This document is a Performance Work Statement (PWS) for an Environmental Engineering Review contract under a firm-fixed-price (FFP) arrangement. The objective of the contract is to review proposed construction, maintenance, and repair projects at U.S. Army Garrison (USAG) Ansbach to evaluate their environmental impacts and provide recommendations to mitigate those impacts.
Key tasks include reviewing work requests, completing environmental review forms, developing Records of Environmental Consideration, conducting reviews of Military Construction (MILCON) projects, and providing environmental engineering support for active projects. The contractor will also be required to report labor hours through the System for Award Management (SAM) Service Contract Reporting system. The contract will be awarded based on a low price technically acceptable evaluation. Offers are due by August 15, 2024 at 11:00 AM to the Regional Contracting Office - Bavaria. The work will be performed at USAG Ansbach.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912PB24R3032 Solicitation Amendment 0001 Released.pdf | ||
| UPDATED PWS FY24 Environmental Review Final.pdf | ||
| W912PB24R3032 Solicitation.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
Environmental Engineering Review, DPW Environmental Management Division 12 December 2023
Part 1 General Information
1. General: This is a non-personal service(s) contract under which the personnel rendering the service(s) are not subject, either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees.
1.1 Description of Services/Introduction: This is a non-personal services, Firm-Fixed-Price contract to provide Environmental Engineering Review.
1.2 Background: The U.S. Army Garrison (USAG) Ansbach maintains a comprehensive environmental program covering all aspects of environmental management, protection, remediation and enhancement. The purpose of this project, as described in this Performance Work Statement (PWS), is to review proposed construction, maintenance, and repair projects, to include the review of shop drawings, engineering designs, and plans and specifications, in order to evaluate the environmental impacts of design and construction.
1.3 Scope: The Contractor shall provide non-personal services. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services. The Contractor shall perform to the standards and acceptable quality levels identified in this PWS and associated contract documents.
1.4 Objectives: The objective of this project, as described in this Performance Work Statement (PWS), is to review proposed construction, maintenance, and repair projects, to include the review of shop drawings, engineering designs, and plans and specifications, in order to evaluate the environmental impacts of design and construction. The Contractor shall prepare environmental and engineering comments to recommend possible alternate solutions to mitigate environmental impacts.
1.5 General Information
1.5.1 Quality Control Plan (QCP): The Contractor shall develop and maintain a QCP to ensure services are performed in accordance with (IAW) this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor's QCP is the means by which it assures that the work provided complies with the requirements of the contract.
The Contractor’s Proposed QCP shall be submitted to the Contracting Officer (KO) through the Contracting Officer’s Representative (COR) for review within ten (10) days after date of contract award (Deliverable A.001).
The Government will review and either notify the Contractor in writing of acceptance of the plan or return their comments to the Contractor within ten days. If the Government has provided comments, the Contractor shall then have three (3) days to submit a Final QCP. After receipt of the Final QCP, the Contractor may receive the Contracting Officer’s acceptance in writing. Any proposed changes to the accepted QCP are required to be resubmitted for acceptance by the Contracting Officer no later than 30 days prior to the anticipated change and before implementation by the Contractor. The timeline noted above will apply for review and acceptance for proposed changes. At a minimum, the QCP must include and answer the following to be acceptable:
a. A chart showing the organizational structure and lines of authority, the names, qualifications, duties, responsibilities, and classification of each member of the Contractor's Quality Control Team.
b. How will the Contractor monitor work to ensure that performance complies with all deliverables (etc. timelines, deadlines, and goals)?
c. How will the Contractor monitor work to ensure that performance complies with all specifications and requirements of the contract, including clauses?
d. How will the Contractor monitor and ensure staff qualifications remain current and valid including DOCPER processes/approvals throughout contract performance?
e. How will the Contractor ensure all keys issued will remain controlled items (Paragraph 1.7 Key Control)?
f. How will the Contractor inventory and track maintenance of all Government Provided Equipment / Materials?
g. How will the Contractor identify, investigate, and correct any non-conforming performance and prevent similar deficiencies in the future?
h. How will the Contractor file and save all Quality Control related documents for the life of the contract plus 5 years?
