This is a Quality Assurance Surveillance Plan (QASP) for Local National Health Surveillance Services Occupational Health & Safety Program at Aviano Air Base, Italy under solicitation FA568225Q0004. The QASP establishes procedures for monitoring contractor performance across key areas including administration, key personnel, medical examinations, clinical tests, risk assessment, and reporting. Performance thresholds are defined with specific compliance requirements, such as no more than 3-5 occurrences of non-compliance for most measures, and 100% compliance requirements for key personnel qualifications and service continuity.
The document outlines roles and responsibilities for program oversight, including the Program Manager, Contracting Officer (TSgt Joshua Largent), COR (Capt Lucas Lemoine), and Contract Administrator (Ms. Resi Santin). It includes detailed procedures for performance monitoring, reporting methods, and corrective action processes through tools like Corrective Action Reports (CARs), Customer Complaint Records, and Performance Assessment Reports (PARs). Performance ratings range from Excellent/Outstanding to Unsatisfactory based on defined criteria measuring the contractor's adherence to contractual requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan (QASP) for
LOCAL NATIONAL HEALTH SURVEILLANCE SERVICES
OCCUPATIONAL HEALTH & SAFETY PROGRAM
AVIANO AIR BASE, ITALY
Solicitation #FA568225Q0004
20 February 2025
THIS PAGE IS NOT USED.
Table of Contents
| 1.0 | Purpose | 3 |
| 2.0 | Authority | 3 |
| 3.0 | Roles and Responsibilities | 3 |
| 4.0 | Performance Requirements and Method of Surveillance | 5 |
| 4.1 | Contract Surveillance | 5 |
| 4.2 | Surveillance Matrix | 5 |
| 5.0 | Performance Rating Definitions | 6 |
| 6.0 | Performance Reporting | 7 |
| 6.1 | Corrective Action Report (CAR) | 8 |
| 6.2 | Customer Complaint Record | 9 |
| 6.3 | Performance Assessment Report (PAR) | 10 |
| 7.0 | Surveillance Matrix for Title of Contractor | 11 |
1.0 Purpose
a. This Quality Assurance Surveillance Plan is a government-developed document used to determine if the contractor’s performance meets the performance standards contained in the contract. The QASP establishes procedures on how this assessment/inspection process will be conducted. It provides the detailed process for a continuous oversight process:
· What will be monitored
· How monitoring will take place
· Who will conduct the monitoring
· How monitoring efforts and results will be documented
b. The contractor is responsible for implementing and delivering performance that meets contract standards using its Quality Control Plan. The QASP provides the structure for the government’s surveillance of the contractor’s performance to assure that it meets contract standards. It is the government’s responsibility to be objective, fair, and consistent in evaluating contractor performance.
c. The QASP is not part of the contract nor is it intended to duplicate the contractor’s quality control plan. This QASP is a living document. Flexibility in the QASP is required to allow for an increase or decrease in the level of surveillance necessary based on contractor performance.
d. The government may provide a copy of the QASP to the contractor to facilitate open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor.
e. Bottom line--the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.
2.0 Authority
Authority for issuance of this QASP is provided under Part 46 of the Federal Acquisition Regulation, Inspection of Services clauses, which provide for inspection, acceptance and documentation of the service called for in the contract or order. This acceptance is to be executed by the contracting officer or a duly authorized representative.
3.0 Roles and Responsibilities
The following personnel shall oversee and coordinate surveillance activities.
a. Program/Project Manager (PM). The PM provides primary program oversight, nominates the COR, ensures the COR is trained before performing any COR duties and supports the COR’s performance assessment activities. While the PM may serve as a direct conduit to provide Government guidance and feedback to the Contractor on technical matters, they are not empowered to make any contractual commitments or any contract changes on the government’s behalf.
Assigned PM:
Organization or Agency:
Telephone:
Email:
b. Contracting Officer (CO). The CO shall ensure performance of all necessary actions for effective contracting, ensure compliance with the contract terms, and shall safeguard the interests of the United States in the contractual relationship. The CO shall also ensure that the contractor receives impartial, fair, and equitable treatment under this contract. Determine the final assessment of the contractor’s performance.
Assigned CO: TSgt Joshua Largent Organization or Agency: 31 CONS/PKBX Telephone: 314-632-7952 Email: joshua.largent@us.af.mil
c. Contracting Officer’s Representative (COR). The COR is responsible for providing continuous technical oversight of the contractor’s performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor’s actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the CO. The COR is required to provide an annual performance assessment to the CO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government’s behalf.
