed for filing a bond shall constitute a waiver of proceedings under Chapter 120, Florida Statutes. Written notices, formal requests and proceedings must conform with the requirements set forth in

Chapter 28-110, Florida Administrative Code (F.A.C.). Protests must be filed with the Purchasing Office, Fish and Wildlife Conservation Commission, 1875

Orange Avenue East, Tallahassee, Florida 32311-6160 within the time prescribed in Section 120.57(3), F.S. and Chapter 28-110, F.A.C.

Sincerely, Randy Golightly

FWC Procurement Manager

FWC SOLICITATION ADDENDUM 2

BEGIN ADDENDUM

QUESTION #1

The lead time for this building is approximately 24 weeks. 2-4 weeks are needed for creating custom drawings and another 18-20 weeks are needed for production. We are unable to meet your completion date of 6/15/2026. Please advise if you are still accepting bids if this date cannot be met.

ANSWER #1

We will accept bids with a target completion date of 8/28/2026. Submit bid with target completion date.

QUESTION #2

Is this solely a furnish & deliver? Or is installation to be included?

ANSWER #2

The scope specifies delivery and placement of the structure. Connection of electrical components to a power source is not specified in the scope. FWC will arrange electrical connections to power.

QUESTION #3

Is there a product / manufacturer used as a basis for design?

ANSWER #3

No specific product or manufacturer is identified as a basis for design. The building must meet or exceed the outlined specifications, ratings, and certifications. The specifications have been developed in accordance with herbicide storage requirements and applicable local, state, and federal codes and regulations.