1.5.1.1 RESERVED.
1.5.1.2 The Contractor shall inform the COR of issues or potential issues that might affect the performance within 48 hours of identifying those issues. Verbal reports shall be followed up by written reports within three days. (Deliverable A.002).
1.5.2 Quality Assurance: The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the acceptable quality levels (performance thresholds).
1.5.3 Recognized Holidays: The following provides information on recognized holidays for the purpose of the PWS. If submittal of any documentation (e.g. deliverables, submittals, etc.) deadlines fall on a holiday, the closest work day prior to the holiday will apply as the deadline for submittal.
1.5.3.1 U.S. Holidays: Work shall be performed on U.S. holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively.
| New Year’s Day January 1st | M. L. King Memorial Day 3rd Monday in January | ||
| Presidents Day 3rd Monday in February | Memorial Day last Monday in May | ||
| Juneteenth July 19th | Independence Day July 4th | ||
| Labor Day 1st Monday in September | Columbus Day 2nd Monday in October | ||
| Veteran’s Day November 11th | Thanksgiving Day 4th Thursday in November |
Christmas Day December 25th
1.5.3.2 Host Nation Holidays: Work shall not be performed on local Host Nation holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer.
Host Nation holidays are:
| New Year’s Day January 1st | Epiphany January 6th | |
| Good Friday Varies | Easter Monday Varies | |
| Labor Day May 1st | Ascension Day Varies | |
| Whit Monday Varies | Corpus Christ Varies | |
| Assumption Day August 15th | Day of German Unity October 3rd | |
| All Saints’ Day November 1st | 1st Christmas December 25th |
2nd Christmas December 26th
1.5.4 Operating Hours: The Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however, they may differ. Please refer to the following.
1.5.4.1 Government Facility Office Hours: The Government facility office hours are 0730 to 1600, Monday through Friday except U.S. Holidays identified in paragraph 1.5.3.1 above or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings.
1.5.4.2 Government Facility Operating Hours: The Government facility operating hours occur between the hours of 0600 to 1700, Monday through Friday. The facility will be closed during local or national emergencies, administrative closings, or similar Government directed facility closings. The Government facility is open for operations during the recognized U.S. Holidays identified in paragraph 1.5.3.1 above. The Government facility may close due to local or national emergencies, administrative closings, or similar Government directed facility closings and will be communicated by the Contracting Officer to the Contractor.”)
1.5.4.3 Contractor Support Hours: The Contractor shall provide support between the hours of 0730 to 1600, Monday through Friday. The facility will be closed during local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential. For other than firm fixed price contracts, the Contractor will not be reimbursed when the Government facility is closed for the above reasons.
1.5.4.3.1 Contractor Work Plan: The Contractor shall prepare and maintain a Work Plan. The plan, as a minimum, shall identify regularly scheduled work (to include location, work to be completed, timeline, etc.) The Contractor’s proposed Work Plan shall be submitted to the Contracting Officer via the COR for review within 10 days after date of contract award (Deliverable A.003). The Government will review and either accept or return their comments to the Contractor within 10 days. The Contractor shall then have three (3) days to submit a Final Work Plan. Any proposed change to the accepted Final Work Plan is required to be resubmitted via the COR for review and acceptance by the Contracting Officer at a minimum thirty (30) days prior to implementation. The timeline noted above shall apply for review and acceptance for proposed changes.
1.5.5 Training Holidays: USAREUR has historically granted military personnel training holidays as compensation for time that they spent in field training. These are typically combined with regular holiday leave schedules (for example, Christmas half days or day on day off schedules). Training holidays may affect access to military operated facilities. If scheduled work or access to facilities is required, coordination with occupants will be necessary or the work in affected facilities shall be rescheduled after the training holiday. However, announced training holidays or exodus of military personnel may provide the Contractor with an opportunity for unrestricted access to facilities and areas. The Contractor shall take full advantage of such opportunities by planning maintenance or actions that are better accomplished when such areas are vacant.
