QA_WASSON_2-2-2024.docx

DOCX document 24 KB Posted

Attached to
Wasson Creek Watershed Ridgetop-to Estuary Restoration Project
Solicitation number
S-DASOBO-00009132
Issued by
Coos County, Cheshire CDP, Oregon

About this file

This document is a Questions and Answers (Q&A) document related to the Wasson Creek Restoration Project Request for Proposal (RFP) #S-DASOBO-00009132, issued by the South Slough National Estuarine Research Reserve (SSNER). The RFP seeks services for the Wasson Creek Watershed Ridgetop-to-Estuary Restoration Project in Oregon. The Q&A provides responses to questions about insurance requirements, marking/ribbon protocol for unit boundaries and skips/gaps, and the availability of GIS shapefiles to assist with bidding, including forest management unit boundaries, skip/gap points, fire danger areas, no-touch access areas, roads, trails, gates, streams, property lines, and known protected resources. The document also clarifies that a contractor's license is not typically required for this type of forestry project.

Regarding pricing and other salient information, the document does not mention any specific pricing terms, set asides, incumbents, funding requirements or sources, or contract renewal options. The focus is on providing clarification and additional information to assist potential bidders in preparing their responses to the RFP.

View the file

Other files

File Type Posted
AttC-Proposer-Info-Cert~2.doc DOC document
AttB_Disclosure-Exempt~4.doc DOC document
REV_WASSON-CREEK-RFP_Final_Clean_1-22-2024.doc.pdf PDF
Amendment-1_to_WassonCreekRFP_9132_2-16-2024.doc DOC document
Att_E_PriceProposal_1-11-2024.docx DOCX document
AttG-Resp_Inquiry.doc DOC document
Sample Contract.doc DOC document
Wasson_Ins_Reqs_RAT_2-1-2024.docx DOCX document
AttF_COBID~4.doc DOC document
Exhibit1_SOW_Wasson_ForestryK_South-Slough_Final_cleanDOJpropchanges_1-18-2024.docx DOCX document
AttD - Reference check form~2.doc DOC document
00009133_Preliminary Bid Results.xlsx XLSX spreadsheet
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS & ANSWERS DOCUMENT RE:

WASSON CREEK RESTORATION PROJECT OB RFP #S-DASOBO-00009132

1.

Q1: RFP 5.3.1 Insurance: Can you provide the insurance limits that will be required for this contract?

ANSWER: See attachment labeled Insurance Exhibit - Services.

2.

Q2: What is the marking/ribbon protocol for the unit boundaries and skip/gap locations?

ANSWER: orange unit boundary ribbon and printed boundary posters; blue for gaps, pink for skips, Red/white stripes for access trails.

3.

Q3: Can you provide the following GIS shapefiles to assist with bidding:

0. Forest management unit boundaries

0. Skip/Gap points

0. S/SE Aspect (higher fire danger) areas shown in Figure 4 of the SOW

0. Any areas that are “no-touch” for access or cable logging tailholds

0. All existing roads, trails, gates, streams

0. SSNER property lines

0. Any known protected resources, if those resources will affect the project/project timing

ANSWER: I have added the shapefiles to this Box Folder: https://oregonstatelands.app.box.com/v/ssnerr-download/folder/247267775659 Individual responses to specific requests:

a. Forest management unit boundaries. A: Shapefile included

b. Skip/Gap points A: Shapefile included

c. S/SE Aspect (higher fire danger) areas shown in Figure 4 of the SOW A: Shapefile included

d. Any areas that are “no-touch” for access or cable logging tailholds A: all areas outside unit boundaries should be considered no-touch, however, specific requests can be assessed as needed.

e. All existing roads, trails, gates, streams A: Access roads and streams shapefile included. Stream shapefile does not distinguish between perennial/ephemeral or fish bearing/non-fish bearing. Gates are located at intersection with West Beaver Hill Road and the two southern access roads in the PA and on the first access road off Hinch Road, where is splits and short spur road heads west. No official trails in PA, access trails are still being mapped.

f. SSNER property lines A: Shapefile included

g. Any known protected resources, if those resources will affect the project/project timing. A. There are no areas of cultural resource concerns in the unit boundaries, an inadvertent discovery plan is included (Wasson Restoration Plan Appendix F) as needed. Occupancy of marble murrelet may influence the timing. Two years of surveys will be completed by August 5th, 2024, until that date assume occupancy and adhere to timing restrictions. If occupancy is recorded prior to August 5th, 2024, then all subsequent work will adhere to seasonal and timing restrictions within the occupied site. The PA is divided into 5 sites, therefore occupancy in one site will not affect work in other sites. Site shapefile can be shared upon request.

4.

Q4: Exhibit E of the Sample Contract states that we must be registered under ORS Chapter 701 if required. Will we be required to register as a construction contractor? A Contractor’s License is not typically required for forestry projects.

ANSWER: No, this registration will not be necessary.