This is a Quality Assurance Surveillance Plan (QASP) for the Boiler Plant Comprehensive Contract at VISN 15, Marion VAMC, Contract Number 36C255. The QASP establishes surveillance methods and performance metrics to ensure contractor compliance with boiler plant operations requirements through the five-year period of performance from February 1, 2026 through January 31, 2031. Surveillance will be conducted using direct observation, periodic inspection, random sampling, performance metrics review, contractor self-reporting, and customer feedback. The plan specifies surveillance frequencies for key performance areas including boiler plant safety device testing (semi-annually), boiler combustion tuning (semi-annually), boiler gage/controls/gas sensor calibration (semi-annually), boiler inspections (annually for deaerator and condensate tank), and deaerator non-destructive testing (every five years).

The QASP establishes performance metrics to evaluate contractor success including completion rates of testing and calibration activities, accuracy and timeliness of test results, compliance with VHA guidelines, documentation completeness and accuracy, emergency response time, report status, and identification of test findings and corrective actions. The Contracting Officer maintains contractual authority and approves corrective actions, while the Contracting Officer's Representative conducts surveillance, documents findings, and communicates with the contractor. The Boiler Plant Supervisor provides technical oversight and supports compliance verification. This surveillance plan ensures contractor adherence to VHA Directive for Boiler Plant Operations and the VHA Boiler and Associated Plant Safety Device Testing Manual throughout contract performance.

View the file

Other files

File Type Posted
WD 2015-5769 Rev 27 12.3.25.pdf PDF
36C25526Q0147 0001.pdf PDF
36C25526Q0147.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D.2 Quality Assurance Surveillance Plan (QASP)

For: Boiler Plant Comprehensive Contract Facility: VISN 15, Marion VAMC Contract Number: 36C255 COR: William C. Ahrendt Period of Performance: 2/1/2026-1/31/2031

1. Purpose This QASP outlines the surveillance methods and frequency used to ensure contractor compliance with the performance requirements for the Boiler Plant Comprehensive Contract in accordance with VHA Directive for Boiler Plant Operations, VHA Boiler and Associated Plant Safety Device Testing Manual, and the Performance Work Statement (PWS).

2. Surveillance Methods

Method
Description
Direct Observation
Real-time monitoring of contractor activities such as sample collection, personnel instruction and testing.
Periodic Inspection
Scheduled reviews of reports, and certifications.
Random Sampling
Unannounced checks of procedures, documentation, and equipment.
Performance Metrics Review
Analysis of process reports, and compliance with VHA Directive for Boiler Plant Operations, VHA Boiler and Associated Plant Safety Device Testing Manual.
Contractor Self- Reporting
Review of contractor-submitted documentation and quality control reports.
Customer Feedback
Input from VA staff and stakeholders on service quality and responsiveness.

3. Surveillance Frequency

Performance Area
Surveillance Method
Frequency
Boiler Plant Safety Device Testing
Direct Observation / Documentation Review
Boiler Plant Safety Device Testing Semi-Annually, after each,
Boiler Combustion Tuning
Direct Observation / Documentation Review
Semi-Annually, after each boiler Plant Safety Device Testing.
Boiler Gage, Controls, Gas Sensor Calibration
Direct Observation / Documentation Review
Semi-Annually, after each Boiler Gage, Controls, Gas Sensor Calibration.
Boiler Inspections
Direct Observation / Documentation Review
Annually for deaerator, condensate tank.
Deaerator NDT Inspection
Direct Observation / Documentation Review
Every five years.

4. Performance Metrics The following metrics will be used to evaluate contractor performance:

· Completion rate of Safety Device Testing, Combustion Tuning, Gage/Controls Calibration, Inspections

· Accuracy and timeliness of test results

· Compliance with VHA Guidelines

· Documentation completeness and accuracy

· Emergency response time

· Provided Reports status

· Test findings and corrective actions.

5. Roles and Responsibilities

· Contracting Officer (CO): Maintains contractual authority and approves corrective actions.

· Contracting Officer’s Representative (COR): Conducts surveillance, documents findings, and communicates with the contractor.

· Boiler Plant Supervisor: Provides technical oversight and supports compliance verification.

<After award, both the contractor’s Program Manager, COR, and CO will sign this document.>

Signature – Contractor Program Manager

Signature – Contracting Officer’s Representative

Signature – Administrative Contracting Officer