- The Dalles Watershed Project GNA 2026
- Solicitation number
- S-62900-00018091
- Issued by
- Union County, Oregon
About this file
This Questions and Answers document addresses clarifications for RFP S-62900-00018091, issued by the Oregon Department of Forestry on behalf of the U.S. Forest Service Barlow Ranger District for The Dalles Watershed Project on the Mount Hood National Forest. The project requires comprehensive data collection, analysis, and documentation services to support Environmental Assessment and National Environmental Policy Act compliance. Key deliverables include field surveys for Northern Spotted Owl autonomous recording units (86 units deployed April 1 through May 15, 2027), terrestrial mollusks across 4,552 acres (spring and fall 2027), fungi across 986 acres, and archaeological surveys across approximately 3,210 acres. The contractor must prepare draft and final Environmental Assessments, Biological Assessments, Biological Evaluations, and Findings of No Significant Impact, along with 21 monthly progress review meetings and a fall 2026 collaborative field trip. The contract term runs from the effective date through June 30, 2028 with no renewal options. Proposals were due November 2, 2026 at 2:00 PM Pacific Standard Time, with Notice of Intent to Award anticipated for approximately November 9, 2026.
The RFP does not establish a specific set-aside but encourages participation from Oregon COBID-certified small businesses. No estimated budget range or maximum funding threshold is provided in the RFP or Q&A document. The contractor assumes responsibility for developing silviculture prescriptions, conducting minor field verification workload as necessary, and maintaining consistency with U.S. Forest Service corporate data structure standards. All work product and intellectual property become the exclusive property of the U.S. Forest Service. Standard modeling tools including the Interagency Fuel Treatment Decision Support System and Landfire 2025 are required for fire and fuels analysis. The Forest Service will provide existing stand examination data, GIS files, cultural resource inventory plans, whitebark pine survey data, and invasive plant mapping to the awarded contractor. One contract will be awarded from this solicitation.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP: S-62900-00018091 – The Dalles Watershed Project GNA 2026 Q&A
The Dalles Watershed Project for the Barlow Ranger District on the Mount Hood National Forest Under Good Neighbor Authority 2026
RFP S-62900-00018091
Questions and Answers
Pre-Proposal Conference Questions & Clarification Requests:
1. For Section 3.1.1 Key Person Requirements, can one individual fulfill multiple position requirements? For example, the project lead and writer/editor can be the same person.
Yes, one individual can fulfill multiple Key Persons as long as they meet the qualifications.
2. For Task 9, does the Forest Service have current stand data or will stand exams need to be conducted?
Per the Statement of Work, pg. 31 for Task 9.1 (Exhibit A of Attachment A), “…data provided by MTHNF-PM, including but not limited to … stand data…”
3. Can you provide an estimated budget range or maximum funding threshold for this project?
Neither are being provided for this RFP.
• Clarification – There’s been no change to the project footprint despite the Grasshopper fire impacting the area.
Written Questions & Clarification Requests:
1. General Survey Efforts
a. Are the stated survey acreages (i.e., Section 4.2 on page 21; Section 5.1 on page 24; and Section 7.7 on page 27 of Attachment A), locations, and protocols considered final, or could the scope be refined based on existing data, access constraints, updated project design, or coordination with Forest Service specialists?
Information provided in Attachment A (Sample Contract) is the best available at this time.
b. Section 8.4 on page 31 of Attachment A specifies that connected actions necessary to implement the Proposed Action, such as road repair, must be identified. Is the Contractor expected to define site-specific locations requiring road repair/access work/other activities or can these activities be described in a more general conditions based management approach in the EA?
These activities are expected to be described in concise, general terms based on information provided to the awarded Contractor.
c. Sections 9.1, 10.2, 13.2, and 14.1 of Attachment A indicate that additional field verification may be required to support resource analysis. Is there a general scope of how much additional fieldwork could be required or how complete the existing natural resource data is?
In some cases, additional field verification may be needed to complete the effects analysis tasks or ensure project compliance with applicable laws and regulations (e.g. Clean Water Act, Endangered Species Act, etc.). In these cases, a minor workload at the discretion of the Contractor with the level of effort limited to that necessary to meet the tasks as specified is anticipated.
