PWS Trunked.docx
DOCX document 50 KB Posted
- Attached to
- LMR Trunking System for Ebbing ANGB
- Solicitation number
- F1T0AM4325AC01
About this file
This Performance Work Statement (PWS) outlines requirements for installing a trunked repeater system at the 188th Wing Communications Flight at Fort Smith Regional Airport in Arkansas. The contractor must provide installation, documentation, configuration, testing and commissioning of a solution that integrates with existing Motorola APX 6000 ELMR equipment and RF infrastructure within 150 days of award.
The system requires installation of specific components including 6 VHF GTR 800 trunking channels, 2 DSC 8000 site controllers, SRX 345 site gateway, RF mixing combiner, transmission lines and antennas, tower UPS, and workstation equipment. Key requirements include P25 Phase II TDMA/FDMA dual mode capability, software integration, pre-installation planning, system testing, one year of maintenance support, security monitoring, and training. The contractor must provide 24/7/365 security monitoring, remote security patch installation, and routine maintenance. The government will provide site access, permits, frequencies, space for equipment, and structural analysis of existing infrastructure.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
Performance of Work Statement Trunking System Installation
27 January 2025
188th Wing, Communications Flight, Arkansas Air National Guard
Fort Smith Regional Airport 4850 Leigh Avenue Fort Smith, AR
Table of Contents
1.0 DESCRIPTION OF INSTALLATION:
2.0 BACKGROUND:
3.0 REQUIREMENTS
4.0 GOVERNMENT SHALL
5.0 DISPOSAL
6.0 ENVIORNMENTAL
7.0 DELIVERABLES
8.0 PERFORMANCE STANDARDS
9.0 BASE HOLIDAYS
10.0 SECURITY REQUIREMENTS
1.0 DESCRIPTION OF INSTALLATION:
1.1 Contractor will be required to provide installation, comprehensive documentation of the installation, configuration, testing, and commissioning processes of the proposed solution. They will take advantage of all asset capabilities of the current Motorola APX 6000 ELMR, Motorola Consolettes, and other associated RF equipment. Contractor shall provide a warranty for the installed equipment. Equipment must provide seamless integration of associated software and programming of ELMR equipment, RF trunking infrastructure, and ELMR equipment. In totality the desired outcome of the proposed solution shall provide seamless operation between end item equipment listed herein. Upon completion of installation the contractor shall provide testing and commissioning to ensure system is fully functional. The contractor shall complete delivery and installation with 150 days from the date of award. The place of performance for the installation will be located at 4850 Leigh Ave, Fort Smith, AR 72903 Building 444.
2.0 BACKGROUND:
2.1 188th Communication Flight requires the installation and programming of a Trunked Repeater System to accommodate the influx of radio communication to support FMS mission sets. The current Radio Frequency (RF) infrastructure system is a Very High Frequency (VHF) conventional repeater system comprises of three Generalized Trunking Radio (GTR) 8000 Repeaters, duplexers, and antennas located at Building 444. The current infrastructure does not meet required capabilities to handle the influx of communication traffic required by the future pilot training center at Ebbing ANGB. A proposed solution will need to have capabilities including increased Radio Frequency (RF) traffic management, Over-the-Air-Rekeying (OTAR), and operate in dual dynamic mode providing both Time Division Multiple Access (TDMA) and Frequency Division Multiple Access (FDMA) capabilities to allow the use of Ebbing’s current FDMA radio equipment and providing interoperability with recent acquisition of Motorola Electronic Land Mobile Radio (ELMR) equipment operating in TDMA. TDMA will allow modernization, standardization, and provide Spectrum efficiency leading into the future meeting DoD requirements. This installation shall include the following equipment:
2.1.1 (6) VHF GTR 800 Trunking Channels
2.1.2 (2) DSC 8000 Site Controllers
2.1.3 (1) SRX 345 Site Gateway, RF Mixing (Tx/Rx Combiner)
2.1.4 (1) Tx Antenna and Transmission Lines
2.1.5 (1) Rx Antenna and Transmission Lines
2.1.6 (1) Tower Uninterruptible Power Supply (UPS)
2.1.7 (1) SRX 345 Site Gateway
2.1.8 (1) EX4100 Site Switch
2.1.9 (1) Z2 G9 Workstation(1) 22” Monitor
3.0 REQUIREMENTS
3.1 Software Integration:
3.1.1 Install the necessary software to enable P25 Phase II Time Division Multiple Access (TDMA) on the 10-Channel RF Site Configuration: Configure the system to support both P25 Frequency Division Multiple Access (FDMA) and P25 TDMA to provide efficiency and interoperability to accommodate a diverse fleet of user and mobile radios.
3.2 Pre-Installation and Planning
3.2.1 Conduct kickoff meeting prior to installation.
3.2.2 Perform site evaluation, conduct design review, and planning of project.
3.2.3 Revise design based on any agreements made post-design review to accommodate specific site conditions or constraints.
