This Performance Work Statement (PWS) outlines the U.S. Army Test, Measurement and Diagnostic Equipment Activity's (USATA) requirement for commercial calibration and repair services for a Hopewell Designs, Inc. Model X83A System Irradiator. The unit is currently non-operational and requires comprehensive repair, including potential upgrades, calibration, training, and reinstallation to manufacturer specifications. The contractor must use original equipment manufacturer parts and adhere to specified turnaround times.
Performance will occur on-site at two locations within Redstone Arsenal, Alabama, during normal business hours (0730-1630, Monday through Friday). Strict security protocols are in place, requiring contractor employees to undergo background checks and comply with installation access requirements, including National Crime Information Center and Terrorist Screening Database checks. The contractor must follow all personal identity verification requirements and be prepared to adapt to potential Force Protection Condition changes at the facility.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USATA-NG-0008-25
PERFORMANCE WORK STATEMENT
FOR CALIBRATION and/or REPAIR SERVICES(C&RS) X83A X-Ray System
Irradiator
1.0 GENERAL. The U.S. Army Test, Measurement and Diagnostic Equipment Activity (USATA) has a requirement to acquire commercial calibration and/or repair services (C&RS) and of the following test, measurement and diagnostic equipment manufactured by Hopewell Designs, Inc. Model X83 System Irradiator.
2.0 CONTRACTOR TASKS.
2.1 A preliminary evaluation for the Model X83A System Irradiator shows the unit has been completely shut down and is not operational for use and will require repair services along with any calibration that’s needed to return the unit back functioning properly.
The contractor shall provide repair, calibration, upgrades, training or any updates and reinstallation of the unit by manufacturer’s specifications.
2.2 The contractor shall replace defective parts, as required, with original equipment manufacturer parts only. The contractor shall strictly comply with the turnaround time to repair as stated in the contract.
2.3 The contractor shall not provide any repair or other services outside the scope of this contract without authorization from the government Contracting Officer listed at page 1 of the contract. The contractor shall not relocate equipment to the contractor’s facility outside without authorization from the Contracting Officer.
3.0 GOVERNMENT TASKS.
3.1 The Government shall provide adequate storage space for spare parts, tools and test equipment required by the Contractor in performance of Contractor tasks, as well as adequate working space, to include desks, chairs, heating, lighting, ventilation, electrical current and outlets for tools and test equipment for use by the Contractor’s customer support technicians. These facilities shall be within a reasonable distance of the equipment to be services and shall be provided at no additional cost to the Contractor.
3.2 Subject to applicable security regulations, the Government shall provide the Contractor access to the equipment to perform the maintenance services.
4.0 PRINCIPAL PERIOD OF MAINTENANCE (PPM). On-site services shall be provided by the Contractor during normal business hours, 0730 – 1630 hours, Monday through Friday (excluding weekends and holidays).
USATA NG-0026-21
Attachment 01
5.0 PLACE OF PERFORMANCE. Required maintenance services shall be performed on-site at Building 5417 Jungerman Road, and Building 5435 Fowler Road, Redstone Arsenal, AL.
5.1 Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility, or area. Contractors and all associated subcontractors’ employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DoD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. Contractor and all associated subcontractor employees shall comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
5.2 For contractors that do not require a CAC but require access to a DoD facility or installation. Contractor and all associated subcontractor employees shall comply with adjudication standards and processes using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
6.0 QUALITY REQUIREMENTS. Not applicable.
7.0 GOVERNMENT-FURNISHED EQUIPMENT. None.