COMMAND AIRCRAFT CREW TRAINING (CACT) PROGRAM FOR ACADEMIC AND SIMULATOR TRAINING ON THE UC-35D AIRCRAFT
Solicitation number
N6134026R1017
Issued by

About this file

This is a Quality Assurance Surveillance Plan (QASP) for the Command Aircraft Crew Training (CACT) UC-35 Academic and Simulator Training contract, effective April 1, 2026. The QASP establishes the Government's approach for monitoring contractor performance through Government Quality Assurance personnel, consisting of the Contracting Officer's Representative (COR) and Model Manager (MM), who are responsible for ensuring all contractor services meet contract standards and performance requirements.

The QASP defines contractor quality control responsibilities and Government surveillance methods to verify compliance. Performance success is measured against the Airman Certification Standards (ACS), FAA-S-ACS-11A, and Naval Air Training and Operating Procedures Standardization (NATOPS). Surveillance methods include direct observation and participation in classes and simulator sessions, as well as systematic review of student evaluation forms and complaint handling. The performance matrix establishes five key metrics: maintenance of FAA certification (Pass/Fail), maintenance of NATOPS standards (Pass/Fail annual review by MM), and three course evaluation form elements for simulation training, ground school training, and crew coordination training (each rated 1-5, with 3 being satisfactory). Unsatisfactory performance is defined as any service not meeting specified standards and may result in corrective action plans, cure notices, show cause notices, or contract termination for cause. The Government retains unilateral discretion to decline exercising option periods regardless of contractor performance history.

View the file

Other files

File Type Posted
Wage Determination KS.pdf PDF
Combined SS CACT UC-35 RFP 1.pdf PDF
UC-35 PWS_UPRT N6135025R1017.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMAND AIRCRAFT CREW TRAINING

(CACT) PROGRAM

MOPAS 2 REPORT

ATTACHMENT (1)

QUALITY ASSURANCE SURVEILLANCE PLAN

(QASP)

1 April 2026

1. Purpose This Quality Assurance Surveillance Plan (QASP) defines the Government's approach for monitoring the performance of the Command Aircraft Crew Training (CACT) UC-35 Academic and Simulator Training contract. Government Quality Assurance (QA) personnel, consisting of the Contracting Officer's Representative (COR) and the Model Manager (MM), will use this QASP to ensure contractor performance meets all contract standards. The COR and MM monitor all tasks issued under this requirement.

This plan uses quality metrics to evaluate the services the contractor is required to perform, assuring the Government that performance is acceptable.

Any noncompliance with contract performance requirements will be deemed unsatisfactory.

Unsatisfactory performance is defined as any service that does not meet the specified standards.

This QASP is based on the premise that the contractor, not the Government, is responsible for the management and quality control actions required to meet the terms of the contract.

Surveillance methods account for the possibility of unforeseen and uncontrollable issues. QA personnel are required to be objective, fair, and consistent when evaluating contractor performance against the established standards.

The contractor is expected to maintain an effective quality control program. Proper management of this program is essential for ensuring performance complies with all contract requirements and meets the standards outlined in this QASP.

2. Authority This Quality Assurance Surveillance Plan (QASP) is issued under the authority of Federal Acquisition Regulation (FAR) Part 46.4, Government Contract Quality Assurance, as implemented in Section E – Inspection and Acceptance of the contract. This provision grants the Contracting Officer, or a duly authorized representative, the right to inspect and accept all services and documentation required under the task order to ensure they meet contract standards.

3. Scope This section defines the distinct roles and responsibilities of the Contractor and the Government regarding quality management.

3.1. Contractor Quality Control (QC)

The Contractor, not the Government, is responsible for quality control. The Contractor shall implement and manage its own internal quality control program to ensure all services meet the performance standards specified in the contract and all associated task orders. This program is the primary mechanism for ensuring quality.

3.2. Government Quality Assurance (QA)

This Quality Assurance Surveillance Plan (QASP) is the Government's oversight mechanism. It outlines how the Government will surveil the Contractor's QC efforts to validate that they are timely, effective, and consistently deliver the results specified in the contract. The QASP is a verification tool, not a substitute for the Contractor's own quality control.

4. Government Resources The following definitions for Government resources are applicable to this plan:

Role & Acronym Definition and Responsibilities

Contracting Officer

(PCO/ACO)

A Government employee formally appointed with the authority to enter into, administer, or terminate contracts and make related determinations. The PCO for this contract is the NAWCTSD Code

2.5.3.2.2 office. The Administrative Contracting Officer (ACO), if different, will be designated in the contract award. A Contracting Officer's authority is strictly defined in their written warrant.

Contracting Officer's Representative (COR)

An individual designated in writing by the PCO to act as their technical representative for contract administration. The COR monitors performance, but their authority is limited to the duties specified in their written letter of appointment. The COR for this contract will be formally appointed upon award.