1.5.6 Place of Performance: The work to be performed under this contract will be performed USAG Ansbach.
1.6 Security Requirements: The following information is provided on security related matters.
1.6.1 Security Program: RESERVED.
1.6.2 Personnel Security Clearance Requirements: RESERVED.
1.6.3 Installation Access: Access to U.S. installations and controlled areas is limited to personnel who meet security criteria and are authorized by Host Nation law to work in that country. Failure to submit required information/data and obtain required documentation or clearances in accordance with Army in Europe (AE) Regulation 190-16 (AE Reg 190-16) Installation Access Control or (AE) Regulation 604-1 for Germany specific contracts, will be grounds for denying access to U.S. installations and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements. Should anything in this paragraph conflict with AE Reg 190-16 or (AE) Regulation 604-1, the regulation takes precedent.
The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control System (IACS) processing requirements.
The Contractor shall return installation passes to the issuing IACS office when the contract is completed or when a Contractor employee no longer requires access.
AE Reg 190-16 (and AE 190-16-G German translation) can be found on the following website:
https://media.defense.gov/2017/Apr/27/2001921546/-1/-1/0/AER190-16.pdf https://media.defense.gov/2017/Apr/27/2001921547/-1/-1/0/AER190-16-G.pdf
1.6.3.1 In addition, the Contractor shall provide the Contracting Officer, via the COR, an Initial Installation Pass Log within three (3) calendar days after contract award (Deliverable A.004). The log must at a minimum contain the following information. The log shall be updated as employees are added or removed. The Updated Installation Pass Log shall be current and available at any time upon request by the Government and submitted to the COR within five (5) days after any changes to the log.
1.6.3.2 The Contractor shall collect the installation access passes the same day employment of an individual has expired or has been terminated and shall return them to the issuing office within three (3) days (Deliverable A.005).
1.6.3.3 Upon termination or cancellation of this contract, the Contractor shall collect all outstanding installation access passes and return them to the issuing office within three (3) days (Deliverable A.006).
1.6.3.4 Common Access Cards (CAC): The Contractor shall provide the following information: Last, First Middle Name, Cadency Name, Personal identifier (e.g. Social Security Number, Federal Identification Number, or Tax Identification Number), date of birth, primary email address (this email address will be used to contact the individual) to the COR with 15 calendar days after award (unless circumstances require otherwise and as directed by the Contracting Officer) (Deliverable A.007).
1.6.3.4.1 The Contractor shall provide a CAC log within the first 30 calendar days after contract award and within five (5) days after changes have been made (Deliverable A.008) (unless circumstances require otherwise and as directed by the Contracting Officer). The COR will provide format and content for the log during the post award meeting. Note - CACs are Government property and must be accounted for.
1.6.4 Background Checks: Army in Europe (AE) Regulation 604-1 provides guidance pertaining to background checks for U.S. and Host Nation Contractors.
1.6.4.1 U.S. Citizen: RESERVED.
1.6.4.2 Local Nationals and Third Country Nationals: Local national and third country national Contractors that work with or teach youths under the age of 18 years are subject to background checks as determined by the Requiring Activity Manager. As a minimum prior to beginning performance, Contractors employing local national and third country nationals shall furnish the Contracting Officer via the COR and the Requiring Activity Manager a Polizeiliches Fuehrungszeugnis, issued within the previous four months, no later than ten (10) days after contract award (Deliverable A.009). Forwarding correspondence from the Contractors shall identify the associated contract number. The Requiring Activity Manager will determine the favorability of the Polizeiliche Fuehrungszeugnis and notify the Contractor. The Contractor shall forward a copy of unfavorable Polizeiliche Fuehrungszeugnis to the Contracting Officer via the COR and the Requiring Activity Manager within ten (10) days of receipt, identifying such with the appropriate contract number. Local nationals and third country nationals agree to the same employee termination provisions as stated for U.S. Citizens (see paragraph 1.6.4.1 above, in particular, same requirements to replace the employee (and within timeframe noted) when results of background check are unfavorable).
