Questions and Answers_response.pdf
PDF 97 KB Posted
- Attached to
- Tilt Monitoring Systems and Accessories
- Solicitation number
- RFQ 591 200000000315 3
- Issued by
- Wayne County, Detroit City, Michigan
About this file
This is a Questions and Answers document from the Michigan Department of Transportation (MDOT) regarding Request for Quote Number 200000000315 for a Tilt Monitoring System and Accessories. The project involves monitoring three sites with a total of six tiltmeters, configured at two tiltmeters per location. MDOT will be responsible for the installation, commissioning, and maintenance of the system upon delivery. Vendors are required to note the soonest available delivery time in their RFQ responses. The document clarifies that multiple dataloggers are permissible, as tiltmeter cables do not need to be consolidated to a single location.
Technical assistance will be provided by the vendor, with pricing to be structured either as a per-hour cost or included in the equipment purchase price. The document does not specify response deadlines, contract award dates, or contract term details, focusing instead on clarifying the system configuration and installation responsibilities to ensure bidders submit accurate and complete quotes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Request for Quote Worksheet_ Form 2654.pdf | ||
| Specifications-Tilt Monitoring System.pdf | ||
| Quote Instructions.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Michigan Department of Transportation Request for Quote Number 200000000315
Tilt Monitoring System and Accessories Questions and Answers
Question #1: Do services for installation and commissioning of the system need to be included in the quote
Answer#1: MDOT will install and maintain the system. Note how technical assistance will be provided to
MDOT. Will it be a per hour cost or is it included in purchase of equipment.
Question #2: What is the delivery time frame required, after contract begin date?
Answer#2: Please note soonest delivery time available in RFQ response.
Question #3: Are all 6 tiltmeters required to have their cables run to a single location for a single datalogger or can there be a datalogger at each location?
Answer#3: Two tiltmeters per location are required.
Question #4: The RFQ calls for 3 sites to be monitored, then the Specification calls for 6 tilt meters. Is the configuration anticipated to be 2 tilt meters per location or is there another configuration required?
Answer#4: Two tiltmeters per location are required.