QRL ARSR Gate Lighting Upgrades and Site Improvements SOW.pdf

PDF 378 KB Posted

Attached to
QRL ARSR Small Area Parking Lot Pavement
Solicitation number
697DCK-24-R-00292
Issued by

About this file

This document is a Statement of Work (SOW) for the QRL ARSR Gate Lighting Upgrades and Site Improvements project in Benson, North Carolina. The key work items include:

Replacing the existing fence system with a new 10-foot high security fence and gate, installing a new motorized sliding gate with a wireless controlled linear operator and card reader system, excavating and installing a new paved parking area, and upgrading the existing lighting system by replacing fluorescent bulbs/fixtures with new LED lighting.

The SOW also includes details on submittal requirements, construction conditions, safety, and contact information. A related federal contract opportunity is provided, Solicitation Number 697DCK-24-R-00292, which is a Screening Information Request (SIR) for a Firm Fixed Price contract to complete the QRL ARSR Small Area Parking Lot Pavement work. The SIR is set-aside for small businesses and has an estimated cost magnitude between $250,000 and $500,000 with a projected period of performance of approximately 35 calendar days.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Aviation Administration

NAS DEFENSE PROGRAM

NDP RESOURCE SERVICES TEAM

AJW-B710

INFRASTRUCTURE PROGRAM

GATE, LIGHTING UPGRADE, AND SITE

IMPROVEMENTS PROJECT

FAA-B710-QRL-SOW

BENSON, NC

QRL ARSR

STATEMENT OF WORK

JANUARY 2024

FEDERAL AVIATION ADMINISTRATION JANUARY 2024

Gate, Lighting Upgrade, and Site Improvements Project

Table of Contents

_Toc128501339

1.0 GENERAL

1.1 SCOPE

1.2 APPLICABLE DOCUMENTS

1.3. CONSTRUCTION CONDITIONS

1.4 SAFETY

2.0 FURNISHED MATERIAL AND EQUIPMENT

2.1 MATERIAL DELIVERIES

2.2 STORAGE AND PROTECTION

2.3 PERTINENT INFORMATION

3.0 EXECUTION

3.1. WORK SEQUENCE

3.2 CONTRACTOR USE OF PREMISES

4.0 DELIVERABLES

4.1. DOCUMENTATION

4.2. RECORD DRAWINGS

5.0 CONTACT INFORMATION

6.0 ATTACHMENTS

Gate, Lighting Upgrade, and Site Improvements Project

QRL ARSR 3

SUMMARY OF WORK

1.0 GENERAL

1.1 SCOPE

The Benson, North Carolina (QRL) Air Route Surveillance Radar (ARSR) site is located southwest from the intersection of Raleigh Road and State Highway 210.

The approximate address for the project site is below:

11555 NC-210

Benson, NC 27504

Coordinates for the project site are listed below:

LATITUDE: 35° 30' 41.0" N

LONGITDE: 78° 32' 56.4" W

The project scope include the replacement of the existing fence system, installation of a new motorized gate, parking lot pavement, excavation for the new pavement section, and installation of lighting upgrades to the existing Engine Generator building. Further description of the work for this project can be found in Section 1.1-B Work Description of this document.

A. General

1. All work shall be coordinated with the onsite Resident Engineer (RE).

2. The Contractor shall provide all temporary services required for construction as necessary.

3. The Contractor shall clean up and restore the site grounds to the pre-construction condition after the work has been performed, unless otherwise noted in the project documents for this project modification.

4. The Contractor shall submit project schedule prior to commencement of work.

5. Construction debris and garbage will be managed and disposed of by The Contractor according to State of North Carolina’s standing processes and procedures. These processes and procedures shall include plans for recycling whenever feasible.

6. All efforts shall be made to prevent turbid water from entering the storm drain systems during this work, as required. A Temporary Erosion and Sediment Control (TESC) Plan may be required by the State of North Carolina.

7. The maximum length of time for a road closure is four (4) hours before opening the access road to general vehicle traffic. The contractor shall provide safe access for emergency vehicles at all times.

