Questions and Answers for ITB 22-23-37.pdf

PDF 112 KB Posted

Attached to
Painting Orlando CSP Service Center
Solicitation number
ITB-04840
Issued by
Orange County, Orlando City, Florida

About this file

This document is a Question and Answer submission regarding an Invitation to Bid (ITB) issued by the Florida Department of Revenue for a painting project at the Child Support Service Center in Orlando, Florida. The purpose of the ITB is to secure competitive bids from qualified vendors to prep and paint all interior rooms spanning approximately 28,457 square feet across the 1st, 5th, and 6th floors of the facility. The questions and answers cover requirements such as licensing, prequalification information, and acknowledgement of addenda. The ITB timeline includes a mandatory site visit and bid submission deadlines.

The ITB does not provide details on pricing terms, set asides, incumbents, funding requirements and sources, or other financial considerations. It focuses primarily on the project scope, bidder qualifications, and administrative requirements.

View the file

Other files

File Type Posted
ITB 22-23-37 Final.pdf PDF
Addendum Acknowledgement Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DOR TEMPLATE for VENDOR SOLICITATION QUESTIONS SUBMISSION

# QUESTION

Applicable to which section?

(Solicitation Page Number and Paragraph)

DEPARTMENT's RESPONSE/ANSWER

Based on the size and complexity of this project, I assume that the Prime contractor(Painting contractor) Needs to have the General contractor License in order to meet the Qualified requirements?

4.2.13.1

All entities defined under Chapters 607, 608, 617, 620, 621 or 622, Florida Statutes, seeking to do business with the Department shall be properly licensed and in good standing with the Florida Department of State and all applicable regulatory agencies.

Please provide the prequalification information needed to be able to bid on this project.

4.2.13 Please refer to section 4.2.13 - 4.2.15 of the Invitation to Bid

Do we need to complete the Addenda Acknowledgement Form Addendum #1 and send it to your email in order to be able to assist to the mandatory site visit or just include it in the BID Package proposal?

Addendum #1 This Addendum now becomes part of the original ITB. Acknowledge receipt of this addendum in the space provided on the bid form. Failure to do so may subject the bidder to disqualification.

VENDOR NAME:

(Vendor Name will be removed for final Q & A's posted to VIP)

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Questions will only be accepted up to the date and time specified in the solicitation Timeline of Events. The Q A's will be posted on the Vendor Bid System on date specified in Timeline

Sheet1

File details come from the government source that posted it. Updated .