3.3 Integration
3.3.1 Integrate the trunking system with existing communication infrastructure.
3.3.2 Perform system compatibility testing to ensure interoperability with current equipment, such as Land Mobile Radio (LMR) equipment.
3.4 Testing and Commissioning
3.4.1 Conduct pre-and post-installation testing to ensure the system meets the operation and performance standards
3.4.2 Provide detailed test reports and address any deficiencies.
3.5 Training & Documentation
3.5.1 Conduct user and administrator training sessions.
3.5.2 Provide comprehensive system documentation, including operating manuals, configuration guides, and maintenance schedules.
3.6 Removal and Disposal of Existing Equipment
3.6.1 Uninstall and remove any existing equipment and deliver to 188th personnel for disposal.
3.7 Security and Updates
3.7.1 Provide Remote Security Patch Installation to install security updates that are pre-tested by Motorola Solutions
3.7.2 Offer Security Monitoring to provide 24x7x365 monitoring of the radio network's security elements.
3.7.3 Commit to sustaining the ASTRO 25 system through a program of software and hardware updates aligned with the ASTRO 25 platform lifecycle
3.8 Maintenance and Client Support
3.8.1 Provide one year of maintenance support, beginning from the date of final system acceptance.
3.8.2 Perform routine preventative maintenance, including system diagnostic and updates.
3.8.3 Respond to critical system failures within the hours set forth in this PWS.
3.8.4 Ensure access to spare parts and technical support throughout the maintenance period.
3.8.5 Submit quarterly maintenance reports detailing performed services, system performance metrics, and any recommended improvements.
4.0 GOVERNMENT SHALL:
· Obtain and provide zoning approvals, permits, and lease agreements for all the proposed sites and locations as required.
· Obtain and provide authorized frequencies.
· Provide adequate space for the system equipment.
· Provide site acquisition and development, electrical work, HVAC, grounding systems, provisioning of emergency power systems (e.g. backup generators), cable entry panels, wall penetrations and core drilling, and support equipment for cable runs (cable tray, ice-bridge, conduit, etc.).
· Provide backhaul network connectivity to the AETC Core for the proposed sites.
· Perform structural analysis of existing tower and rooftops as required.
5.0 DISPOSAL:
5.1 Residue, debris, other materials left over from removal and/or installation will be carried off base and disposed of by the contractor in compliance with laws, ordinances, and codes. Work area will be kept clean and neat, maintained in a hazard free and orderly condition.
6.0 ENVIORNMENTAL:
6.1 CONTRACTOR shall be responsible for compliance with EPA/ADEQ requirements and is required to provide a list of proposed hazardous materials that will be used on the project to the Base HAZMART representative prior to commencing work (FAR 52.223-3), (DFARS 252.223-7001)
7.0 DELIVERABLES
| DELIVERABLE |
| DUE DATE |
| DESCRIPTION |
| Installation Plan |
| (TBD) |
| Detailed plan for installation services. |
| Test and Evaluation Plan |
| (TBD) |
| Procedures for systems testing and validation. |
| Training Materials |
| (TBD) |
| Training guides, schedules, and system manuals. |
| Final System Configuration |
| (TBD) |
| Fully operation and tested Motorola trunking system. |
| Quarterly Maintenance Reports |
| (Quarterly) |
| Reports on maintenance activities and system status |
8.0 PERFORMANCE STANDARDS
| TASK |
| PERFORMANCE STANDARD |
| ACCEPTABLE QUALITY LEVEL (AQL) |
| METHOD OF SURVEILLANCE |
| System Installation |
| System Installed per specific actions |
| 100% |
| Inspection and functional testing. |
| System Integration |
| Interoperability with existing systems |
| 100% |
| Testing and Certification. |
| Training Delivery |
| Training conducted effectively. |
| 95% |
| Feedback from participants. |
Maintenance Support
| Issues resolved within specified timeframes |
| 100% |
| Maintenance Reports and Audits |
9.0 BASE HOLIDAYS
9.1 Contractor personnel are not required to work on those holidays listed in the DOL Wage Determination as cited below:
| New Year’s Day |
| 1 January |
| Martin Luther King’s Birthday |
| 3rd Monday in January |
| President’s Day |
| 3rd Monday in February |
| Good Friday |
| Friday before Easter |
| Memorial Day |
| Last Monday in May |
| Independence Day |
| 4 July |
| Labor Day |
| 1st Monday in September |
| Columbus Day |
| 2nd Monday in October |
| Veterans Day |
| 11 November |
| Thanksgiving Day |
| 4th Thursday in November |
| Christmas Day |
| 25 December |
NOTE: Any of the above holidays falling on a Saturday will be observed on the preceding Friday. Holidays falling on a Sunday will be observed on the following Monday.
10.0 SECURITY REQUIREMENTS
10.1 The contractor shall comply with security requirements at Ebbing Air National Guard.