B. Work Description

All of the equipment and material shall be reviewed and accepted by the Contracting Officer’s Representative / Resident Engineer (COR / RE). The following items are a summary of the project and are provided solely for describing the general nature of the work. The Contractor is responsible for accomplishing all items of work identified in the applicable manufacturer’s specification(s), project drawings, project specifications, and provisions of the Statement of Work. This work includes, but is not limited to, the following principal items:

B-1 Motorized Gate Installation The contractor shall remove the existing vehicle entry/exit gate on the northeast corner of the site and replace it with a motorized sliding gate, refer to the project drawings for additional details. The following scope items represent the minimum work required to complete the motorized gate and fencing improvement installation:

a. Installation of a new #4/0 bare copper fence bonding cable across the new access road as indicated on the drawings.

b. Furnish and install a new 1 H.P. 120V linear gate operator as described in this statement of work including:

1. Construction of an approximately 3’ long x 4’ wide, 18” thick, 3000 p.s.i.

concrete reinforced pad and 24” diameter, 60” deep, 3000 p.s.i., concrete reinforced pier for the new gate operator.

2. Furnish and install a new wireless controlled linear motorized gate operator as specified in this Statement of Work, including new exit loop sensors.

3. Furnish and install a new card reader system for gate access. FAA badge reader is preferred, but other access systems are acceptable upon FAA approval.

4. Furnish and install gate opener inside of the ARSR facility for FAA use in allowing access to parties that should not normally have gate control.

5. Installation of a new dedicated gate operator ground consisting of a new

#2 AWG, Type THWN green insulated ground connected to a new ¾”x10’ copper clad ground rod with an exothermic weld.

6. Connect gate motor to facility electrical distribution. Cables should be trenched and buried in PVC coated RMC. Any asphalt that was cut and trench should be back filled and resurfaced with new asphalt.

7. All related work required for a complete operating system including modifications to the perimeter fence and all related civil and electrical work.

B-2 Security Fencing Improvements The Contractor shall remove and replace the existing security fencing system and replace it with a 10-foot high security fencing system. The following items represent the minimum work required for completing needed the fencing improvements for the project:

a. Provide temporary fencing during new security fence system construction.

Temporary fencing shall be removed from the project site once the project site is considered secured when new fence installation has completed, or as deemed secured by the FAA Resident Engineer.

b. Remove and salvage existing signage on existing fence and gate. Replace signage in original location, layout, and configuration on new fence and gate system after installation has completed. Replacement of signage shall utilize salvaged signage or new signage that is provided by the local FAA System Support Center.

c. Remove and dispose approximately 800 lineal feet of existing security fence system including existing post base materials.

d. Install new 10-foot-high security fence and gate system to match the footprint of the existing fence system, unless otherwise shown in the project drawings.

Security fence system and gate system shall meet or exceed the requirements set per the FAA Order 1600.69C, Federal Specification RR-F-191K, Federal Specification Sheets RR-F-191-E through 4E, and ASTM F567-07. Relevant excerpts from FAA Order 1600.69C has been included in the Appendix section of this Statement of Work.

e. Ground and Bond new security fencing system per the project drawings.

B-4 Lighting Upgrades Replace existing florescent lighting with new LED lighting as follows:

a. New LED Lighting shall be a one-for-one replacement with existing fluorescent bulbs & fixtures, providing equal or greater light (lumens) per square foot.

b. Actual Fixture location shall be altered to accommodate new ductwork.

c. LED light fixtures shall be similar design to existing. Drop ceiling models installed into the same circuits as the existing lights. Lights shall be Nicor T6C LED Troffer (4000K Color Temperature), or FAA approved equal.

1. LED fixture must be fully sealed to prevent bug entry.

2. Troffer surface mount kit required for all surface mounted lights.

d. In areas requiring hanging light due to ductwork or other interference, utilize

Lithonia SBL4 48L (4000K Color Temperature) or FAA approved equal.

In areas requiring hanging shop lighting, utilize Nicor VT320 (4000K Color Temperature) or FAA approved equal.