1.6.5 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured IAW the Army Physical Security Program (AR 190-13).
1.6.6 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel.
1.7 Key Control: The Contractor shall establish and implement methods of making sure all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. NOTE: All references to keys include key cards. No keys issued to the Contractor by the Government shall be duplicated. Such procedures shall include turn-in of any issued keys by personnel who no longer require access to locked areas.
1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.
1.9 Contracting Officer’s Representative (COR): Refer to Part 2 of this PWS for the definition of a COR. As determined by the Contracting Officer, a COR will be appointed and identified by letter of designation, a copy of which will be provided to the Contractor by the Contracting Officer. The designation letter states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates, or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is not authorized to obligate the Government. If the work is not written in the contract, the COR is not authorized to request new work. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract, perform inspections necessary in connection with contract performance, maintain written and oral communications with the Contractor concerning technical aspects of the contract, issue written interpretations of technical requirements, including Government drawings, designs, specifications, monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies, coordinate availability of Government property, and coordinate site entry of Contractor personnel.
1.10 Key Personnel: The following personnel are considered key personnel by the Government: Program Manager. The Contractor shall provide a Program Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Program Manager, who shall act for the Contractor when the Program Manager is absent, along with a Curriculum Vitae (CV) for each of these individuals, shall be provided in writing to the Contracting Officer no later than five (5) days after contract award (Deliverable A.010). The Program Manager and Alternate Program Manager shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract. The Program Manager or Alternate Program Manager shall be available between 7:30 and 16:00, Monday through Friday. Qualifications for all key personnel are listed below:
a. Contract Manager and Alternate Contract Manager: The CV provided by the Contract Manager and Alternate Contract Manager must demonstrate a minimum of 5 years’ experience in Environmental related management. These individuals designated as key personnel shall be able to read, write, and speak the English and German languages with proficiency level B2 or higher.
b. Environmental Engineer: The Environmental Engineer must have a B.S. college degree from an accredited post-secondary institution in an environmental engineering specialty or HN equivalent engineering certification; five or more years’ experience working with environmental compliance and compliance with , regulations, and HN requirements, and a minimum of two years as an environmental engineer responsible for planning and implementing all project-related activities, including preparation of required plans and reports in English.
1.11 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.
1.12.1 RESERVED.
1.12.2 Contractor Identification Badges: RESERVED.
1.13 Contractor Travel: The Contractor may be required to travel during the performance of this contract to attend meetings, conferences, and training. The Contractor may be required to travel to off-site training locations and to ship training aids to these locations in support of this PWS. The Contractor may be authorized travel expenses at rates no higher than the substantive provisions of the Joint Travel Regulation (JTR), IAW FAR Part 31.205-46, and the limitation of funds specified in this contract. All travel requires Government approval and authorization 10 days prior to scheduled travel.
1.14 Other Direct Costs (ODCs): RESERVED.
1.15 Data Rights: The Government has unlimited rights to all documents and materials produced under this contract. All documents and materials, to include the source codes of software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership and copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.16 Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. The Contractor and Contractor personnel, shall not divulge or release data or information developed, or obtained under performance of this PWS, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.
1.17 The use of propaganda violates DoD Commercial Use of Imagery Guidelines stated at http://www.defenseimagery.mil/products/dodimagery/commercialuse.html The Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any marketing tools to include its company website.
1.18 Non-Disclosure Statements: RESERVED.
1.19 Organizational Conflict of Interest (OCI): Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCI as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI (Deliverable A.011). The Contractor’s OCI Mitigation Plan will be determined to be acceptable solely at the discretion of the Contracting Officer. In the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.20 Phase In /Phase Out Period: To minimize decreases in productivity and to prevent possible negative impacts on additional services, the Contractor shall have personnel on board, during the sixty (60) day phase in/ phase out periods. During the phase in period, the Contractor shall become familiar with performance requirements in order to commence full performance of services on the contract start date.
1.21 Safety: The following provides information pertaining to Safety and Accident Prevention:
1.21.1 Host Nation Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein (e.g. U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1)), and applicable Host Nation Safety Laws and Regulations.