2. Section 2 of Attachment A states that an Emergency Action Determination (EAD) may be used. Should proposals assume that the project will proceed under the EAD process, or include time and effort for the standard NEPA process?
Assume the EAD process will be followed.
3. Task 7 on page 27 of Attachment A.
a. Does the Forest Service have an estimate of the number of previously unidentified cultural resources that may require documentation throughout the entire survey area?
Not beyond what is identified in Task 7.
b. Are cabins or other lodging available for field crews in the vicinity of the project area that the MHNF can provide to reduce field costs?
Contractor may request a camping permit from the Barlow District Ranger.
c. Will MHNF provide GIS files for High Probability, Medium Probability, and Low Probability areas at this time to aid with preparing the proposal?
Not at this time. These will be provided to the awarded Contractor once the Archaeological Investigations Permit is in place (see Task 7.2).
d. Does MHNF have a Cultural Resource Inventory Plan that needs to be followed?
If yes, will MHNF provide that at this time to aid with preparing the proposal?
This will be provided to the awarded Contractor .
4. Task 9. Silviculture Report and Prescriptions on page 31 of Attachment A. What proportion of the proposed treatment units already have sufficient stand examination data to support prescriptions and Forest Vegetation Simulator modeling? Are new stand examinations expected, and approximately how many individual prescriptions and marking guides should consultants anticipate?
All stand examination data is complete. If stands affected by Grasshopper Fire are recommended for treatment in the final proposed action, those may require updated exams. If additional work is deemed necessary by Agency and Mt.
Hood National Forest (MTHNF), it must be added through a properly executed written amendment to the Contract.
Number of prescriptions and marking guides will depend on the treatments proposed in the final proposed action; at least one for commercial units and one for non-commercial units. These may differ across the two to three distinct ecological zones within the Project Area.
5. Task 10. Fire and Fuels Report on page 32 of Attachment A. Is a quantitative, modeled approach to analyzing potential impacts of the proposed treatments required?
The Contractor shall perform standard modeling at the level necessary to generate relevant information for the fire and fuels report. Models typically include Interagency Fuel Treatment Decision Support System (https://iftdss.firenet.gov/iftdss2/#/landing) and Landfire 2025 (https://landfire.gov/), or similar models as approved by MHNF-PM.
https://iftdss.firenet.gov/iftdss2/#/landing https://landfire.gov/
6. Task 12. Botany and Invasive Species Report on page 34 of Attachment A. The area requiring botany fieldwork is not defined. Is there a specific acreage of botany fieldwork that is expected to be needed?
Significant botanical survey efforts have occurred in the past 15 years within the analysis area. Therefore, a minor workload at the discretion of the Contractor with the level of effort limited to that necessary to meet the tasks as specified is anticipated.
7. Task 16. Recreation and Visuals Report on page 37 of Attachment A. Are any visual simulations expected to be required?
No.
8. Task 18. Draft EA and FONSI on page 37 of Attachment A. Are socioeconomic resources expected to be an issue of concern and will any degree of socioeconomic analysis, either qualitative or quantitative, be required?
No specific socioeconomic analysis is required unless specific issues are raised under Task 8: Final Purpose and Need and Proposed Action.
9. Task 19. Comment Consideration Document on page 38 of Attachment A. Is there an anticipated level of public interest or number of comments that consultants should consider when budgeting for comment review and response?
Comments received on similar projects can be reviewed on MTHNF “pinyon public” where all prior planning documents are available.
10. Pricing – Attachment E – Price Proposal Form. Should the proposal include any additional pricing details beyond Attachment E – Price Proposal Form?
No.
11. RFP, Section 3.3.3, states that the proposer must send Attachment D to its References and that completed forms must be sent to the SPC before opening.
Attachment D itself states that "Proposer must submit this attachment with its proposal". Please clarify whether References should email completed forms directly to the SPC at Katrina Chinn at katrina.chinn@odf.oregon.gov, or if they should email their completed forms to the proposer to include in their proposal?
Proposer is to follow the process outline in the RFP Solicitation Document.
Please see Addendum 1 published on OregonBuys on 10/16/26.
12. Are there District- or Forest-level design criteria that should be incorporated into the EA along with the project-specific design criteria that will be developed by the contractor?