Primary COR: Capt Lucas Lemoine Organization or Agency: 31 FW/A1 Telephone: 314-632-5302 Email: lucas.lemoine@us.af.mil
d. Other Key Government Personnel. This may include performance monitors, inspectors, technical experts, or others who provide information that helps the COR monitor contractor performance.
Contract Administrator
Assigned CA: Ms. Resi Santin Organization or Agency:
Telephone: 314-632-7125 Email: resi.santin.it@us.af.mil
Contractor Representatives
The following employees of the contractor serve as the contractor’s Program Manager and Task Manager for this contract. (Complete this section after the contract award) Program Manager: to be named Telephone:
Email:
Other Key Contract Personnel – to be named Title:
Telephone:
Email:
4.0 Performance Requirements and Method of Surveillance
4.1 Contract Surveillance
The goal of the QASP is to ensure that contractor performance is effectively monitored and documented. The COR’s contribution is their professional, non-adversarial relationships with the CO, PM, and the contractor, which enables positive, open, and timely communications. The foundation of this relationship is built upon objective, fair, and consistent COR evaluations of contractor performance against contract requirements. The COR uses the methods contained in this QASP to ensure the contractor is following contract requirements. The COR function is responsible for a wide range of surveillance requirements that effectively measure and evaluate the contractor’s performance. Additionally, this QASP is based on the premise that the contractor, not the government, is responsible for management and QC/QA actions to successfully meet the terms of the contract.
4.2 Surveillance Matrix
a. The Surveillance Matrix (Appendix 1 & 2) is the list of performance objectives and standards that must be performed by the contractor. This matrix details the method of surveillance the COR will use to validate and inspect these performance elements. Inspection of each element will be documented in the COR file.
b. Performance objectives define the desired outcomes. Performance Standards define the level of service required under the contract to successfully meet the performance objective. The inspection methodology defines how, when, and what will be assessed in measuring performance. The Government performs surveillance, using this QASP, to determine the quality of the contractor’s performance as it relates to the performance element standards. The Service Summary (SS) should be used to form the foundation of the COR’s inspection checklist.
5.0 Performance Rating Definitions
In evaluating the quality of contractor’s performance, the following performance ratings may be used.
| Performance Rating |
| Criteria |
| Excellent / Outstanding |
| Performance meets contractual requirements and exceeds many to the government’s benefits. The contractual performance of the element or sub-element being assessed was accomplished with no problems and |
contractor actions were highly effective.
| Very Good |
| Performance meets contractual requirements and exceeds some to the government benefits. The contractual performance was accomplished with few minor problems for which corrective actions taken by the |
contractor were effective.
| Good |
| Performance meets contractual requirements. The contractual |
performance contains some minor problems for which corrective actions taken by the contractor were satisfactory.
| Marginal |
| Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s |
proposed actions appear marginally effective or were not fully implemented.
| Unsatisfactory |
| Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or |
were ineffective.
6.0 Performance Reporting
The below documents are located on the following pages.
6.1 CORRECTIVE ACTION REPORT (CAR)
Adobe Acrobat Document
6.2 CUSTOMER COMPLAINT RECORD (CCR)
Adobe Acrobat Document
6.3 PERFORMANCE ASSESSMENT REPORT (PAR)
Adobe Acrobat Document
6.1 Corrective Action Report (CAR)
Describes how discrepancies are reported and resolved.
CORRECTIVE ACTION REPORT (CAR)
(If more space is needed, use reverse and identify by number)
| 1. CONTRACTOR |
| 2. CONTRACT NUMBER |
| 3. TYPE OF SERVICES |
| 4. FUNCTIONAL AREA |
| 5. SUSPENSE DATE |
| 6. CONTROL NUMBER |
7. DEFICIENCY MAJOR MINOR FINDING:
FINDING IMPACT:
Please respond with a written corrective action plan that details the corrective action of the cited deficiency, the cause of the deficiency, and actions taken to prevent recurrence by Suspense Date in Block 5. If date was not entered in Block 5, the contractor is not required to provide a response.
