This is a Question and Answer document for RFB #19-BM08, City Hall Entrance Door Replacement, issued by the City of Wisconsin. The project scope encompasses the replacement of the outer entry/exit doors to the main lobby at City Hall along the north side of the building, including doors, windows, framing, threshold, and associated hardware. The work also includes replacement of door hardware on eight additional entry/exit doors within the building with Von Duprin rim exit devices or equivalent panic bar hardware. All entry/exit work must be coordinated with the City's Information Technology Department to ensure integration with the building's security system.
The project budget is established at $47,000. No additional details regarding response dates, due dates, site visits, bidder conferences, award dates, or contract terms are provided in this question and answer document. The document does not contain information regarding pricing terms, set asides, incumbents, funding sources, or other salient contract conditions beyond the budget allocation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFB 19-BM08 - Draft Contract.pdf | ||
| RFB19-BM08 Entry Door Replacement 7-18-19.pdf | ||
| OFFICIAL NOTICE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
g:\finance\forms\contracts and rfp templates\2019 bm rfbs, rfps\rfb#19-bm08 - city hall entry door replacement\question and answers.docx
City Hall Entrance Door Replacement RFP Question and Answer
RFB: 19-BM08
Question 1: What is the budget for this project?
Answer: The budget is $47,000.