This document is a Performance Work Statement (PWS) for a federal contract opportunity to remove, furnish, and install a new fire alarm system at Building 335 at Little Rock Air Force Base in Arkansas.
The PWS outlines the specific requirements for the contractor, including providing all qualified personnel, transportation, tools, equipment, drawings, materials, and services needed to install a new Monaco basic fire alarm system. The work must be completed within 180 calendar days and comply with all federal, state, and local regulations, codes, and license requirements. Key details include the requirement for a QFPE to provide drawings, the need to reuse existing Monaco equipment where possible, and the installation of carbon monoxide detectors. The contractor will be responsible for disconnecting and removing the existing system. The PWS also includes pre-government testing and final government testing requirements. The related federal contract opportunity, solicitation number FA446024Q0287, has a site visit scheduled for September 19, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Provision and Clauses.pdf | ||
| B-335 Asbestos survey.pdf | ||
| Appendixes.pdf | ||
| Addendum 52.212-1 & 52.212-2.pdf | ||
| Combo Updated( Resolicitation).pdf | ||
| Brand Name Justification Redacted.pdf | ||
| Wage Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
28 April 2023
PERFORMANCE WORK STATEMENT (PWS)
FIRE ALARM REPLACEMENT B335
LITTLE ROCK AFB, AR 72099
1. DISCRIPTION OF SERVICES
1.1. The contractor shall provide all qualified personnel, transportation, tools, equipment, drawings, materials and services required to install a new Monaco basic fire alarm system at B335. The contractor shall accomplish all services below to meet the requirements of this Performance Work Statement (PWS). Work shall be in regulatory compliance with all Federal, State and local regulations, codes, IAW, UFC, NFPA and license requirements. Work shall be accomplished within 180 days of award.
1.2. The requirements official has determined that none of the services to be performed are inherently governmental.
2. SAFETY AND REGULATORY REQUIREMENTS
2.1. The fire alarm systems are located in mech room and throughout building 335. Contractor shall coordinate with Contracting Officer Representative (COR) for access to building 335. It’s estimated that 100% of the work will need to be performed during normal working hours of 0800-1600 M-F excluding federal holidays and will not be considered as overtime hours.
Contractor shall be escorted by government personnel for access to building 335. The intent is to complete all work within 180 calendar days. Escort shall be provided by LRAFB.
2.2. Pre-Install Requirements: Before services are commenced, the contractor shall inspect the work site and ascertain all information for the diligent performance of the service(s). The contractor shall notify the ordering agency of any conditions that prevent the suitable completion of these services to include operations that could endanger Government personnel or property and require appropriate abatement action. If the contractor discovers problems associated with the work after starting, he or she shall immediately notify the Contracting Officer (CO) for their approval if the work is to continue. Coordinate with the Government designated representative to have utilities/fire alarms etc…turned on or off during the competition of the task.
2.3. Disposal of waste: All waste disposals are the responsibility of the contractor to include any fees or permits. Recycling containers may be provided if needed for the operation.
Coordinate through your government representative or COR.
2.4. All work shall be accomplished in accordance with all environmental regulations on disposal.
2.5. All work shall be accomplished in accordance with all UFGS 28 31 70, UFC 3-600-01, UFGS 25 05 11 and UFC 4-010-06. Contractor must use newest regulations.
2.6. Clean/wipe/vacuum all floors, furniture and flat surface areas to ensure the work area is clean from all work done. Protection of the work area is a must.
3. WORK REQUIREMENTS
3.1. Drawings provided by the contractor.
3.1.1. Contractor shall provide drawings according to UFGS 28 31 70. A QFPE is required. No additional personnel are needed except DFPE for final testing. Please use UFGS 28 31 70 for design requirements for fire alarm system.
3.1.2. Contractor shall show single-line fire alarm riser diagram. Each device on riser should be identified by type. Indicate connection of equipment.
3.1.3. This work includes designing and providing a new, complete, basic fire alarm system as described herein and contract drawings at building 335. Include system wiring, raceways, pull boxes, control equipment, initiating devices, notification appliances, and other accessories and miscellaneous items required for a complete operational system even though each item is not specifically mentioned or described. Provide systems complete and ready for operation. Existing interior fire alarm system was manufactured by Monaco. Design and installation must comply with UFGS 25 05 11, UFC 4-010-06 and AFGM 2019-320-02.