MTHNF does not have standardized design criteria but PDCs for similar projects can be reviewed on MTHNF “pinyon public” where all prior planning documents are available.
13. When does the Forest expect the EAD determination to be made?
Likely in spring 2027, prior to completion of the final proposed action.
14. Can the Forest Service and ODF summarize the level of public and tribal awareness and interest in this project and provide a summary of known or anticipated public and tribal concerns, including any major prior comments, opposition, or engagement from the City, the Collaborative groups, or other stakeholders?
Comments received on similar projects can be reviewed on MTHNF projects page https://www.fs.usda.gov/r06/mthood/projects or “pinyon public” where all prior planning documents are available.
https://www.fs.usda.gov/r06/mthood/projects
15. In Task 5.1, a total of 4,552 acres are to be surveyed with one visit in the spring 2027 and one visit in the fall of 2027. The survey windows for mollusk can vary greatly year to year and seasonally as to how long they are open with acceptable survey conditions. Is there any priority hierarchy of units to be surveyed within a survey season?
No.
16. Is there any possibility of extending mollusk surveys into the spring of 2028 for lower priority survey units?
No.
17. The number of survey acres per survey visit is provided in the SOW. Will the Agency provide unit boundary GIS data for these survey acres to help support the scoping of the field survey effort?
Unit boundary GIS data will be provided to the awarded Contractor. In general, survey units are a subset of the potential treatment units shown on the overview map in the appendix.
18. If unit boundary data is not available, is it possible to get any metrics regarding unit size and distribution?
In general, survey units are a subset of the potential treatment units shown on the overview map in the appendix.
19. Can the Agency clarify if the survey units tend to be smaller (1-20 acres) or do they tend to be larger?
In general, survey units are a subset of the potential treatment units shown on the overview map in the appendix. Some units are small, others are larger.
20. Can the Agency clarify if the survey units are dispersed widely across the project area or do they tend to be more clumped together in discrete areas?
In general, survey units are a subset of the potential treatment units shown on the overview map in the appendix.
21. Can the Agency identify the type of equipment (brand, model) of the recording units (ASUs) that ODF will provide and clarify whether they are completely passive or are they enabled to allow remote monitoring of unit/recording status?
The units are Instinct Environmental Automated Surveying Unit 3 (ASU 3) (https://www.instinctenvironmental.com/product/). These are active satellite enabled units, and the mobile and web app dashboards display the operational status (health), species observations, location coordinates, and memory storage space among other information. The onboard computer processes the data in near real time and data can be downloaded whenever a user has a need.
22. Is an intermediate-check of units required if there is an ability to review recorder status remotely?
There is no need for an intermediate check of any unit that is reporting normal status. As with any acoustic monitoring device and electronic devices in general, users should assume a small failure rate. Failure of memory modules should also be expected at low rates.
23. Is there an estimate of the total number of ASU needed to complete the entire survey effort in a single season? Would multiple rounds of ASU deployment be needed https://www.instinctenvironmental.com/product/ utilizing all 86 of the units to complete the survey effort prior to the July 30, 2027 reporting deadline specified in the SOW?
Attachment A (Sample Contract) states 84 ASUs will be provided for surveys (with two extra units provided as backups). There is a potential that additional ASUs may need to be deployed (up to 100 total units), dependent on outcome of survey design coordination with the US Fish and Wildlife Service. If additional work is deemed necessary by Agency and Mt. Hood National Forest (MTHNF), it must be added through a properly executed written amendment to the Contract.
All units are expected to be deployed at the beginning of the sampling period for six weeks with most (if not all) deployed by April 1 and retrieved by May 15.
Actual deployment date is dependent on accessibility related to snow conditions.
24. Task 6.4 states that all surveys must occur during the survey season of March 15 through August 31, yet there is a deadline of July 30, 2027 for all reporting. Is there a possibility the Agency will extend the deadline for the NSO Autonomous Recording Unit Survey Report to be able to utilize the final month (August 2027), of the NSO survey window for data collection, data processing and reporting?
All units are expected to be deployed at the beginning of the sampling period for six weeks with most, if not all deployed by April 1 and retrieved by May 15.
Actual deployment date is dependent on accessibility related to snow conditions.