B-3 Site Improvements The contractor shall pave an additional area to provide a paved parking space at the project site. For additional information and location on this area, refer to the project drawings for more details. The following represents the minimum work required to accomplish the site improvements for this project:

e. Excavation, removal, and disposal of approximately 650 cubic yards of existing material for the installation of the proposed pavement section in accordance with this statement of work and project drawings.

f. Preparation of subgrade to follow good engineering practices. Subgrade shall be prepared and allowed to reach a Proctor Density of ninety-five percent (95%) through natural cycles of consolidation or may be rolled and watered where placement of the base material is to be done immediately. For additional guidance see Section 500-2 CONSTRUCTION METHODS before placement of base material in accordance with the North Carolina Department of Transportation Raleigh Standard Specifications for Roads and Structures (January 2024).

g. Installation of proposed pavement section defined in the project drawings and in accordance with the table of materials shown below per the North Carolina Department of Transportation Raleigh Standard Specifications for Roads and Structures (January 2024):

Section Number

Title Additional Reference

Drawing Reference

520 Aggregate Base Course Table 1005-1, ABC Aggregate Base Course

Asphalt Concrete Plant Mix Pavements

PG 64-22

New Asphalt Concrete

Pavement

Sealing Existing Pavement Cracks and Joints

Section 1028-2 Joint Sealer

1056 Geosynthetics Type 2 Geotextile Fabric

h. Sawcutting and Sealing of approximately 145 feet of sawcut joint between the old and new pavement. See North Carolina Department of Transportation Raleigh Standard Specifications for Roads and Structures Section 657 Sealing Existing Pavement Cracks and Joints and Section 1028-2 for Hot Applied Joint Sealer.

1.2 APPLICABLE DOCUMENTS

A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and contract drawings referenced in this and the following divisions form a part of this specification and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract, unless otherwise noted below:

1. FAA ORDER 1600.69B FAA Security Management Program

2. North Carolina Department of Transportation Raleigh Standard Specifications for

Roads and Structures (January 2024)

B. Drawings

B-1 PROJECT DRAWINGS

QRL-D-ARSR-G001 COVER SHEET/DRAWING INDEX

QRL-D-ARSR-C001 CONSTRUCTION PLAN

QRL-D-ARSR-C002 TYPICAL FENCE DETAILS

QRL-D-ARSR-E001 FENCE AND GATE FROUNDING DETAILS

QRL-D-ARSR-E002 SLIDING GATE AND GATE OPERATOR

DETAILS

B-2 REFERENCE DRAWINGS

QRL-D-ARSR-C001 PLOT LAYOUT

DR.FW-E-5141-1B PLOT TOPOGRAPHY

These listed drawings are for information only, expressing existing conditions and construction details. The contractor shall verify dimensions, locations, and sizes on the applicable drawings prior to installation.

1.3. CONSTRUCTION CONDITIONS

A. Pre-construction Conference – The Contractor shall attend a pre-construction conference at the time and location specified by the Project Engineer (PE). Requirements for material disposal, security and safety will be discussed. Use of facility restrooms, water, and power will also be discussed. Compliance with these procedures while on site is mandatory.

B. Submittals - Samples, certificates, reports, catalog cuts, letters, shop drawings, maintenance and operations manuals, etc. required shall be submitted to the Project Engineer.

a. Preconstruction Submittals- Prior to the start of the work, submit the following items for review and permanent file.

1) Product Data- Submittals are required for any new material that will be installed as a part of this project. All new materials shall be certified to be asbestos free.

The contractor may not install/use any product that contains asbestos, lead, PCB’s or other materials that may cause future worker exposures. See Appendix 1 for a Schedule of Submittals.

2) General Project Submittals – See Appendix 1 for Schedule of Submittals.

b. Submittals at Completion of Work- Within 14 days of completion, provide the following information:

1) Warranty: Manufacturer’s agree to repair or replace components that fail in materials or workmanship within specified warranty period, after assembly in the field:

(a) Warranty Period: One year from date of Substantial Completion.

C. Conflict Resolution – The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases. Specifications shall govern over drawings. If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the RE.

D. Inspection

1. Access for Inspection – The Contractor shall allow PE complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the PE or SSC before being obscured by the next operation of the Contra. In all cases, the RE shall be informed accordingly and given access to the work.

The RE will inspect all work in progress up to completion and final Joint Acceptance Inspection (JAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The RE will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.

2. Joint Acceptance Inspection (JAI) - After substantial completion of all the Contractor’s work, a JAI will be conducted between the Contractor and Government. The RE will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly.