3.1.4. Each remote fire alarm control unit must be powered from a wiring riser specifically for that use or from a local emergency power panel located on the same floor as the remote fire alarm control unit. Where remote fire control units are provided, equipment for notification appliances may be located in the remote fire alarm control units.
3.2. Contractor must provide all materials, workmanship, installation, inspection, testing and equipment.
3.2.1. Provide all materials, equipment, and devices that have been tested by a nationally recognized testing laboratory and listed for fire protection service when so required by NFPA 72 or this specification. The current system is based on Monaco. Select material from one manufacturer –Monaco and not a combination of manufacturers, for any classification of materials. No transceiver is needed just the Monaco fire alarm panel. Reuse Monaco receiver. No heat detectors for fire alarm system. Smoke detectors are needed. Duct smoke detectors are included in this fire alarm system.
Material and equipment must be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid opening.
3.2.2. Contractors must provide wiring where needed. Can reuse existing wire. Wiring must be solid copper cable in accordance with the manufacturer’s requirements. Please refer to UFGS 28 31 70.
3.2.3. Where an emergency generator provides standby power supply for life safety system circuits, the generator must be monitored by the Fire Alarm Control Unit (FACU) and transmit emergency generator signals in accordance with NFPA 72. Building 335 generator is 125 KW and 160 HP. A carbon monoxide device and carbon dioxide device must be installed in generator room.
3.2.4. Major components of equipment must have the manufacturer's name, address, type or style, model or serial number, catalog number, date of installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or equipment. Major components include, but are not limited to, the following:
3.2.4.1. FACU Nameplates must be etched metal or plastic, permanently attached by screws to control units or adjacent walls.
3.2.5. Keys and locks for equipment, control units and devices must be identical. Master all keys and locks to a single key as required by the Installation Fire Department.
3.2.6. Provide a typeset printed or typewritten instruction card mounted behind a glass cover in a stainless-steel frame. Install the instructions on the interior of the FACU. The card must show those steps to be taken by an operator when a signal is received as well as the functional operation of the system under all conditions, normal, alarm, supervisory, and trouble. The instructions must also include procedures for operating live voice microphones. The instructions and their mounting location must be approved by the Contracting Officer before being posted.
3.2.7. The fire alarm system must be independent of the building security, building management, and energy/utility monitoring systems other than for control functions.
3.3. Fire alarm (FACU) control unit provided by the contractor.
3.3.1. Contractors must provide a complete fire alarm control unit (FACU) according to the UFGS 28 31 70. FACU must have a fully enclosed in a lockable steel cabinet as specified herein.
Operations required for testing or for normal care, maintenance, and use of the system must be performed from the front of the enclosure. If more than a single unit is required at a location to form a complete control unit, the unit cabinets must match exactly. The system must be capable of defining any module as an alarm module and report alarm trouble, loss of polling, or as a supervisory module, and reporting supervisory short, supervisory open or loss of polling such as valve supervisory switches, independent smoke detection systems, relays for output function actuation.
3.3.2. Contractor must install control unit components in cabinets large enough to accommodate all components and to allow ample gutter space for interconnection of control units as well as field wiring. The cabinet must be a sturdy steel housing, complete with back box, hinged steel door with cylinder lock, and surface mounting provisions. The enclosure must be identified by an engraved phenolic resin nameplate. Lettering on the nameplate must say "Fire Alarm Control Unit" and must not be less than 25 mm 1-inch high. Provide prominent rigid plastic or metal identification plates for lamps, circuits, meters, fuses, and switches.
3.3.3. Each control unit must provide power, supervision, control, and logic for the entire system, utilizing solid state, modular components, internally mounted and arranged for easy access.
Please refer to UFGS 28 31 70.
3.3.4. Nameplates for fuses must also include ampere rating. Separate alarm and trouble LEDs must be provided for each zone alarm.
3.3.5. Contractor must install (4) LED Signs and Modules to Monitor Sprinkler. Please refer to
UFGS 28 31 70.
3.3.6. A suitable means (single operation) must be provided for testing the control unit visual indicating devices (meters or LEDs). Meters and LEDs must be plainly visible when the cabinet door is closed. Signals and LEDs must be provided to indicate by zone any alarm, supervisory or trouble condition on the system. Please refer to UFGS 28 31 70.