The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:
(a) Before initiation of work at the job site, an Accident Prevention Plan, written by the Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1; will be reviewed for acceptance by designated Government personnel (Deliverable A.012). Specific requirements for development of the Accident Prevention Plan are found in 01.A and Appendix A of EM 385-1-1. EM 385-1-1 is available online at www.usace.army.mil.
(b) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of EM 385-1-1).
(c) The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.
(d) The Contractor shall discuss the plans in conferences convened by the Contracting Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within fifteen (15) calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than fifteen (15) calendar days prior to initiation of work on each major phase.
(e) In all areas where construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:
(i) Short sleeve shirt.
(ii) Long trousers.
(iii) Steel-toed safety boots.
(iv) Hard hat.
1.21.1.1 In addition to other requirements for accident prevention specified in this contract, the Contractor shall comply with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes. In particular, within the requirements of the German Safety and Health Protection Regulation for Construction Sites, Baustellenverordnung (BaustellV) (current version in effect), the Contractor shall coordinate all work at the site, including development of plans and providing advance notices.
The Contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract. For the compliance with host nation laws and regulations, the Contractor shall comply with the non-exclusive list of duties described in this paragraph. If the Contractor determines that additional activities are required to fully comply, the Contractor shall ensure that compliance with the laws is complete. The duties include:
(a) Conditions of construction and operational activities to be considered include but are not limited to:
(i) For all construction activities meeting the following criteria: the work is scheduled to last longer than 30 working days and more than 20 workers are occupied simultaneously, or the volume of work is scheduled to exceed 500 person days, or the work presents particular tasks, e.g. excavations deeper than 5 meters, falls from a height of greater than 7 meters, exposures to hazardous chemical or biological substances, work at less than 5 meters from high voltage lines, underground earth works or tunnels, danger of drowning, diving, use of compressed air, work with ionizing radiation, explosives, or work involving assembly or dismantling of heavy prefabricated components (10 tons or greater).
(b) If the Contractor determines that the BaustellV, dated 10 June 1998, applies, the Contractor shall prepare a Safety and Health Protection Plan (SIGE) as required under that regulation. The SIGE shall be submitted two weeks prior to mobilization. In addition, the Contractor shall appoint a qualified Safety Coordinator who will ensure that safety measures are implemented during construction. The Safety Coordinator must meet minimum training and experience requirements required under Host Nation laws.
(c) The SIGE will be written in a comprehensive form and explained in language the workers understand and shall contain the following minimum information:
(i) Maintenance of tools and equipment.
(ii) Provisions for the storage and disposal of materials and waste, particular hazardous materials and substances.
(iii) Modifying performance periods for such work, taking into consideration the site conditions.
(iv) Organizing cooperation between different employers and Contractors without employees.
(v) Interaction between work at the site and other operational activities in the area, on which or near which the first identified work will be performed, and taking into consideration the instructions and advice of the coordinator as well as safety and health plans.
1.21.1.2 The Contractor shall complete and provide safety notifications required by host nation authorities and will provide documented proof to the Contracting Officer via the COR, no later than 10 days (Deliverable A.013) that such notifications were made.
1.22 Environmental Compliance: RESERVED.
1.23 Required Training: The following provides information on training requirements.
1.23.1 Anti-Terrorism (AT) Level I Training: All Contractor employees, including subcontractor employees, who are employed under the contract, shall complete AT Level I Training within 10 days (Delierable A.014) after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or 10 days after employment of new personnel. Contractor personnel travelling overseas shall complete area of responsibility (AOR) specific AT awareness training for U.S. based Contractor employees and associated subcontractor employees. The Contractor shall submit certificates of completion for each affected Contractor employee and subcontractor employee to the COR (or to the Contracting Officer, if a COR is not assigned) within 10 days after completion of this training by all employees and subcontractor personnel. AT Level I awareness training is available at https://jkodirect.jten.mil. Contractor personnel shall complete refresher training every twelve (12) months except AOR specific AT Level I training which shall be completed as required by local AT policies
If training cannot be conducted on the website, the Contractor shall coordinate with the COR who will contact the local AT Officer at their assigned location for classroom training. Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the AT Officer. Verification of the training shall be provided to the COR within three (3) days after completion of the training.
