PWS Sector Chiller Pump Feb 2024.docx

DOCX document 2 MB Posted

Attached to
Chill Water Pump Repairs at SECTOR HOUSTON
Solicitation number
70Z02924QNEWO0004
Issued by

About this file

This solicitation requests quotes for chill water pump repairs and piping inspection at the US Coast Guard SECTOR Houston facility. The Coast Guard seeks a contractor to provide all labor, materials and equipment to replace an existing chill water pump and inspect piping suspected of leaks. Quotes are due to Joshua Calderon by email no later than the solicitation closing date. The requirement is set aside exclusively for small businesses. The contractor must visit the site and be familiar with existing conditions. The award will be a firm-fixed-price purchase order to the lowest bidder meeting standars. The NAICS code is 238220 and small business size standard is $19 million.

View the file

Other files

File Type Posted
SF1442-22 Chiller Pump.pdf PDF
Wage Determination for Harris County.pdf PDF
Construction Clauses Provisions FAC 2023-01.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

BASE GALVESTON

Performance Work Statement

FOR

Sector Chill Water Pump Repairs & Identify Chill Water Line Corrosion and Leaks

AT

USCG SECTOR HOUSTON

134111 HILLARD St. Houston, TX 77034

Table of Contents

1. GENERAL

1.1 GENERAL REQUIREMENTS

1.2 LOCATION

1.3 POINTS OF CONTACT

1.4 SITE INVESTIGATION

1.5 CONTRACTOR SECURITY REQUIREMENTS PROJECT SYNOPSIS

2. SCOPE OF SERVICES

2.1 FIELD INVESTIGATION

2.2 DESCRIPTION OF WORK TO BE COMPLETED

3. PROPOSAL SUBMITALS

3.1 SITE VISIT REPORT

3.2 ESTIMATE

3.3 SUBMISSION

4. CONSTRUCTION NOTIFICATIONS

4.1 NOTIFICATIONS

4.2 RECYCLING AND DISPOSAL OF REFUSE

4.3 SAFETY

4.4 TEMPORARY FACILITIES STORAGE

4.5 SANITARY FACILITIES

4.6 WATER AND ELECTRICITY

4.7 REFERENCE DRAWING

4.8 CONTRACTING REQUIREMENTS

5. COAST GUARD PROCUREMENT SELECTION

4.1 BID PROCEDURES

4.2 QUESTIONS

6. REFERENCE DOCUMENTS AND PHOTOS

1. GENERAL

1.1 GENERAL REQUIRMENTS

The United States Coast Guard is accepting quotes for qualified individuals or firms to Provide all labor, materials, and equipment necessary to replace existing chill water pump with new pump and inspect chill water piping in space suspected of leaking located at USCG SECTOR Houston. Prior to submitting a quote, it is mandatory to examine the Performance Work Statement (PWS) and it is highly recommended to visit the facility to take field measurements, evaluations, etc., and become familiar with existing conditions under which the work will be performed.

1.2 LOCATION:

Project site is located at USCG SECTOR HOUSTON 134111 Hillard St. Houston TX, 77034

1.3 POINT OF CONTACT:

A. Facility Engineer

a. LT Jordan Groff (786) 295-2688

b. CWO Ruben Santellanes (325) 518-8930

c. Mr. Nashaun Hawkins: o. (409) 766-4856; m. (847) 627-0653

1.4 SITE INVESTIGATION

Investigate the site per FAR 52.236-3 to ascertain the general and local conditions which can affect the work or its cost. Contact Mr. Tim Florez for site access. Perform all on-site work between the hours of 7:00 AM and 4:00 PM, Monday through Friday (Federal Holidays excluded), unless otherwise approved by the Facility Engineer (FE).

1.5 CONTRACTOR SECURITY REQUIREMENTS:

For this affected Coast Guard facility/property, the Contractor shall provide a list of all on-site personnel, including sub-contractors and suppliers, to the Facilities Engineer. The contractor shall update this list when changes occur. Contractor personnel not listed may be denied access to the Coast Guard facility. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard facility. Contractor personnel shall have photo identification at all times while working on Coast Guard facilities. Contractors shall provide Point of Contacts (POCs) in 1.3 with 24 hours of advance notice of every delivery to the site (e.g., concrete, lumber, parts, etc.) and provide the company name, delivery person, and phone number of the firm(s) making deliveries. All vehicle access to government property requires vehicle registration and proof of liability insurance. Otherwise access to the Coast Guard facility may be denied.

2. SCOPE OF SERVICES

2.1 FIELD INVESTIGATION

Contractor shall conduct a thorough field investigation for the project. Inspection shall identify and document existing site conditions, specifically the location of all utilities (i.e., electric, water, sewer, gas etc.) or shared systems (Example: HVAC, Fire Suppression, Network) to identify any conditions that may be affected by work.