3.3.7. Provide an alarm silencing switch at the FACU that must silence the audible and visual notification appliances. Subsequent activation of initiating devices must cause the notification appliances to re-activate.
3.3.8. Upon restoration of power, startup must be automatic, and must not require any manual operation. The loss of primary power or the sequence of applying primary or emergency power must not affect the transmission of alarm, supervisory or trouble signals. Refer to UFGS 28 31 70.
3.3.9. Power and supervise each circuit such that a signal from one device does not prevent the receipt of signals from any other device. Initiating devices must be manually reset by switch from the FACU after the initiating device or devices have been restored to normal.
3.3.10. Contractor shall use UFGS 28 31 70 for all equipment and materials that must be provided.
3.4. Installation
3.4.1. Locate the FACU where indicated on the drawings. The FACU must be located in conditioned space. Conductor terminations must be labeled and a drawing containing conductor, their labels, their circuits, and their interconnection must be permanently mounted in the FACU.
Locate the document storage cabinet adjacent to the FACU unless the Contracting Officer directs otherwise.
3.4.2. When batteries will not fit in the FACU, locate battery cabinets below or adjacent to the FACU. Battery cabinets must be installed at an accessible location when standing at floor level.
Installing batteries above drop ceilings or in inaccessible locations is prohibited. Refer to UFGS 28 31 70.
3.4.3. Duct-mounted photoelectric smoke detectors must consist of a smoke detector, as specified in paragraph Spot Type Detectors, mounted in a special housing fitted with duct sampling tubes.
Detector circuitry must be mounted in a metallic or plastic enclosure exterior to the duct. Refer to UFGS 28 31 70.
3.4.4. Locate manual stations as required by NFPA 72 and as indicated on the drawings. Mount stations according to UFGS 28 31 70.
3.4.5. Locate smoke and heat detectors as indicated on the drawings. Remove existing heat detectors and replace ceiling tiles. No heat detectors will be replaced. Install smoke detectors according to the UFC 3-600-01 and UFGS 28 31 70.
3.4.6. Locate carbon monoxide detectors as indicated on the drawings. Carbon monoxide detectors must be installed separate from smoke detector. Carbon monoxide (CO) detectors must be listed to UL 2075 and set to respond to the sensitivity limits of UL 2034. Carbon monoxide (CO) detectors must be listed for use with fire alarm control units. There will be two CO detectors. Install a CO detector the furnace closet and downstream in adjacent room. Refer to
UFGS 28 31 70.
3.4.7. Locate the remote annunciator as shown on the drawings. Install and mount the annunciator according to UFGS 28 31 70.
3.4.8. Provide ceiling bridges for ceiling-mounted appliances and tiles where needed. Ceiling bridges must be as recommended/required by the manufacturer of the ceiling-mounted notification appliance. Replace damaged ceiling tiles.
3.4.9. No blank covers. Patch and paint all holes and removal of devices. Match paint with current paint. Must be a smooth finish unless it’s a popcorn ceiling.
3.4.10. Provide wiring that is installed in a neat and workman like manner and installed parallel with or at right angles to the sides and back of any box, enclosure, or cabinet. Protect all fire wall and smoke wall penetrations with a UL approved system. Conductors that are terminated, spliced, or otherwise interrupted in any enclosure, cabinet, mounting, or junction box must be connected to screw-type terminal blocks. Mark each terminal in accordance with the wiring diagrams of the system. The use of wire nuts or similar devices is prohibited. Wiring to conform with NFPA 70. Refer to UFGS 28 31 70.
3.5. Disconnection and removal of existing system.
3.5.1. Maintain existing fire alarm equipment fully operational until the new equipment has been tested and accepted by the Contracting Officer. As new equipment is installed, label it "NOT IN SERVICE" until the new equipment is accepted. Once the new system is completed, tested, and accepted by the Government, it must be placed in service and connected to the supervising station. Remove tags from new equipment and tag the existing equipment "NOT IN SERVICE" until removed from the building. No decommissioned equipment is permitted to be abandoned in place.