1.23.2 OPSEC Training: All Contractor employees, including subcontractors, shall complete Level I OPSEC training within 10 days of employment under this contract (Deliverable A.015). Verification of the training shall be provided to the COR within three (3) days after completion of the training. OPSEC Level I training is available at http://www.cdse.edu/catalog/elearning/GS130.html. Contractor personnel must complete refresher training every 12 months. Verification of the training shall be provided to the COR within three (3) days after completion of the training.
If training cannot be conducted on the website, the Contractor shall coordinate with the COR, who will contact the local OPSEC Officer at their assigned location for classroom training. Contractor personnel completing training in the classroom will receive a certificate or the training attendance roster signed by the OPSEC Officer. Verification of the training shall be provided to the COR within three (3) days after completion of the training.
1.23.3 iWATCH Training: The Contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 10 days after the contract is awarded and within 10 days after new employees commence contract performance, with the results reported to the COR within three (3) days after the contract is awarded and within 10 days after new employees commence contract performance (Deliverable A.016). Verification of the training shall be provided to the COR within three (3) days after completion of the training. Training slides can be found on the Army OneSource we site:
http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx.
1.23.4 Information Assurance (IA) Training
1.23.4.1 All Contractor employees, including subcontractors, requiring access to Government information systems shall complete the Department of Defense (DoD) IA Cyber Awareness Training within 10 days (Deliverable A.017) after contract start date or effective date of incorporation of this requirement into the contract, whichever applies, or 10 days after employment of new personnel. Verification of the training shall be provided to the COR within three (3) days after completion of the training.
1.23.4.2 All Contractor employees, including subcontractors, working information technology (IT)/IA functions shall comply with DoD and Army training requirements per Information Assurance Training Certification and Workforce Management DoD Directive (DoDD) 8570.01, Information Assurance Workforce Improvement Program DoD 8570.01-M, and Information Assurance AR 25-2 within thirty (30) calendar days of employment. Training is available at https://ia.signal.army.mil/DoDIAA/default.asp.
1.23.4.3 All Contractor employees, including subcontractors, performing services under this contract with access to a Government information system must be registered in the Army Training Certification Tracking System (ATCTS), the web address is https://atc.us.army.mil/iastar/index.php. Verification of registration shall be provided to the COR within three (3) days after registration. (Deliverable A.018). Contractor personnel must complete refresher training every twelve (12) months. Verification of the training shall be provided to the COR within three (3) days after completion of the training.
1.23.5 Personally Identifiable Information (PII): RESERVED.
1.24 Authorization to Perform Services in Germany
1.24.1 Contractors performing services in the Federal Republic of Germany (FRG) shall comply with German law. The Contractor shall determine whether performance requires registration with German authorities or authorization to do business in Germany and, if so, shall comply with all requirements. Whether or not registration or authorization to do business is required, the Contractor shall determine what documents or authorization its employees and any subcontractor employees must possess to work in Germany. The Contractor shall ensure affirmatively that its employees and subcontractor employees possess such documents or authorizations.
1.24.2 Contractor employees who: (a) are not nationals of Germany or other European Union countries; (b) are not members of the force, the civilian component or their dependents; or c) do not have assimilated status under Articles 71, 72, or 73 of the Supplementary Agreement to the NATO SOFA shall possess work and residence permits.
1.24.3 By acceptance of and performance under this contract, the Contractor affirms that it has complied with the requirements above. Compliance with this requirement and German law is a material contract requirement. Noncompliance by the Contractor or subcontractor at any tier shall be grounds for issuing a negative past performance evaluation and terminating this contract for default.
