Q&A Memo-RFQ FL 090226.pdf
PDF 303 KB Posted
- Solicitation number
- 2138032
- Issued by
- Warren County, New York
About this file
This is a Questions and Answers memo issued by the New York State Office for People With Developmental Disabilities (OPWDD) Contract Management Unit in response to inquiries regarding RFQ FL 090226 for temporary fence installation around Building 59 at the Finger Lakes Developmental Disabilities State Operations Office Newark Campus in Wayne County. The project requires design, procurement, and installation of approximately 1,600 linear feet of temporary chain-link fencing with a minimum of two 10-foot swing gates, with work to be completed within 120 working days of contract approval. A mandatory site visit was held on August 19, 2026, with quotes due by September 2, 2026. The procurement is restricted to MWBE-certified, SDVOB-certified, or New York State small business contractors, with two separate postings issued for the same work but only one award to be made.
The Q&A memo addresses technical specifications and contracting procedures relevant to bidders. Key clarifications include confirmation that all three fence rails (top, middle, and bottom) are required; corner posts must be 3 inches in diameter; only SCH40 pipe is acceptable, not Class B Steel Tubing; and galvanized fabric must meet ASTM A 392 class II specifications with 2.0 ounces per square foot. The memo confirms that no non-collusion form, bid bond, or retainage is required. Payment will be made in accordance with New York State Finance Law upon the Bronx Developmental Center's receipt of a complete and accurate invoice upon completion of work. The project is subject to prevailing wage requirements as a New York State Public Works project, and contractor responses must remain valid for 120 days from the due date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ FL090226.pdf | ||
| Mandatory Supporting Documents.pdf | ||
| Exhibit A-Fence Installation Location.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KATHY HOCHUL
Governor
WILLOW BAER
Commissioner
OPWDD Contract Management Unit 25 Center Circle, Wassaic, NY 12592 │ www.opwdd.ny.gov │ TEL: 845-877-6821 | eny.nyc.li.contracthub@opwdd.ny.gov
August 24, 2026
Re: RFQ FL 090226
Questions and Answers:
Below is a compilation of the questions received for this Request For Quotes. Questions that were repeated, or of a recurring nature, were consolidated. Thank you very much for your interest.
1. Question: Are all three (Top, Middle & Bottom) Rails required for the proposed fence?
Answer: Yes
2. Question: Please clarify pipe size for corner posts.
Answer: 3 inches.
3. Question: Is Class B Steel Tubing (SS40) Pipe acceptable in lieu of SCH40 pipe?
Answer: No.
4. Question: Is 1.2 OZ per square foot Galvanized Fabric acceptable?
Answer: Bid what is specified - Galvanized Finish: ASTM A 392 class II zinc coated after weaving, with 2.0 ounces per square foot.
5. Question: How many days after the first invoice will the Contractor be paid?
Answer: Contractors will be paid in accordance with NYS finance law upon the BSC’s receipt of a complete and accurate invoice upon completion of work.
6. Question: Do we need to submit a non-collusion form with the bid?
Answer: No
7. Question: Does this bid require a bid bond?
8. Question: Are you holding retainage?