3.5.2. In unfinished areas (including areas above drop ceilings), paint all exposed electrical conduit (serving fire alarm equipment), fire alarm conduit, surface metal raceway, junction boxes and covers red. In finished areas, paint exposed electrical conduit (serving fire alarm equipment), fire alarm conduit, surface metal raceways, junction boxes, and electrical boxes to match adjacent finishes. Refer to UFGS 28 31 70.
3.5.3. Contractor shall use UFGS 28 31 70 for all disconnection and removal of existing system instructions.
3.5.4. All fire and smoke wall penetrations will be closed with UL approved systems.
3.6. Pre-Government Testing
3.6.1. Conduct inspections and tests to ensure that devices and circuits are functioning properly.
Tests must meet the requirements of paragraph entitled "Minimum System Tests" as required by NFPA 72. The contractor and an authorized representative from each supplier of equipment must be in attendance at the pre-Government testing to make necessary adjustments. After inspection and testing is complete, provide a signed Verification of Compliant Installation letter by the QFPE that the installation is complete, compliant with the specification and fully operable. The letter must include the names and titles of the witnesses to the pre-Government tests. Provide all completion documentation as required by NFPA 72 including all referenced annex sections and the test reports.
3.6.2. When the verification of compliant installation has been completed, submit a formal request for Government final test to the Contracting Officer's Representative (COR).
Government final testing will not be scheduled until the DFPE has received copies of the request for Government final testing and Verification of Compliant Installation letter with all required reports. Government final testing will not be performed until after the connections to the installation-wide fire reporting system and the installation-wide mass notification system have been completed and tested to confirm communications are fully functional. Submit request for test at least 15 calendar days prior to the requested test date.
3.6.3. If equipment was found to be defective or non-compliant with contract requirements, perform corrective actions and repeat the tests. Tests must be conducted and repeated, if necessary, until the system has been demonstrated to comply with all contract requirements.
3.6.4. The tests must be performed in accordance with the approved test procedures in the presence of the DFPE. Furnish instruments and personnel required for the tests.
3.6.5. Contractor shall use UFGS 28 31 70 for all final testing requirements.
4. GOVERNMENT FURNISHED EQUIPMENT - None
5. GENERAL REQUIREMENTS
5.1. Contractor personnel and vehicles must possess appropriate passes. These shall be obtained from Installation Security Forces Pass and ID at the Vehicle Inspection Center.
5.2. The Contractor is subject to all installation fire, safety, security, and traffic regulations.
5.3. The Government contracts on the understanding that the Contractor is complying with applicable laws concerning workplace safety.
5.4. The Contractor is subject to all citations and penalties for violation of applicable workplace safety laws. The burden of compliance rests with the Contractor. Enforcement of workplace safety laws is the responsibility of the agency specified in the applicable law.
5.5. The Contracting Officer may notify the Contractor of hazards in Contractor operations that endanger Government personnel or property and require appropriate action. This provision does not constitute assumption of liability for Occupational Safety and Health compliance on the part of the Government or negate other agency responsibility for enforcement of applicable laws.
5.6. Accident prevention principles must be thoroughly integrated into all operations. Unsafe conditions and practices, as identified by the designated representative, must be corrected immediately.
5.7. Contractor Employees: While on the installation, the contractor shall not employ persons for work on this contract if such employee is identified to the contractor by the Contracting Officer as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population. Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the name of the organization or by wearing appropriate badges containing the organization's name and the employee's name. Contractor personnel must wear issued base identification cards at all times while on the installation.
5.8. Service contracts shall require contractor employees to identify themselves as contractor personnel by introducing themselves or being introduced as contractor personnel and displaying distinguishing badges or other visible identification for meetings with government personnel. In addition, contracts shall require contractor personnel to appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
6.0. WARRANTY
6.1. Contractor shall guarantee all material, workmanship, and labor from defects for a period of 1 year from the date of acceptance of the work.
7.0. APPENDIXES
Appendix A - Commander’s Environmental Policy Appendix B - UFGS 28 31 70 Appendix C - UFC 4-010-06 Appendix D – UFGS 25 05 11 Appendix E – UFC 3-600-01 Appendix F – Fire Protection Plan Appendix G – Fire Alarm Riser Plan Appendix H – Power Plan Appendix I – Mechanical Plan & Schedules
File details come from the government source that posted it. Updated .