1.25 N/A
1.26 Electromagnetic Compatibility Directive: RESERVED.
1.27 Government Property and Services: Refer to Part 3 of this PWS for Government property (GP) for this contract.
1.28 Conventional Forces Europe (CFE) Treaty Verification Inspection: Contractor-owned or controlled structures and containers located on U.S. Government installations are subject to short-notice inspections by CFE treaty inspection teams. The Government will endeavor to provide the Contractor as much notice as possible in the event of such inspections. The contractor shall provide access to such structures and containers at the request of the Government. The Contractor shall report such inspections to the KO through the COR in writing within ten (10) calendar days of completion of the inspection. Contractor-owned or controlled structures and/or containers on U.S. installations may have to be inspected to comply with the CFE treaty even if Contractor personnel are unavailable to provide access. Any costs borne by the Contractor or any impact on contract performance as a result of the inspection will be a matter of negotiation between the Contractor and the KO.
PART 2
DEFINITIONS & ACRONYMS
2. Definitions and Acronyms
2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.
Contracting Officer – means a person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
Contracting Officer's Representative (COR) – As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. Department of Defense Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, contracting officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing support personnel to assist the COR, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”
Contractor – means a supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
Contractor-acquired property - means property acquired, fabricated, or otherwise provided by the Contractor for performing a contract, and to which the Government has title.
Day – means, unless otherwise specified, a calendar day.
Defective Service – means service output that does not meet the standard of performance associated with the Performance Work Statement.
Deliverable – means anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.
Government-furnished property - means property furnished to the contractor the Government and subsequently furnished to the Contractor for performance of a contract. Government-furnished property includes, but is not limited to, spares and property furnished for repair, maintenance, overhaul, or modification. Government-furnished property also includes Contractor-acquired property if the Contractor-acquired property is a deliverable under a cost contract when accepted by the Government for continued use under the contract.
Government property - means all property owned or leased by the Government. Government property includes both Government-furnished property and Contractor-acquired property. Government property includes material, equipment, special tooling, special test equipment, and real property. Government property does not include intellectual property and software.
Property Administrator - means an authorized representative of the Contracting Officer appointed in accordance with agency procedures, responsible for administering the contract requirements and obligations relating to Government property in the possession of a Contractor.
High Level Objective (HLO) – means a key overarching result-based objective for a project necessary to achieve the project’s vision. HLOs are similar to Level 2 in a Work Breakdown Structure. Each HLO may contain several statements to flesh out the areas necessary to meet the objective.
Physical Security – means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.
Quality Assurance – (or Government contract quality assurance) means the various functions, including, inspection, performed by the Government to determine whether a Contractor has fulfilled the contract obligations pertaining to quality and quantity.
Quality Assurance Surveillance Plan (QASP) – means the key Government-developed surveillance process document, and is applied to Performance-Based Service Contracting (PBSC). The QASP is used for managing Contractor performance assessment by ensuring that systematic quality assurance methods validate that Contractor quality control efforts are timely, effective, and are delivering the results specified in the contract or task order. The QASP directly corresponds to the performance objectives and standards (i.e., quality, quantity, timeliness) specified in the Performance Work Statement (PWS). It provides specific details on how the Government will survey, observe, test, sample, evaluate, and document Contractor performance results to determine if the Contractor has met the required standards for each objective in the PWS. The QASP, with very few if any exceptions, is an internal to Government document.
Quality Control – means all necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
Statement – means the specific results-based activities required to satisfy HLOs. A statement contains a result, the context of the statement, and the required action(s). Statements focus on “what” is to be accomplished; however they are not prescriptive in describing “how” the outcome is to be achieved. Each HLO may have several statements to flesh out the areas necessary to meet the objective. Statements are similar to Level 3 in a Work Breakdown Structure.
Subcontractor – means one that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
Work Day - The number of hours per day the Contractor provides services in accordance with the contract.
Work Week - Monday through Friday, unless otherwise specified.