E. Layout of Work – The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at their own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.

F. Permits, Inspection, Licenses, Certificates – The Contractor shall obtain and pay fees for permits, inspections, licenses, or certificates required by Federal, State and City/Town officials as necessary to perform the work, prior to starting construction, and in a timely manner to avoid delays in starting the job. The Contractor shall submit evidence that they have obtained all required permits, inspections, licenses, and/or certificates.

G. Compliance with Local and Other Codes – The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.

H. Stop Work Orders - When the Contractor or subcontractors are notified by the RE of any non-compliance with the provisions of the contract and the action(s) to be taken, the Contractor shall correct the unsafe or unhealthy condition. Life threatening or other serious violations shall be corrected immediately. Non-serious violations shall be corrected within 24 hours of the non-compliance notice. The RE may stop the work with a “stop work order” if the Contractor fails to comply promptly with all or any part of the work being performed. When, in the opinion of the RE, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, the Contractor may resume work.

I. Protection of Existing Vegetation, Improvements and Structures – The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by the Contractor or any subcontractors, shall be repaired or replaced to their original conditions by the Contractor. Repairs shall be approved by the RE and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.

J. Schedules

1. Schedule – The Contractor shall submit to the RE for approval a practical project schedule. The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the RE.

2. Progress Schedule – Due to the duration of this project, the Contractor shall submit a progress schedule at such intervals as directed by the RE.

3. Hours of Work – All work shall be accomplished during normal business hours from

7:00 AM – 3:30 PM, unless otherwise agreed upon with the project RE or defined at the pre-construction conference.

K. Waste Disposal – The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site. Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of off-site in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste. The Contractor shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the Contractor.

L. Cleanup - The work site shall be kept clean and orderly during the progress of work. After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.

M. O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new equipment. This information will then be retained by the Contractor (and the FAA) and used to reflect the as-constructed conditions.

N. Warranties - Documentation for the warranties shall be provided to the government upon completion of the project.

1.4 SAFETY

OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:

A. Safety Plan – The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site. The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the RE to insure that the work is accomplished in accordance with accepted safety practices.

B. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The RE may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.

C. HAZCOM Program – The Contractor shall have a Hazard Communications (HAZCOM) program and the Contractor shall submit a copy of their HAZCOM, if requested.

D. Safety Data Sheets (SDS) – The Contractor shall have Safety Data Sheets (SDS) conforming to Federal Standard 313E, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. These must be reviewed by the RE prior to project start. One (1) copy of each SDS shall be submitted to the RE and one (1) copy of each SDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable SDS on file at the site until such SDS arrives on site. Notification should be given when different chemicals will be used and the control measures in place.

Refer to OSHA CFR 1926.101.

E. Safety Equipment – The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.

F. Personal Protective Equipment – Wear safety glasses, hard hats, protective footwear, gloves and other PPE as required by job tasks. OSHA CFR 1926 Subpart E.

G. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the RE may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The RE may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.

H. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site. The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.

I. Work Force – The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.

J. Crystalline Silica Exposure – Gravel and concrete dusts likely contain silica. If any work producing silica dust is conducted, applicable work activities shall comply with the OSHA “Occupational Exposure to Respirable Crystalline Silica” Final Rule, 1926.1153.

Compliance includes: Written program, training, and following exposure monitoring protocol. Wet spray should be incorporated and work should be performed so that no visible dusts are generated.

K. Hearing Protection – Hearing protection must be worn when loud machinery (>85dBA) is in operation at the site such as heavy machinery operation, grinding, cutting, etc. per

OSHA CFR 1926.101.

L. Trenching or Excavation Operations – OSHA defines an excavation as any man-made cut, cavity, trench, or depression in the earth’s surface formed by earth removal. A trench is defined as a narrow underground excavation that is deeper than it is wide, and is no wider than 15 feet. Trenching must be overseen by a competent person trained on OSHA regulations for excavations, trenches, and soil mechanics. Utilities must be located, and protective systems must be in place (trench boxes, sloping) if necessary OSHA CFR 1926.650.

