Questions and Answers for W9124C20R0013
Electrical Support System
1. Question: Do you have a list of companies that will be bidding on this project?
Answers: The Government is not able to discuss other parties bidding on this project.
2. Question: I see that they have to have a Minority business on it as so.
Answers: Yes this is correct.
3. Question: I have read the solicitation and I did not find any site visit date for this project, will there be a site visit?
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) To be determined at the Task Order Level
Answers: There will be no site visits for this solicitation. Site visits will be determined at the award of Task Order Level.