2.2 Acronyms: Although not inclusive of every term used within this PWS, the following provides a list of acronyms used throughout this PWS or commonly used in the acquisition field.
| ACOR | Alternate Contracting Officer's Representative | ||
| AE | Army in Europe | ||
| AE Form 200-1A | Request for Environmental Review | ||
| AFARS | Army Federal Acquisition Regulation Supplement | ||
| AHA | Activity | Hazard Analysis | |
| AOR | Area of Responsibility | ||
| AR | Army Regulation | ||
| AQL | Acceptable Quality Level | ||
| AT | Anti-terrorism | ||
| ATCTS | Army Training Certification Tracking System | ||
| BOID | Business Organization and Integration Division | ||
| CAC | Common Access Card | ||
| CCE | Contracting Center of Excellence | ||
| CFE | Conventional Forces Europe | ||
| CFR | Code of Federal Regulations | ||
| CONUS | Continental United States (excludes Alaska and Hawaii) | ||
| COR | Contracting Officer’s Representative | ||
| COTS | Commercial-Off-the-Shelf | ||
| DA | Department of the Army | ||
| DD1391 | Military Construction Project Data Sheet | ||
| DD250 | Department of Defense Form 250 (Receiving Report) | ||
| DD254 | Department of Defense Contract Security Requirement List | ||
| DFARS | Defense Federal Acquisition Regulation Supplement | ||
| DMDC | Defense Manpower Data Center | ||
| DoD | Department of Defense | ||
| EMD | Environmental Management Division | ||
| ERG | Environmental Review Guide | ||
| FAR | Federal Acquisition Regulation | ||
| FRG | Federal Republic of Germany | ||
| FGS | Final Governing Standards | ||
| GIS | Geographic Information System | ||
| GFP | Government Furnished Property | ||
| HLO | High Level Objective | ||
| HIPAA | Health Insurance Portability and Accountability Act of 1996 | ||
| IA | Information Awareness | ||
| IAC | Installation Access Control | ||
| IACO | Installation Access Control Office | ||
| ID | Identification | ||
| IGCE | Independent Government Cost Estimate | ||
| IT | Information Technology | ||
| JTR | Joint Travel Regulation | ||
| JPAS | Joint Personnel Adjudication System | ||
| KO | Contracting Officer | ||
| MILCON | Military Construction | ||
| NEPA | National Environmental Policy Act | ||
| OCI | Organizational Conflict of Interest | ||
| OCONUS | Outside Continental United States (includes Alaska and Hawaii) | ||
| ODC | Other Direct Costs | ||
| OPSEC | Operations Security | ||
| PA | Property Administrator | ||
| PII | Personally Identifiable Information | ||
| PIPO | Phase In/Phase Out | ||
| POC | Point of Contact | ||
| PRS | Performance Requirements Summary | ||
| PWS | Performance Work Statement | ||
| QA | Quality Assurance | ||
| QAP | Quality Assurance Program | ||
| QASP | Quality Assurance Surveillance Plan | ||
| QC | Quality Control | ||
| QCP | Quality Control Program | ||
| RA | Requiring Activity | ||
| REC | Record of Environmental Consideration | ||
| RCO | Regional Contracting Office | ||
| SCR | Service Contract Reporting | ||
| SEMS | Sustainable Environmental Management System | ||
| SIGE | Safety and Health Protection Plan | ||
| STD | Standard | ||
| TE | Technical Exhibit | ||
| USAREUR | U.S. Army Europe | ||
| UOM | Unit of Measure |
PART 3
GOVERNMENT PROPERTY (GP) AND SERVICES
3. Government Property and Services
3.1 Services: RESERVED.
3.2 Facilities: The Government will provide necessary workspace, desk space for the Contractor to provide the support outlined in the PWS to include desk space and storage rooms.
3.3 Utilities: The Government will provide basic utilities for the Contractor. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.
3.4 Equipment: RESERVED.
3.5 Special Tooling and Test Equipment: RESERVED.
3.6 Materials: RESERVED.
3.7 Training: RESERVED.
3.8 Common Access Cards (CAC): The Government will provide Common Access Cards (CAC) via the Trusted Associate Sponsorship System (TASS) (Web site https://www.dmdc.osd.mil/tass/).
PART 4
CONTRACTOR FURNISHED ITEMS AND SERVICES
4. Contractor Furnished Property and Services
4.1 General: The Contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .