Question and Answers
1. How old is the preambles at location 2095 Bitar Ave?
Answer: - about 8 years
2. What is the performance standard of the pavement cleaning vehicle?
Answer: Some sort of vac truck that can lay down water and suck it back up. The equipment used will need to be approved the government.
3. Is there any requirement to work weekends or nights?
Answer: - no
4. My question is for the road striping/ maintenance contract listed above, what percentage of the job has to be self-performed? I have a subcontractor I have utilized on another road project however, I was simply oversight.
Answer: According to the US small business administration for general construction contracts the small business prime contractor must perform at least 15% of the cost of the contract with its own employees, not including the cost of material. https://www.sba.gov/node/1504180 https://www.sba.gov/node/1504180