Questions & Answers for DCMR Kitchen Renovation U. S. Embassy Ankara, Turkiye
Solicitation number
19TU1526Q3003QA
Issued by

About this file

This is a Questions and Answers document for the U.S. Embassy Ankara kitchen renovation solicitation (19TU15-26-Q-3003). The document addresses eight questions received from potential bidders as of August 9, 2026, regarding the DCMR Kitchen Renovation project.

Key clarifications include: bidders must submit technical specifications for all materials including kitchen cabinets, countertops, sinks, faucets, and wall and floor tiles; the location shown in the concept design prevails over any contradictory renderings; debris and waste removal is permitted only during working hours between 08:00 and 17:00; proposed materials such as Vitra/Kale brand antislip tiles are acceptable if they comply with SOW technical specifications; the refrigerator will be a standard double-door model and the existing dishwasher will remain unchanged; garbage disposers and water treatment systems are explicitly excluded from the scope; and no additional accessories or equipment are required beyond those already specified in the SOW. The document does not address deadline extensions for material lead times, indicating the bidding schedule remains as originally established.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. EMBASSY ANKARA, TÜRKİYE

SOLICITATION FOR the DCMR Kitchen Renovation

ANSWERS TO QUESTIONS 19TU15-26-Q-3003

Below is the list of questions received as of 08/09/26 and their respective answers:

1. What are the specifications/properties of the materials used for kitchen cabinets, countertops, sinks, faucets, and wall and floor tiles?.

Answer: As already stated in the SOW, bidders are required to submit the technical specifications of the materials they intend to use for the project.

2. The bidding period seems short due to material lead times. Could you please extend the deadline?

Answer: The location shown in the concept design shall be taken into consideration.

3. After what time in a day we may dispose of debris from the site?

Answer: Debris and waste may be removed from the site during working hours, between 08:00 and 17:00.

4. The sink and faucet location in render contradicts with current site location. Could you please advise which one prevails?

Answer: The location shown in the concept design shall be taken into consideration.

5. Could you please inform the brand and model of the refrigerator and dishwasher to collect the size information?

Answer: The refrigerator will be a standard double-door refrigerator. The dishwasher will not be replaced; the existing standard dishwasher will remain in use. In addition, the dimensions of these appliances are not expected to have any impact on the project cost.

6. We intend to use Vitra/Kale brand antislip tiles. Could you please confirm if these local brands will be acceptable or if we will be required to use imported products?

Answer: The proposed materials may be used provided that they comply with the technical specifications stated in the SOW.

7. Garbage disposer under sink and water treatment for the faucet will not be included in proposal. Could you please confirm?

Answer: The garbage disposer under the sink and the water treatment system for the faucet will not be included in the scope of the proposal.

8. Spoon holder and knife holder are included in proposal. Could you please inform if there is any further need?

Answer: No additional accessories or equipment are required beyond those already specified