PWS - REPAIR Glycol Bldg 1812 Scott Inn 375 FSS.pdf

PDF 141 KB Posted

Attached to
Sources Sought - Glycol Line Repair and Refill - Scott AFB, IL
Solicitation number
FA440726GLYCOL
Issued by

About this file

This Performance Work Statement (PWS) details a glycol line repair and system refill project for Building 1812 (Scott Inn) at Scott Air Force Base in Illinois. The critical objective is to repair a glycol piping system that is currently allowing glycol to back feed into the potable water system, which risks improper chiller operation and potential system corrosion. The project requires a comprehensive repair approach including site assessment, leak detection, system repair, flushing, and refilling with a minimum 30% propylene glycol/water mixture.

The project has a 30-calendar day period of performance from the Notice to Proceed (NTP) date, with specific requirements including a 3-business day diagnostic report, industry-standard repair methods, environmental disposal of used glycol, system pressure and flow testing, and verification of glycol concentration using a refractometer. The contractor must provide detailed progress schedules, including completion percentages and critical path items, which must be approved by the Contracting Officer before construction authorization. The facility serves approximately 50,000 guests annually and contains 284 rooms, making timely and effective repair critical to maintaining building comfort and HVAC operations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

Glycol Line Repair and System Refill, Bldg. 1812 Scott Inn

SCOTT AIR FORCE BASE, ILLINOIS

09 September 2025

1 GENERAL

1.1 BACKGROUND

SAFB Lodging is to provide quality lodging facilities and service to authorized personnel in order to maintain mission readiness and quality of life, while keeping official travel costs to a minimum. The facility serves as the main lodging facility for all of Scott Air Force Base and has approximately 284 rooms within six floors. The average annual number of guests that use the facility is approximately 50,000 guests. In May 2025, it was discovered that the glycol piping system in Building 1812 is allowing glycol to back feed into the potable water system. This condition compromises the glycol-to-water ratio, risking improper operation of the multistask chiller. When glycol mixes with city water, a chemical reaction occurs that forms acid, leading to corrosion within the cooling tower piping system. Immediate corrective action is required to avoid system failure and ensure continued building comfort.

1.2 OBJECTIVES

The objective of this Performance Work Statement (PWS) is to outline the requirements for the repair of the glycol piping system and the refill of glycol solution at the Scott Inn, located at Scott Air Force Base, Illinois. This effort is necessary to restore the system to full operational capacity, ensuring effective HVAC operations during cold weather months.

1.3 STANDARDS, REGULATIONS, AND CODES

The work associated with this project shall adhere to all applicable standards, regulations, and national codes, in effect as of this date of this Performance Work Statement (PWS). Compliance does not exempt from additional Scott AFB engineering, environmental or safety directives. This PWS is reviewed by base civil engineering office and confirm policy or local installation guidance requires additional compliance.

2 TASKS AND TECHNICAL REQUIREMENTS

2.1 Site Assessment and Leak Detection

• Inspect entire glycol system, including visible lines, fittings, joints, and pumps.

• Identify and document the source(s) of leaks or failures.

• Provide a written diagnostic report with photos and repair recommendations within 3 business days of initial inspection.

2.2 Glycol Line Repair

• Isolate and repair all identified leaks using industry-standard repair methods and materials.

• Replace damaged sections of piping, insulation, valves, or fittings as required.

• Use piping materials consistent with existing system specifications or as approved by the Contracting

Officer (CO)

2.3 System Flush and Refill

• Completely flush the system of old glycol and debris prior to refill.

• Dispose of used glycol in accordance with federal, state, and local environmental regulations.

• Refill system with a minimum of 30% propylene glycol/water mixture (or per manufacturer/system requirements).

• Bleed air and ensure proper flow throughout the system.

2.4 Testing and Verification

• Conduct system pressure and flow testing after refill.

• Verify system is leak-free and glycol concentration is within acceptable range using a refractometer.

• Provide a test report including glycol concentration, system pressure, and flow data.

3 DELIVERABLES

3.1 Contractor shall provide deliverables as detailed in Task and Technical Requirements unless otherwise noted below.

4 SCHEDULE

4.1 The period of performance (PoP) for this project is approximately 30 calendar days from the date that Notice to Proceed (NTP) is issued. All work must be scheduled to be completed within this timeframe. Any modifications or extensions must be requested through the Contracting Officer (CO) for review and discussion.

4.2 Prior to beginning construction, Contractor shall provide the CO construction milestones in sufficient detail to accurately identify all phases/disciplines of work to be performed as detailed below:

4.2.1 Contractor shall provide detailed progress schedule including completion percentages for each line item.

4.2.2 Contractor shall provide a general construction schedule, showing, at a minimum, the critical path items.

4.3 Construction may be authorized by the Contracting Officer upon acceptance and approval of the schedule and equipment/material submittal approvals.

PERFORMANCE WORK STATEMENT
2.1 Site Assessment and Leak Detection
2.2 Glycol Line Repair
2.3 System Flush and Refill
2.4 Testing and Verification