2.2 DESCRIPTION OF WORK TO BE COMPLETED

The Contractor to supply all plant, labor, materials, and equipment:

· All new material, supplies, and equipment (MES) must be new. The Contractor shall not re-use any existing MES, unless directed to by the PWS.

• Under FacEng supervision labor will be conducted by Contractor to ensure United States Coast Guard Standards are met for Quality and Safety.

• Maintain a clean working area.

• Protect adjacent areas during chiller repair.

• Provide signage to clearly indicate the area is under construction.

• Removal of old chill water pump and installation of new chill water pump.

• Ensure newly installed chill water pump is free of chill water leaks.

• Operate chill water pump to ensure proper performance at pressure

· Section 6 of this PWS displays the damaged chill water pump.

· Remove pipe insulation on chilled water lines in affected space to inspect for corrosion, leaking fittings, or pipes.

· Reinstall demoed pipe insulation with new insulation.

3. PROPOSAL SUBMITALS

3.1 Estimated Costs:

Material Shipping if applicable Labor to include estimated time of completion.

3.2 SUBMISSION:

Contractor shall make the following submittals as a minimum, to the Contracting Officer specified on the cover sheet.

The contractor is required to provide verbal progress reports daily for the period of project duration. The progress report shall cover all work completed during the day and shall present the work to be accomplished during the subsequent period. This report shall also identify any problems that arose and a statement explaining how the problem was resolved. This report shall also identify any problems that have arisen but have not been completely resolved and provide an explanation.

4. CONSTRUCTION NOTIFICATIONS

4.1 NOTIFICATIONS:

The Contractor shall notify the Facilities Engineer in writing (or email) five (5) business days in advance of the date they intend to commence work, and all work must be inspected by the Coast Guard POCs in section 1.3 upon completion.

4.2 RECYCLING AND DISPOSAL OF REFUSE:

Refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of off Government property. All disposals shall be done in accordance with federal, state, and local laws and regulations.

4.3 SAFETY:

During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by, 29 CFR 1926 is a National Code within OSHA that applies across the board. Texas is a “home run” state where the local municipality controls the building codes. The city of Houston has a code “City of Houston Building Code Ordinance No. 2021-1037”. When the standards differ, the more restrictive standard shall apply. The contractor shall provide barriers, temporary fencing, trench covers, etc. wherever work could cause injury to workers, visitors, Coast Guard personnel, or dependents. An Accident Prevention Plan shall be submitted by the contractor prior to any commencement of work.

4.4 TEMPORARY FACILITIES STORAGE:

The location for exterior stock piling or lay down area of materials will be available on base with location to be determined by POC and Facilities Engineer depending on size. The Contractor shall be responsible for protecting materials stockpiled against weather, damage, theft, and other risks of loss. The Coast Guard assumes no responsibility for material or equipment left in the storage area.

4.5 SANITARY FACILITIES:

Toilet facilities are available for use, pending the status of the COVID Pandemic, it may be required that all contractors to wear face masks while entering and transiting the interior of buildings or when social distancing can’t be maintained with other government or contractor personnel. Additionally, good personal hygiene is required, and handwashing is required to prevent the potential spread, to include, but not limited of the COVID virus.

4.6 WATER AND ELECTRICITY:

Limited water and standard 110v electricity are available. The utility connections and disconnections of machinery or equipment shall be the responsibility of the Contractor. Personnel using extension cords to bring power from another location for construction, maintenance, remodeling, etc., shall employ portable ground fault circuit interrupters (GFCIs), even if connecting to building wiring. Use of portable generators is authorized at contractor expense to power portable equipment, if required to provide power other than standard building supplied power sources.

4.7 REFERENCE DRAWING:

Contractor shall verify all information provided. Drawings are provided and available onsite, as well as the photos attached. The photos reflect items that need repairs and provide a view of the entire system as a whole for visibility.

4.8 CONTRACTING REQUIREMENTS:

All contractors must be registered in SAM (System for Award Management) and have an active Unique Entity Identification (UEI).

5. COAST GUARD PROCUREMENT SELECTION

5.1 QUESTIONS:

The Contracting Officer will answer any questions posed by prospective bidders or Contractors. All such inquiries, problems, etc., shall be transmitted with appropriate comments and opinions to the Contracting Officer who will reply.

6. REFERENCE DOCUMENTS AND PHOTOS

Sector Chill water pump –

Sector chill water pump – image1.png image2.jpg image3.jpg image4.jpg image5.jpeg image6.jpeg image7.jpeg

File details come from the government source that posted it. Updated .