PWS Troubleshoot 400V SFL System.docx
DOCX document 31 KB Posted
- Attached to
- Offutt Runway Light Troubleshooting
- Solicitation number
- FA4600_RunwayLightTroubleshooting_SourcesSought
About this file
This Performance Work Statement (PWS) details troubleshooting requirements for the Sequenced Flashing Light (SFL) system at Runway 31, Offutt Air Force Base in Nebraska. The scope involves comprehensive diagnostic and repair work on the 400VDC Approach Lighting System, including examination of the Master Cabinet, programming computer, and individual control cabinets. Key objectives include verifying system functionality, correcting anomalies, checking firmware and software installations, and conducting an operational test in the presence of a Contracting Officer.
The contract has a 30-day performance period, with work to be conducted between 0730 and 1630 hours, excluding weekends and federal holidays. Contractors must comply with specific safety and security requirements, including possessing government-issued photo identification, adhering to base speed limits, and potentially obtaining restricted area badges. The work requires conforming to various industry standards including NFPA, OSHA, and Air Force Instructions, with all repair and troubleshooting costs to be included in a lump sum price. The equipment furnished will be guaranteed against defects for at least one year from the date of acceptance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement (PWS)
Troubleshoot Sequenced Flashing Light (SFL) system F607
1. Scope: The work covered by this Performance Work Statement (PWS) consists of all labor, equipment, and materials, and performing all work required to troubleshoot the following components of the RWY 31 400VDC Approach Lighting System with Sequenced Flashing Light - Category 2 (ALSF-2) System: Master Cabinet, programming computer, and faulty individual control cabinets.
2. Location of Work: The work location is at Runway 31 approach field, Facility 607, Offutt AFB, Nebraska.
3. Major Items of Work:
Master Control Cabinet and Individual control cabinets:
• Verify proper function
• Correct any anomalies found.
Programming Computer:
· Verify all Firmware, software, and patches are installed as required
· Verify function of the Dongle used to connect to the Sequenced Flashing Light (SFL) System.
Test/Inspect/Certify (after troubleshooting):
• After the troubleshooting is completed, and at such time as the Contracting Officer may direct, the contractor shall conduct an operating test for approval.
• The contractor shall demonstrate functionality of SFL system.
• The test shall be performed in the presence of the Contracting Officer or an authorized representative. The contractor shall furnish all of the instruments and personnel required to perform the tests.
4. Codes: All work and personnel shall conform to the latest applicable NFPA, OSHA, Air Force Instructions (AFI), United Facilities Criteria (UFC) 3-535-01, and other Industry Standards.
a. UFC: http://www.wbdg.org/ccb/browse_cat.php?c=4
5. Occupancy: During maintenance the Government will occupy the existing facilities. The contractor shall not restrict nearby pedestrian or vehicular traffic to this facility and shall coordinate construction with the Contracting Officer’s Representative to minimize conflicts and to facilitate usage. The contractor shall perform the work so as not to interfere with ongoing operations.
6. Coordination: The contractor shall coordinate and properly relate the work to be done to the site and to the work of all the trades. The contractor shall visit the premises and thoroughly familiarize him or herself with all the details of the work to be done and the working conditions. The contractor shall verify all of the dimensions in the field and advise the Contracting Office of any discrepancy before performing any work. If any conflicts arise during work necessitating departure from the Performance Work Statement (PWS), details of the departure and the reasons for the departure shall be submitted to the Contracting Office for written approval.
7. Submittals: The contractor shall submit two copies of inspection certifications and any applicable letters of findings to the Contracting Office.
8. Repair of Work: The work shall be carefully laid out in advance. Where cutting, channeling, chasing, or drilling is necessary, it shall be done carefully. Any damage to buildings, piping, or equipment, shall be repaired by workers skilled in that particular trade, at no additional cost to the Government.
9. Clean Up: The contractor shall assure that the work area is cleaned up at the end of each day. Debris and trash shall be removed and properly disposed of by the contractor outside the confines of Offutt AFB.
10. Work Schedule: The working hours for this contract shall be between 0730 and 1630 hours daily, excluding Saturdays, Sundays, and Federal Holidays.
11. Performance Period: 30 Days
12. Use of Utilities: All reasonable quantities of utilities will be made available to the contractor without charge. Any temporary connections of lines that may be required will be installed, maintained and removed by the contractor at his own expense and in a manner satisfactory to the Contracting Officer. Removal of such connections or lines shall be accomplished prior to final acceptance of the contract.
13. Guarantee: The equipment furnished under this contract shall be guaranteed against defective materials, design, and workmanship for the full warranty time which is standard with the manufacturer and/or supplier, but in no case less than one year from the date of acceptance either for beneficial use or final acceptance (whichever is earlier). Upon receipt of notice, from the Government, of failure of any part of the guaranteed equipment, during the guarantee period, the affected part or parts shall be replaced promptly with new parts at the expense of, and by, the contractor.
14. Payment: All of the costs in connection with this contract shall be included in the lump sum price for all of the work to be performed under the contract.
15. Government Furnished Equipment: None
16. Security and Safety Requirements: The contractor shall comply with all requirements and procedures IAW FAR 5353.242-9000, Contractor Access to Air Force Installations.
Personal Security Requirements
• Contractor personnel shall be in possession of Government issued photo identification at all times while on Offutt AFB, and coordinate with Contracting Officer Representative (COR) through the Contracting Office for entry onto the Security Force’s Visitors List.
• Except where otherwise posted, the speed limit on Offutt AFB is 25 MPH. Seatbelts shall be worn at all times by driver and all passengers. Cellphone use is prohibited while driving anywhere on Offutt AFB, except while using hands-free device. All vehicles and personnel are subject to search at any time while on Offutt AFB.
Restricted Area Badges
• If necessary, the COR shall coordinate with Using Agency Facility Manager (UAFM) to obtain a United States Air Force (USAF) Restricted Area Badge for all personnel who require unescorted entry into a restricted area(s) for specific work, for the duration of the contract. It is the responsibility of the UAFM to assist the contractor and his/her employees in initiating a DD Form 254, DOD Contract Security Classification Specification, through the Unit Security Manager (USM). If for any reason the UAFM cannot assist the contractor in the processing paperwork for restricted area badges, it is their responsibility to provide escorts. It is the contractor’s responsibility to fully document all cases where entry to restricted areas was not granted. All contractor personnel shall have proper identification prior to entry into restricted areas. It is the responsibility of each UAFM to brief all contractor personnel working in their area on procedures and policies of their particular restricted area.
17. Final Inspection: Contractor will remove material and construction equipment from the site. Contractor will provide submittals and turn in appropriate badges.