25. Task 6.4 states that MTHNF will provide the ASU sample point locations. If these are already determined, could they be provided to help with scoping of the needed survey effort?
No. These will be provided to the awarded Contractor.
26. In Task 9.1 – Does standard error need to be verified from stand exam data that was collected for the project? And, if additional stand exam plots are needed to meet standard error who will be responsible for additional data collection?
No, this has already been completed.
27. Under Task 9.3, could the Agency clarify whether the Forest Service or the Contractor is responsible for developing the prescriptions used in FVS modeling?
Contractor responsibility.
28. Regarding Task 9.4, will the Forest Service be able to provide an LSR example from a previous project?
Yes, this will be provided to the awarded Contractor. See Regional Ecosystem Office Late-Successional Reserve Project-Level Consistency Reviews, August 5, 2009, guidance at https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf
29. Task 9.5 – Are model results expected to be field reviewed, or is the field review part of the stand exam collection?
No. See the purpose of modeling under Task 9.3 and the purpose of potential field verification (field visits) under Task 9.1 of Attachment A (Sample Contract).
https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf
30. The Biological Evaluation is due 8/31/2027; however, at that time the results of the terrestrial mollusk surveys will not be completed. Would this be a preliminary BE, to be completed once the mollusk surveys are complete?
The Biological Evaluation (BE) remains due 8/31/2027 using all available information at the time of preparation. There is potential that the BE and associated successor tasks may need to be updated after final surveys are completed. If additional work is deemed necessary by Agency and Mt. Hood National Forest (MTHNF), it must be added through a properly executed written amendment to the Contract.
31. To help contractors accurately gauge level of effort, could you please provide more information regarding US Forest Service (USFS) expectations regarding specific quantitative and qualitative habitat modeling that is required or envisioned for wildlife.
General expectation is that a wildlife biologist familiar with NSO eastside habitat types does qualitative ground truthing of modeled habitat.
32. Please provide any additional details regarding the level of effort required to coordinate Late Successional Reserve treatments. For example, identify meetings, memos, specific methods etc that the USFS envisions for LSR treatment planning and consistency analysis.
A minor workload at the discretion of the Contractor with the level of effort limited to that necessary to meet the tasks as specified is anticipated. Level of effort would depend on the final proposed action and if/how any LSR units deviate from desired conditions as listed in the LSR assessment. See Regional Ecosystem Office Late-Successional Reserve Project-Level Consistency Reviews, August 5, 2009, guidance at https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf
33. Please identify species to be evaluated in BA. Include any factors or assumptions that would help inform level of effort.
Standard industry practices shall be used to identify potential federally endangered, threatened, proposed, or candidate species in the action area, including generation of a U.S. Fish and Wildlife official species list (https://ipac.ecosphere.fws.gov/) and exploration of National Marine Fisheries Service’s West Coast Region Species and Habitat App (https://maps.fisheries.noaa.gov/portal/apps/webappviewer/index.html?id=e83 11ceaa4354de290fb1c456cd86a7f).
Reports for similar projects can be reviewed on MTHNF projects page https://www.fs.usda.gov/r06/mthood/projects or “pinyon public” where all prior planning documents are available.
34. Whitebark pine is present in small portions of the project area and may overlap some commercial and non-commercial treatment areas. Please clarify if MTHNF has existing survey data for white bark pine presence and whether treatment prescriptions already take into account white bark pine locations (e.g. are there non-commercial treatment areas in place that are intended to enhance white bark pine habitat?).
Existing survey data and habitat map will be provided to the awarded Contractor.
https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf https://www.fs.usda.gov/r6/reo/landuse/lsr/downloads/reviews/documents/lsr-concurrence-review-criteria-final-20220315.pdf https://ipac.ecosphere.fws.gov/ https://maps.fisheries.noaa.gov/portal/apps/webappviewer/index.html?id=e8311ceaa4354de290fb1c456cd86a7f https://maps.fisheries.noaa.gov/portal/apps/webappviewer/index.html?id=e8311ceaa4354de290fb1c456cd86a7f
35. Given the size of the planning area, could the Agency provide general guidance on the nature of noxious weed surveys needed? Should proposers anticipate comprehensive surveys, or more targeted surveys focused on disturbance-prone habitat (treatment areas, roadsides, meadows) and more locally-problematic species?
A minor workload at the discretion of the contractor with the level of effort limited to that necessary to meet the tasks as specified is anticipated, generally focused along roads and timber haul routes.
36. Regarding data collection and GIS deliverables; is there an expectation to deliver data in a FS-specific GIS schema? If so, please share the database or tables showing the required data domains.
Relevant, resource-specific feature classes, rasters, and tables and required schema elements (e.g. fields and attribute domains) will be provided in a geodatabase, along with associated metadata to the awarded Contractor.
Contractor is expected to maintain consistency with the provided schema and compatibility with USFS corporate data structure (https://www.fs.usda.gov/about-agency/enterprise-data-warehouse).
37. Given that this project has been in the planning phase for some time; are there changes to the footprint and related survey efforts due to the 2026 Grasshopper fire?
The awarded Contractor will work with ODF and the Forest Service as field survey data are collected and the final proposed action is developed to suggest whether units within the Grasshopper Fire still require treatment to meet the purpose and need.
38. Can the Agency provide if botanical surveys been conducted within the last 5-10 years over the entire 958 acres? If yes, did those include invasive plant mapping?
Significant botanical survey efforts have occurred in the past 15 years within the analysis area. Therefore, a minor workload at the discretion of the Contractor based on their needs in order to meet the tasks as specified is anticipated. Invasive plant mapping would likely be focused along roads and timber haul routes.
39. Will maps or GIS data layers be provided for invasive plant populations?
Yes, to the awarded Contractor.
40. How many stream miles require field verification?
Field verification will be based on ground truthing of existing LiDAR data using a very simplified field protocol. A rough approximation can be ascertained from the Project Overview Map in Exhibit D of Attachment A (Sample Contract).
41. How many road-stream crossings require assessment?
All road-stream crossings on timber haul routes within the Project Area.
Number to be determined during evaluation of existing LiDAR and hydrology datasets. A rough approximation can be ascertained from the Project Overview Map in Exhibit D of Attachment A (Sample Contract).
42. What stream classification protocol must be followed?
A simple 5-page protocol ground truthing lidar data to locate and specify type of hydrologic feature will be provided to the awarded Contractor.
43. What level of wetland/spring/seep mapping is expected?
https://www.fs.usda.gov/about-agency/enterprise-data-warehouse
A general estimated GIS polygon would be requested, not just a point feature.
44. Are quantitative hydrologic analyses or modeling required and what method is expected?
Not required.
45. What GIS data and previous inventories will be provided?
Standard Forest Service and public datasets.
46. Can the Agency provide a sample hydrology report and geodatabase from a similar project?
Reports for similar projects can be reviewed on MTHNF projects page https://www.fs.usda.gov/r06/mthood/projects or “pinyon public” where all prior planning documents are available.
47. Do USFS existing soil inventories include data that covered the entire proposed project area?
Yes, this will be provided to the awarded Contractor.
48. Does USFS have existing topography data for the project area?
Yes, this will be provided to the awarded Contractor.
49. Is the preferred protocol for ground-truthing the Forest Soil Disturbance Monitoring Protocol (FSDMP), which is the standard agency-recommended methodology (Page- Dumroese et al., USDA Forest Service GTR-WO-82a)?
Yes.
50. Could the Agency provide the sample report for recreation and visual as described in the SOW?
Reports for similar projects can be reviewed on MTHNF projects page https://www.fs.usda.gov/r06/mthood/projects or “pinyon public” where all prior planning documents are available.
51. Does MTHNF have a preferred fisheries report template that already addresses FSM
2672.4 requirements?
Reports for similar projects can be reviewed on MTHNF projects page https://www.fs.usda.gov/r06/mthood/projects or “pinyon public” where all prior planning documents are available.
52. What fisheries data will be provided (fish surveys, habitat surveys, redd counts, snorkel surveys, eDNA, passage inventories, aquatic habitat inventories)?
Existing fisheries habitat data in Forest Service and state databases and species distribution data will be provided to the awarded Contractor.
Contractor will, as needed, conduct field verification of hydrologic features (e.g. seeps and streams) under Task 13.2.
https://www.fs.usda.gov/r06/mthood/projects