Model Manager (MM) The Government's subject matter expert responsible for the hands-on surveillance of the contractor's training performance. The MM's primary duties include monitoring compliance with NATOPS and evaluating the quality of training delivery. The MM reports all surveillance findings directly to the COR.

5. Responsibilities The following Government resources shall have responsibility for the implementation of this

QASP:

Role Responsibilities & Authority

Contracting Officer

(CO)

Directs all aspects of contract administration, ensuring fair treatment and safeguarding U.S. Government interests.

Holds ultimate authority to determine the final adequacy of the contractor’s performance and authorize any contractual remedies.

Contracting Officer's Representative (COR)

Responsible for the technical administration of the contract. The COR oversees day-to-day surveillance activities and acts as the primary technical liaison with the contractor. The COR has no authority to alter contract scope, price, terms, or conditions. All such matters must be referred to the CO.

Model Manager (MM) The designated subject matter expert who performs the hands-on, technical surveillance of training delivery. The MM monitors daily contractor performance against NATOPS requirements and reports all findings and observations directly to the COR, providing the basis for the COR's technical oversight.

6. Method of QA Surveillance

For all courses, the outcome to be achieved is a successfully trained student. Performance success is measured against standards established by:

• Airman Certification Standards (ACS), FAA-S-ACS-11A

• Naval Air Training and Operating Procedures Standardization (NATOPS)

Surveillance Method

Description Performed By

Purpose & Documentation

Direct Observation & Participation

Observing classes and simulator sessions;

participating as a student in training events.

MM Provides direct, firsthand evaluation of training quality and NATOPS compliance. Findings are formally documented.

Customer Feedback & Complaint Handling

Systematically reviewing student evaluation forms and investigating any reported complaints.

MM &

COR

Serves as a primary indicator of user satisfaction. A formal process is used to classify complaints as Minor or Major and track them to resolution.

7. Unsatisfactory performance This section outlines the process for addressing services that do not meet the performance standards established in this QASP.

7.1 Definition and Notification

Any service identified through surveillance that fails to meet the contract requirements will be deemed Unsatisfactory Performance. The Contracting Officer (CO) or their designated representative (COR) will formally notify the contractor of the deficiency.

7.2 Initial Remedy: Re-performance

For services that can be re-performed, the CO may, at their discretion, request the contractor to re-perform the service at no additional cost to the Government. If the service cannot be re-performed, or if the re-performance is also deemed unsatisfactory, the Government will proceed to further remedies.

7.3 Further Government Remedies

When Unsatisfactory Performance cannot be corrected by re-performance, the CO may exercise one or more of the following remedies, in accordance with the Federal Acquisition Regulation

(FAR):

• Require a Corrective Action Plan: Demand the contractor implement actions necessary to ensure all future performance conforms to contract requirements.

• Issue a Cure Notice: Formally notify the contractor of the failure and provide a period of ten (10) days, or other specified time, to "cure" the failure.

• Issue a Show Cause Notice: Require the contractor to show cause why the contract should not be terminated for default.

• Terminate the Contract for Cause/Default: Terminate all or part of the contract due to the contractor's failure to perform.

7.4 Impact on Option Periods

The Government reserves the unilateral right to not exercise any option period, regardless of the contractor's performance record. A decision not to exercise an option is not a contract remedy and may be made if it is determined to be in the Government's best interest.

Attachment (1) - QASP Surveillance Performance Matrix

Description Performance

Standard Surveillance Method/Measure

Incentives

Maintain FAA Certification

Airman Certification Standards (ACS), FAA-S-ACS-11A

Pass/Fail, per FAA annual review

Pass - Training continues

Fail - Contract Terminated for Cause

Maintain NATOPS Standards

Naval Air Training and Operating Procedures Standardization

(NATOPS)

Pass/Fail, per annual review by Model Manager

Pass - Training continues

Fail - Correction of unsatisfactory performance *

Course Evaluation Form Element – Simulation Training

Student Input Rated 1 through 5, 5 being the highest and 3 is satisfactory

Satisfactory (3 through 5) – Training continues

Unsatisfactory (1 through 2)

– Model Manager reviews performance pattern with possibility of correction of unsat performance *

Course Evaluation Form Element – Ground School Training

Student Input Rated 1 through 5, 5 being the highest and 3 is satisfactory

Satisfactory (3 through 5) – Training continues

Unsatisfactory (1 through 2)

– Model Manager reviews performance pattern with possibility of correction of unsat performance *

Course Evaluation Form Element – Crew Coordination Training

Student Input Rated 1 through 5, 5 being the highest and 3 is satisfactory

Satisfactory (3 through 5) – Training continues

Unsatisfactory (1 through 2)

– Model Manager reviews performance pattern with possibility of correction of unsat performance *

5. Responsibilities
6. Method of QA Surveillance