M. COVID Precaution - Ongoing COVID-19 concerns require the use of face protection and social distancing methods. Personnel should wash their hands regularly and maintain a minimum of six (6) feet of distance from other persons. Given the potential close working conditions of that this project requires, within the LOC facility, personnel should be limited inside the facility to achieve virus protection and safety.

2.0 FURNISHED MATERIAL AND EQUIPMENT

2.1 MATERIAL DELIVERIES

All material deliveries made under this contract shall be arranged for delivery to the Contractor’s material staging area. This area shall be located as determined at the pre-construction conference.

2.2 STORAGE AND PROTECTION

The Contractor, through the RE, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas. The storage and protection of The Contractor’s material shall be the sole responsibility of the Contractor.

The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.

2.3 PERTINENT INFORMATION

Any pertinent information listed about Contractor-furnished material and equipment shall be submitted to the RE.

3.0 EXECUTION

3.1. WORK SEQUENCE

Performance of this work should be accomplished during ideal weather conditions. The Contractor shall provide temporary storage for their products and/or equipment that meet specifications, if weather conditions deem it necessary.

3.2 CONTRACTOR USE OF PREMISES

A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required. If disturbed, areas must be restored to a condition that is equal or better than conditions prior to construction related activities or movements.

B. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency vehicles at all time. Do not use these areas for parking or storage of materials.

Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Access – The access to the QRL ARSR Project Site is gated and locked. The Contractor shall coordinate with the RE for access to this area. The Access Road to the facility is not secured and may be accessed by the contractor without RE assistance.

4.0 DELIVERABLES

4.1. DOCUMENTATION

Documentation for labor and material warranties shall be provided to the RE upon completion of the work.

4.2. RECORD DRAWINGS

A set of four (4) redline-drawings in D-Sheet scale shall be produced pending JAI approval.

A. One set shall be produced and shall remain at the facility.

B. Two sets shall be produced for use by the RE.

C. One set shall be produced for use by the Contractor for comparison.

5.0 CONTACT INFORMATION

Table 1 - Project Contact Information

Contact Information

Name Title Phone Number

Brian Strickland NAS Defense Liaison Eastern Service Area 803-629-7055

Vincent Castro NAS Defense Program Analyst 771-215-8037

Matthew Cunningham NAS Defense Project/Electrical Engineer 203-980-9413

6.0 ATTACHMENTS

Attachment 1 -Schedule of Submittals Attachment 2 - Project Drawings

END OF DOCUMENT

Vincent Castro Text Box

ATTACHMENTS

ATTACHMENT 1

SCHEDULE OF SUBMITTALS

Submittal

Statement Of Work Section

Title Date

Received Date

Approved Submittal Requirements

001 Not Applicable Security

Information

Security Information as Required by the Contracting Officer or Contract Clause

002 1.3-J Construction

Schedule

Construction schedule to Include all major construction activities including the following:

- Project mobilization.

- Sequence of construction.

003 1.4-A Construction Safety Plan

Contractor’s general safety plan including the following information:

- Equipment training.

- Project mobilization.

- Material Safety Data Sheet information.

004 1.1-B-3 Aggregate

Baes Course Aggregate Gradation and Source Information.

005 1.1-B-3

Asphalt Concrete Plant

MixP avements

Mix Design.

006 1.1-B-3 Joint Sealer Material and technical information.

007 1.1-B-3 Geotextile

Fabric Material technical data sheet

008 1.1-B-1

Sliding gate motor and connection plan

- Technical information on the sliding gate motor and it’s components.

- Shop Drawings indicating the layout and construction of the sliding gate and electrical connection plan.

SCHEDULE OF SUBMITTALS

Submittal

Statement Of Work Section

Title Date

Received Date

Approved Submittal Requirements

SCHEDULE OF SUBMITTALS

009 1.1-B-2 Security Fencing System

Shop drawing of typical fence construction meeting FAA Order and Federal Specifications. At a miniumum, include the following information:

- Fence hardware

- Fence Fabric mesh opening size

- Barbed Wire Type and mounting hardware.

- Tension wires, strecher bars, Top Rails, and etc.

- Galvanizing or Coating Information

010 1.1-B-4 Lighting -Specification sheets for lighting fixtures

ATTACHMENT 2

PROJECT DRAWINGS