8. QUALITY ASSURANCE PERSONNEL (COR)
TYPED NAME AND GRADE
SIGNATURE AND DATE
9. ISSUING AUTHORITY
TYPED NAME AND GRADE
SIGNATURE AND DATE
10. COR RESPONSE TO CONTRACTOR CORRECTIVE ACTION AND ACTION TAKEN TO PREVENT RECURRENCE
| 11. COR DETERMINATION ACCEPTED | REJECTED |
| 12. CLOSE DATE |
6.2 Customer Complaint Record
| CUSTOMER COMPLAINT RECORD |
| DATE/TIME OF COMPLAINT |
SOURCE OF COMPLAINT
| ORGANIZATION |
| BUILDING NUMBER |
| INDIVIDUAL |
| PHONE NUMBER |
NATURE OF COMPLAINT
CONTRACT REFERENCE
VALIDATION
DATE/TIME CONTRACTOR INFORMED OF COMPLAINT
ACTION TAKEN BY CONTRACTOR
RECEIVED/VALIDATED BY
6.3 Performance Assessment Report (PAR)
PERFORMANCE ASSESSMENT REPORT (PAR)
(If more space is needed, use reverse and identify by number)
| 1. CONTRACT/TASK ORDER NUMBER |
| 2. CONTRACTOR |
| 3. TYPE OF SERVICES |
4. QUALITY ASSURANCE PERSONNEL (COR) SIGNATURE AND DATE
5. COR PHONE
6. SUSPENSE DATE
I. PERFORMANCE
7. DEFICIENCY (CHECK ALL BOXES THAT APPLY) NEW
REPEAT
NO DEFICIENCY NOTED
8. SERVICES SUMMARY or PWS PARAGRAPH ITEM REVIEWED
| 9. BRIEF DESCRIPTION OF DEFICIENCY (IF DEFICIENCY BOX WAS CHECKED) |
| 10. DETAILED PERFORMANCE ASSESSMENT |
II. CONTRACTOR VALIDATION
| 11. CONTRACTOR REPRESENTATIVE | CONCUR | NON-CONCUR |
| 12. CORRECTIVE ACTION ESTIMATED COMPLETION DATE |
13. CONTRACTOR REPRESENTATIVE CORRECTIVE ACTION AND PREVENTION OF RECURRENCE OR REASON FOR NON-CONCURRENCE OF COR CITED DEFICIENCY
III. ACTION CORRECTED
14. CONCUR NON-CONCUR COR SIGNATURE AND DATE
15. COR REMARKS (REQUIRED)
6. CONTRACTOR REPRESENTATIVE REMARKS
7.0 Surveillance Matrix for Title of Contractor
| Description of Service |
| PWS Reference |
| Performance |
Threshold Methods of Surveillance
ADMINISTRATION -
Availability of means, tools, equipment and supplies as required in the PWS 3.3 3.5 4.2 4.5
| No more than 3 occurrences of non-compliance |
| Monthly inspection tracked by COR |
ADMINISTRATION -
Lab test premises adequacy 3.3 4.7
| No more than 5 occurrences of non-compliance |
| Monthly inspection tracked by COR |
KEY PERSONNEL -
OHP license, appointment, and qualification 7.1 8.
| 100% of the time. Rated on Pass/Fail |
| Quarterly inspection tracked by COR |
KEY PERSONNEL -
OHP service continuity 8.6 8.7 8.8
| 100% of the time. Rated on Pass/Fail |
| Inspected immediately following OHP changeover by COR |
| MED EXAMINATIONS -completed in a timely, exhaustive, and effective manner |
| 9.2.3 |
9.2.4 9.2.5
| No more than 5 occurrences of non-compliance |
| Monthly inspection tracked by COR |
| CLINICAL TESTS - completed in a timely, exhaustive, and effective manner |
| 9.3.1 |
9.3.2
| No more than 5 occurrences of non-compliance |
| Monthly inspection tracked by COR |
RISK ASSESMENT Availability of OPH for Consultations/Work center visits/Meetings
9.5 9.6
| No more than 3 occurrences of non-compliance |
| Responded to upon individual occurrences by COR |
REPORTING –
Receipt of reports, documents and fit for duty certificates within required timeframe, language, and legal requirements 5.2
| No more than 3 occurrences of non-compliance |
| Bi-weekly inspection tracked by COR |
Appendix 1.0 Version Change History
| Section / Page No. |
| Add / Change / Delete |
| Change No. / Date |
| Explanation |
| Title/Sec.7 |
| Add |
| 1/10 Jun 2024 |
| Added Title/QASP Matrix |
THIS PAGE IS NOT USED.
image1.png
File details come from the government source that posted it. Updated .