This is a Performance Work Statement (PWS) dated January 28, 2025, for an alarm wiring and keypad move project at JBLM Building (location redacted) in Washington state, with a period of performance of February 2025-2021. The primary objective is to connect a collateral vault's IDS to a new vault door and adjust the attached access keypad to enable vault accreditation as an open storage vault and secure vestibule for SCIF validation.

Key requirements include reinstalling one Balanced Magnetic Switch with associated equipment, connecting an X10 lock on the collateral vault door with IDS, ensuring compliance with specified SCIF planning and electronic security systems requirements, providing one-year warranty on parts/installation, and delivering system training. The contractor must develop a Quality Control Plan and comply with an approved Construction Site Security Plan. Work hours are 0900-1600 excluding weekends and federal holidays, with advance approval needed for alternate hours. The contractor must obtain necessary base access credentials and maintain current employee listings with required personal information. The facility is not considered historical and contains no known asbestos hazards.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

present. The Contractor shall make his/her request to the Contracting Officer five (5) calendar days in advance of his/her intention to work during other periods to allow assignment of a government representative. If such force is reasonably available from assigned contract administrators or quality assurance personnel, the Contracting Officer may authorize the contractor to perform work during periods other than normal duty hours/days.

H. Base Access. The Contractor shall be responsible for and shall pay for obtaining all necessary clearances, cards, passes, decals, or other items required for access of Contractor personnel and vehicles to the base or other areas where work will be performed. The Contractor shall be required to apply for vehicle and personnel identification media at the Base Pass and Registration Section (Visitor Control Center). Upon Completion or termination of the contract, the Contractor shall ensure all vehicle and personnel identification media are surrendered to the Base Pass and Registration Section. (Visitor Control Center). The Contractor shall obtain the following pass and identification items:

JBLM Vehicle Pass. For all further inquiries, please contact the Visitor Control Center at

I. Employee Listing. The contractor shall maintain a current listing of employees. The list will include employee names and date of birth. This list shall be provided to the contracting officer and servicing security forces organization. An updated listing shall be provided upon change of employees. The contractor must provide all names, social security numbers and duty hours of all personnel who will be on site at start or anytime during this project

J. Construction Site Security Plan (CSP). Contract requires compliance with approved CSP.

Outlining security protective measures that will be applied to each phase of the construction project. The requirements set forth in this plan provide the baseline for construction security activities and may be supplemented as required but may not be reduced without coordination and approval from the Accrediting Official (AO).